Home / Browse projects / Raigarh, Maharashtra / Divine Hill View
Divine Hill View
RG-MH-05466 · RERA P52000050970 · Last updated on MahaRERA portal: 2 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 17 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Divine Hill View is a Others project by Divine Enterprises in Raigarh, Maharashtra, registered with MahaRERA as P52000050970 on 16 May 2023. Possession is promised by 30 Sep 2027. The completion date has moved by 17 months from the original filing. 16 of the 43 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameDivine Hill View
- TypeOthers
- Location
- Sector No- 1
- Pushpak Node
- Panvel
- Vadghar (CT)
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000050970
- ReraGenie IDRG-MH-05466
Builder
- NameDivine Enterprises
- Entity typePartnership
- PartnersAkshay Sharad Nevase, Rushikesh Bhaguji Zore
- Other registrations2 more →
- No longer live1 lapsed, de-registered or revoked
- Past their filed date1
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 May 2023
- Promised completion30 Sep 2027
- Revised completionRevised to 30 Sep 2027 (originally 30 Apr 2026)
- Buildings1 building record
- Documents filed107 files
Current status
Figures as on 2 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Divine Hill View | NA | 8 | 8 | 36 | 7 | 43 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
Divine Hill View: 58% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mahesh Bharat Bhagat | Pargaon | Raigarh |
| Hirabai Bharat Bhagat | Pargaon | Raigarh |
| Ganesh Bharat Bhagat | Pargaon | Raigarh |
| Avinash Bharat Bhagat | Pargaon | Raigarh |
| Santosh Bharat Bhagat | Pargaon | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Divine Hill View | NA | Rs 4.39 cr | Rs 2.23 cr |
| - | NA | Rs 8.96 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Amit N Patil Architects |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | NB Sayed & Associates |
| Chartered Accountant | Pratiksha Tulshyan & Associates |
| Chartered Accountant | Vikas Abhang & Associates |
| Partner | Role in project |
|---|---|
| Divine Enterprises | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project progress was adversely affected due to unforeseen shortages of labour and essential construction materials, leading to reduced productivity and disruption of planned activities. Delays in material procurement and inconsistent availability of skilled manpower impacted the execution of critical tasks. Given the circumstances, we kindly request an extension until 30-09-2027, to complete the project and fulfil all regulatory requirements.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Apr 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Jun 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Sep 2027
Documents filed107
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: New Sanction Plan_smallpdf-pages-1.pdf | 2 Jun 2026 |
| Building plan approvalFile: New Sanction Plan_smallpdf-pages-2.pdf | 2 Jun 2026 |
| Building plan approvalFile: New Sanction Plan_smallpdf-pages-3.pdf | 2 Jun 2026 |
| Building plan approvalFile: New Sanction Plan_smallpdf-pages-4.pdf | 2 Jun 2026 |
| Declaration and undertaking (Annexure A)File: New Sanction Plan_smallpdf-pages-5.pdf | 2 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Divine Hill View as on 31-03-2026.pdf | 21 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Divine Hill View as on 31-03-2026.pdf | 21 May 2026 |
| Withdrawal Update Form 2File: Form 2 (March 26).pdf | 21 May 2026 |
| Withdrawal Update Form 2File: Form 2 (March 26).pdf | 21 May 2026 |
| Withdrawal Update Form 3File: Form 3 (March 26).pdf | 21 May 2026 |
| Withdrawal Update Form 3File: Form 3 (March 26).pdf | 21 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Divine Hill View as on 31-03-2026.pdf | 20 May 2026 |
| Withdrawal Update Form 2File: Form 2 (March 26).pdf | 20 May 2026 |
| Withdrawal Update Form 3File: Form 3 (March 26).pdf | 20 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Divine Hill view as on June 2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Divine Hill View as on Dec 2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Divine Hill View as on Dec 2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Divine Hill View as on June 2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Divine Hill View as on 30-09-2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Divine Hill View as on 31-12-2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Divine Hill View as on June 2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Divine Hill View as on 30-09-2025.pdf | 14 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Divine Hill View as on 31-12-2025.pdf | 14 Apr 2026 |
| Form 5 (FY 2023-2024)File: Form 5 - Divine Hill View for FY 2023-24.pdf | 4 Oct 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 Divine Hill View FY 24-25.pdf | 4 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Hill View as on March 2025.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Hill View as on Dec 2024.pdf | 9 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 2024 Divine Hill View_compressed.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2024 Divine Hill View_compressed.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sept 2024 Divine Hill View_compressed.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2024 Divine Hill View_compressed.pdf | 29 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Dec 2024 Divine Hill View.pdf | 29 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Divine Hill View.pdf | 29 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2023-24) Divine Hill View.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Divine Hill View as on Dec 2024.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Hill View as on Dec 2024.pdf | 17 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Hill View.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Divine Hill View as on Sep 2024.pdf | 29 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Hill View as on Sep 2024.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 March 23.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 June 23.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 Sep 23.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 Dec 23.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 March 24.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 June 24.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Divine Hill View Form 1 Sep 24.pdf | 5 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Divine Hill View for FY 2023-24.pdf | 5 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 JUNE 23.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Sep 23.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Dec 23.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Mar 24.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 JUNE 24.pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2023.pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 2023.pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Dec 23.pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - March 2024.pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 JUNE 24.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Hill View as on June 2024.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Divine Hill View as on 30-06-2024.pdf | 18 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Divine Hill View as on June 2024.pdf | 4 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 2023.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - June 2023.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sept 2023.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2023.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - March 2024.pdf | 25 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - June 2023.pdf | 25 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Fom 2 - Sept 2023.pdf | 25 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2023.pdf | 25 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - March 2024.pdf | 25 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2023.pdf | 25 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sept 2023.pdf | 25 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2023.pdf | 25 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - March 2024.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan - Divine Hill view.pdf | 17 Apr 2024 |
| Layout approvalFile: Plan - Divine Hill view.pdf | 17 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: Plan - Divine Hill view.pdf | 17 Apr 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan - Divine Hill view.pdf | 17 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 17 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Hill View as on 30th September 2023.pdf | 17 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Divine Hill View as on 30th June 2023.pdf | 17 Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 107 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Divine Hill View on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pushpak Node ,Panvel5,900+ in Raigarh
Filed coordinates, straight-line distance. 320 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: Divine Enterprises
DIVINE ENTERPRISES has 3 registrations on MahaRERA, including DIVINE PATH and Richmond Ananya. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Divine Hill View is delayed beyond 30 Sep 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Divine Hill View?
The registered promoter entity is Divine Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Divine Hill View?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Divine Hill View?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Divine Hill View?
The professionals named in the filing: Architect: Amit N Patil Architects; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Pratiksha Tulshyan & Associates; Chartered Accountant: Vikas Abhang & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Divine Hill View?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback