Divine Paradise

By Rushikesh Bhaguji Zore

RG-MH-06177 · RERA P52000053553 · Last updated on MahaRERA portal: 4 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 16 months from the original
5 of 11Construction stages donefurthest along: Staircases, 64%
35 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

Divine Paradise is a Others project by Rushikesh Bhaguji Zore in Raigarh, Maharashtra, registered with MahaRERA as P52000053553 on 10 Nov 2023. Possession is promised by 30 Oct 2027. The completion date has moved by 16 months from the original filing. 21 of the 56 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameDivine Paradise
  • TypeOthers
  • Location
    • Sector No- 25A
    • Pushpak- Vahal
    • Wahal
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000053553
  • ReraGenie IDRG-MH-06177

Builder

  • NameRushikesh Bhaguji Zore
  • Entity typeIndividual
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredNov 2023First promiseJun 2026Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Nov 2023
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed97 files

Current status

38%21 of 56 units booked
35.2%Work done, per cost certificate

Figures as on 4 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Divine ParadiseNA8851556

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 64%.

Divine Paradise: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises17%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks64%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.36%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%

Progress on shared amenities15

As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered10
Open Space9

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area699 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
Nilesh Harishchandra KoliUlaweRaigarh
Hira Mahadeo KoliUlaweRaigarh
Ganesh Hira KoliUlaweRaigarh
Santosh Hira KoliUlaweRaigarh
Devendra Hira KoliUlaweRaigarh
Pandharinath Abhimanyu KoliUlaweRaigarh
Chandrakant Harishchandra KoliUlaweRaigarh

Approvals and building plan

Sanctioning authorityCity and Industrial Development Corporation of Maharashtra
Permissible FSI2400.0
Proposed, not sanctioned2,363 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShubh Arcade, Shop No 3,4,5, Plot No 22, Sector - 21, Kamothe, Navi Mumbai - 410206
Estimated costRs 5.61 cr
Cost incurredRs 1.97 cr
Work done35.16%
BuildingWingEstimatedIncurred
Divine ParadiseNARs 5.50 crRs 1.97 cr
-NARs 11.22 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Patel Architects
EngineerSK Consultants & Engineers
EngineerRushikesh Zore
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantPranav Bhaskaran & Associates
PartnerRole in project
Rushikesh Bhaguji Zore-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30062621625Jun 2026 → Oct 2027

Reason as filed by the promoterThe delay in completion of the project is primarily attributable to financial constraints faced by us, which affected the timely availability of funds required for execution of the balance works. The situation was further impacted by procurement-related challenges and unforeseen site conditions, resulting in delays in the progress of the project. We are actively arranging the necessary financial resources and expediting the remaining construction activities to ensure completion at the earliest. As certain balance works and statutory compliances are required to be completed prior to applying fo

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2027

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Mar 26 - DP.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 - Mar 26 - DP.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 - Mar 26 - DP.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 - Mar 26 - DP.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 - Mar 26 - DP.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 - Mar 26 - DP.pdf4 Aug 2026
Form 2A (FY 2023-2024)File: Form 2A (FY 2023-34).pdf4 Aug 2026
Form 2A (FY 2024-2025)File: Form 2A (FY 2024-25).pdf4 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf4 Aug 2026
Form 5 (FY 2024-2025)File: Form 5 (FY 2024-25).pdf4 Aug 2026
Form 1File: Form 1 - Divine Paradise as on March 2026.pdf20 May 2026
Form 2File: Form 2 - Divine Paradise as on March 2026.pdf20 May 2026
Form 3File: Form 3 - Divine Paradise as on March 2026.pdf20 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Divine Paradise as on March 2026.pdf20 May 2026
Form 1File: Form 1 of Divine Paradise as on 31-12-2025.pdf14 May 2026
Form 2File: Form 2 of Divine Paradise as on 31-12-2025.pdf14 May 2026
Form 3File: Form 3 of Divine Paradise as on 30-09-2025.pdf14 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - of Divine Paradise as on 31-12-2025.pdf14 May 2026
Form 1File: Form 1 of Divine Paradise as on 31-12-2025.pdf14 May 2026
Form 2File: Form 2 of Divine Paradise as on 31-12-2025.pdf14 May 2026
Form 3File: Form 3 of Divine Paradise as on 31-12-2025.pdf14 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - of Divine Paradise as on 31-12-2025.pdf14 May 2026
Form 1File: Form 1 - Divine Paradise as on June 2025.pdf9 Dec 2025
Form 2File: Form 2 - Divine Paradise as on June 2025.pdf9 Dec 2025
Form 3File: Form 3 - Divine Paradise as on June 2025.pdf9 Dec 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Divine Paradise as on June 2025.pdf9 Dec 2025
Form 1File: Form 1 - Divine Paradise as on March 2025.pdf1 Sep 2025
Form 2File: Form 2 - Divine Paradise as on March 2025.pdf1 Sep 2025
Form 3File: Form 3 - Divine Paradise as on March 2025.pdf1 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Divine Paradise as on March 2025.pdf1 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Paradise as on March 2025.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Paradise as on Dec 2024.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sep 2023.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2023.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Mar 2024.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Jun 2024.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Jun 2023.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2024_11zon.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2024_11zon.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Jun 2024_11zon.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Mar 2024_11zon.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2023_11zon.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2023_11zon.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Mar 2024_11zon.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Jun 2024_11zon.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sep 2024_11zon.pdf4 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2024_11zon.pdf4 Apr 2025
Disclosure of sold/ booked inventoryFile: Circular 29.pdf4 Apr 2025
Declaration about Commencement CertificateFile: Format D.pdf4 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 2023-24.pdf4 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24_11zon.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Paradise as on Sep 2024.pdf12 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Paradise as on Dec 2024.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Divine Paradise as on Sep 2024.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Divine Paradise as on Dec 2024.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Paradise as on Sep 2024.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Paradise as on Dec 2024.pdf12 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Divine Paradise FY 2023-24.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Divine Paradise FY 2023-24.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Paradise as on December 2023.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Paradise as on March 2024.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Paradise as on June 2024.pdf10 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Divine Paradise as on 31-12-2023.pdf10 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Divine Paradise as on 31-03-2024.pdf10 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Divine Paradise as on 30-06-2024.pdf10 Aug 2024
Layout approvalFile: Plan - Divine Paradise-1.pdf3 Aug 2024
Building plan approvalFile: Plan - Divine Paradise-2.pdf3 Aug 2024
Copy of Layout Approval (in case of layout)File: Plan - Divine Paradise-1.pdf3 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan - Divine Paradise-2.pdf3 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: CC - Divine Paradise.pdf3 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: 2 Declaration about Commencement Certificate.pdf23 Oct 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Letter- Finance.pdf21 Oct 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Letter- Legal.pdf21 Oct 2023
Details of encumbrances concerned to LegalFile: Encumbrance Letter- Finance.pdf21 Oct 2023
Details of encumbrances concerned to LegalFile: Encumbrance Letter- Legal.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: First Form 3 of Divine Paradise.pdf17 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A (2).pdf17 Oct 2023
Layout approvalFile: CC DRG - pg 1_11zon.pdf16 Oct 2023

How this compares with Raigarh

38%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 16 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Divine Paradise on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pushpak- Vahal5,900+ in Raigarh

2 kmDivine ParadiseCompleted 122Lapsed / revoked 37Other 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 265 registered projects within 2 km.

Builder: Rushikesh Bhaguji Zore

Rushikesh Bhaguji Zore has 4 registrations on MahaRERA, including Divine Residency and DIVINE PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Divine Paradise is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Divine Paradise?

The registered promoter entity is Rushikesh Bhaguji Zore, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Divine Paradise?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Divine Paradise?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Divine Paradise?

The professionals named in the filing: Architect: Atul Patel Architects; Engineer: SK Consultants & Engineers; Engineer: Rushikesh Zore; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Divine Paradise?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Divine Paradise. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Divine Paradise to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.