Home / Browse projects / Pune, Maharashtra / DNYANADA CITY AND DNYANADA COMMERCIAL CENTER
DNYANADA CITY AND DNYANADA COMMERCIAL CENTER
RG-MH-24926 · RERA P52100009874 · Last updated on MahaRERA portal: 28 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 48 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DNYANADA CITY AND DNYANADA COMMERCIAL CENTER is a Others project by BHAGWAN NARAYAN POKHARKAR in Pune, Maharashtra, registered with MahaRERA as P52100009874 on 22 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing.
At a glance
Project
- NameDNYANADA CITY AND DNYANADA COMMERCIAL CENTER
- TypeOthers
- Location
- CHAKAN SHIKRAPUR ROAD
- CHAKAN
- Chakan (CT)
- Khed
- Pune
- 410501
- Pincode410501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100009874
- ReraGenie IDRG-MH-24926
Builder
- NameBHAGWAN NARAYAN POKHARKAR
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2023)
- Buildings5 building records
- Documents filed122 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 10 | 0 | 0 | 0 | 0 |
| E WING | NA | 9 | 0 | 0 | 0 | 0 |
| COMMERCIAL WING | NA | 6 | 0 | 0 | 0 | 0 |
| WING B | NA | 10 | 0 | 0 | 0 | 0 |
| WING C | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 28 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
33 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Installation of Lifts, at 95%.
A WING90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
E WING90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
COMMERCIAL WING90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
WING B67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
WING C37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 28 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 75% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | Yes | 80% |
| TEMPLE | Yes | 100% |
Parking filed300
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WING | 32 | 36 | 68 |
| E WING | 32 | 36 | 68 |
| COMMERCIAL WING | 63 | 70 | 133 |
| WING B | 1 | 0 | 1 |
| WING C | 30 | 0 | 30 |
Land and ownership10
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MR GULAB DAGDU JADHAV | Chakan (CT) | Pune |
| ANURADHA JADHAV | Chakan (CT) | Pune |
| AKASH BALU JADHAV | Chakan (CT) | Pune |
| GORAKH RAM JADHAV | Chakan (CT) | Pune |
| KERU NAMDEV JADHAV | Chakan (CT) | Pune |
| BALASAHEB GAVATE | Chakan (CT) | Pune |
| LAXMAN SOPAN GAVATE | Chakan (CT) | Pune |
| DATTATRAY RAM JADHAV | Chakan (CT) | Pune |
| SHANABAI RAM JADHAV | Chakan (CT) | Pune |
| AVINASH RAM JADHAV | Chakan (CT) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | WALHEKAR & ASSOCIATES |
| Engineer | AVINASH PANDHARI KOLEWAD |
| Engineer | MAYUR BADSHAHA GODASE |
| Chartered Accountant | SUNSVG & ASSOCIATES |
| Chartered Accountant | REET ANAND MEGHRAJANI |
| Partner | Role in project |
|---|---|
| BHAGWAN NARAYAN POKHARKAR | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWE HAVE GOTTEN REVISED CC AND BUILDING PLAN PERMISSION ON 07/02/2023 IN WHICH 3 MORE BUILDINGS ARE INCLUDED (AFFIDAVIT ATTACHED). NEED MORE TIME TO COMPLETE OHER 3 BUILDINGS.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Nov 2023
Documents filed122
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: form_1.pdf | 28 Apr 2026 |
| Form 2File: form_2__2_.pdf | 28 Apr 2026 |
| Form 3File: form_3__3__compressed.pdf | 28 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: sold_unsold__3__compressed.pdf | 28 Apr 2026 |
| Form 1File: form 1 (1).pdf | 23 Jan 2026 |
| Form 2File: form 2 (1).pdf | 23 Jan 2026 |
| Form 3File: form 3 (1) (1)_compressed.pdf | 23 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold_compressed.pdf | 23 Jan 2026 |
| Form 1File: FORM_1.pdf | 15 Oct 2025 |
| Form 2File: form_2.pdf | 15 Oct 2025 |
| Form 3File: Form-3.pdf | 15 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold_unsold_10_oct_2025_compressed.pdf | 15 Oct 2025 |
| Form 1File: FORM 1 DNYANADA.pdf | 6 Aug 2025 |
| Form 2File: form 2 DNYANADA.pdf | 6 Aug 2025 |
| Form 3File: form 3 DNYANADA.pdf | 6 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: DNYANADA SOL UNSOLD_compressed.pdf | 6 Aug 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 18 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 18 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 18 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 18 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 1.pdf | 18 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 18 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 18 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 16 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 16 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 16 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 16 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 16 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD A WING.pdf | 4 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD B WING.pdf | 4 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD C WING.pdf | 4 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD E WING.pdf | 4 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD COMMERCIAL_compressed.pdf | 4 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 16 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 16 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 16 Jul 2024 |
| Certificates of CA (Form 3)File: FORM 3_compressed (2).pdf | 26 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 3 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 3 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Adobe Scan Mar 28, 2024.pdf | 4 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD B WING.pdf | 23 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD C WING.pdf | 23 Nov 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: DOC-20230503-WA0028.pdf | 23 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21 22.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22 23.pdf | 12 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 10 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 5 FY 19 20.pdf | 10 Oct 2023 |
| Certificates of CA (Form 5)File: FORM 5 FY 17 18.pdf | 10 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 18 19.pdf | 10 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 19 20.pdf | 10 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dnyanada city.pdf | 13 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021 2022.pdf | 13 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022 2023.pdf | 13 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: A WING SOLD INVENTORY.pdf | 13 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: E WING SOLD INVENTORY.pdf | 13 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: COMMERCIAL SOLD INVENTORY.pdf | 13 Aug 2023 |
| Certificates of CA (Form 3)File: form 3_compressed.pdf | 13 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2021.pdf | 13 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 23.pdf | 13 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 dnyanada city.pdf | 2 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2122.pdf | 2 May 2023 |
| Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf | 2 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: discloser if intrest in other real estate organisations.pdf | 2 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: deviation letter.pdf | 2 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: deviation letter.pdf | 2 Mar 2023 |
| Building plan approvalFile: PLAN 1.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 2.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 3.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 4.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 5.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 6.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 7.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 8.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 9.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 10.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 11.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 12.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 13.pdf | 17 Feb 2023 |
| Building plan approvalFile: PLAN 14.pdf | 17 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 122 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DNYANADA CITY AND DNYANADA COMMERCIAL CENTER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHAKAN13,700+ in Pune
Filed coordinates, straight-line distance. 72 registered projects within 2 km.
DWARKA PROJECT3
NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD
SARA NILAAY
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C3
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C2
JAGRUTSARA STRUCTURES LLP
SARA SWAPNODAY
Jagrutsara Structures LLP
Aapla Ghar Moshi Annex Phase I
Maple Shelters Pvt. Ltd.
Builder: BHAGWAN NARAYAN POKHARKAR
BHAGWAN NARAYAN POKHARKAR has 1 registration on MahaRERA, including DNYANADA CITY AND DNYANADA COMMERCIAL CENTER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if DNYANADA CITY AND DNYANADA COMMERCIAL CENTER is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DNYANADA CITY AND DNYANADA COMMERCIAL CENTER?
The registered promoter entity is BHAGWAN NARAYAN POKHARKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DNYANADA CITY AND DNYANADA COMMERCIAL CENTER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DNYANADA CITY AND DNYANADA COMMERCIAL CENTER?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DNYANADA CITY AND DNYANADA COMMERCIAL CENTER?
The professionals named in the filing: Architect: WALHEKAR & ASSOCIATES; Engineer: AVINASH PANDHARI KOLEWAD; Engineer: MAYUR BADSHAHA GODASE; Chartered Accountant: SUNSVG & ASSOCIATES; Chartered Accountant: REET ANAND MEGHRAJANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DNYANADA CITY AND DNYANADA COMMERCIAL CENTER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback