Home / Browse projects / Raigarh, Maharashtra / DHRITI HOMES

Completed No litigation declared Others project

DHRITI HOMES

By DHRITI HOME MAKERS LLP

RG-MH-98752 · RERA P52000047002 · Last updated on MahaRERA portal: 14 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Installation of Lifts, 83%
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

DHRITI HOMES is a Others project by DHRITI HOME MAKERS LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000047002 on 26 Sep 2022. The registration is recorded completed; possession was promised by 31 Dec 2025.

At a glance

Project

  • NameDHRITI HOMES
  • TypeOthers
  • Location
    • PUSHPAK NODE
    • SECTOR 07
    • Dapoli
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000047002
  • ReraGenie IDRG-MH-98752

Builder

  • NameDHRITI HOME MAKERS LLP
  • Entity typePartnership
  • PartnersKAUSHIK MULCHAND SHAH, RAJESH DHANJI CHOUDHARY, PRAKASHKUMAR DEVA DUBARIYA

Key dates

this monthRegisteredSep 2022PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on26 Sep 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DHRITI HOMESNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 83%.

DHRITI HOMES: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.83%

Progress on shared amenities15

As on 14 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area810 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3168.06
Proposed, not sanctioned1,210 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKRISHNA KAMAL CHS,SEC-21,NERUL,NAVI MUMBAI-400706

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL
EngineerS R CONSULTANTSS
Chartered AccountantKETAN RUPANI
PartnerRole in project
DHRITI HOME MAKERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Oct 2024

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final form 3.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 june2024_.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 oc_.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM-1.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Form 1.pdf28 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4_.pdf28 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Dhriti Home Makers LLP____.pdf23 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC copy.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_signed.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 41B-7-PUSHPAK RERA (2024 MARCH).pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PLOT NO 41B SECTOR NO 07 PUSHPAK DAPOLI FORM 2 RERA.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 with sign.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: final form 3.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 41B-7-PUSHPAK RERA (2023 SEPTEMBER).pdf18 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 with sign.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf28 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf1 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf1 Feb 2023
Layout approvalFile: Layout Plan.pdf19 Oct 2022
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf19 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC Copy.pdf19 Oct 2022
Declaration about Commencement CertificateFile: Declartion Of CC.pdf19 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dhriti Home Makers (1).pdf19 Oct 2022
Proforma of Allotment letterFile: FINAL DRAFT AGREEMENT DHRITI HOMES (2).pdf19 Oct 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Of AFS.pdf19 Oct 2022
PAN CardFile: PAN CARD COMPANY.pdf19 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declartaion of Separate bank.pdf19 Aug 2022
Building plan approvalFile: Layout plan-2.pdf17 Aug 2022
Details of encumbrances concerned to LegalFile: Declaration to Encumbrance legal.pdf17 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Layout plan-2.pdf17 Aug 2022
Proforma of Allotment letterFile: Draft Agreement For sale.pdf17 Aug 2022
Proforma of Allotment letterFile: DRAFT OF ALLOTMENT LETTER.pdf17 Aug 2022
Deviation Report with respect to Allotment letterFile: Deviation to Allotment letter.pdf17 Aug 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Of AFS.pdf17 Aug 2022
Layout approvalFile: Layout Plan-1.pdf12 Aug 2022
Copy of the legal title reportFile: legal titile report.pdf12 Aug 2022
Details of encumbrances concerned to FinanceFile: FORMAT OF ENCUMBRANCES LETTER.PDF12 Aug 2022
Copy of Layout Approval (in case of layout)File: Layout Plan-1.pdf12 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf12 Aug 2022
Declaration about Commencement CertificateFile: Declaration Commecement Certificate.PDF12 Aug 2022
Declaration in FORM BFile: FORM B.pdf12 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf12 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf12 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report_200244635218_For_Asset_Based_Search_12_08_2022_16_32_40_670.pdf12 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf12 Aug 2022

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DHRITI HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SECTOR 075,900+ in Raigarh

Builder: DHRITI HOME MAKERS LLP

DHRITI HOME MAKERS LLP has 1 registration on MahaRERA, including DHRITI HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if DHRITI HOMES is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DHRITI HOMES?

The registered promoter entity is DHRITI HOME MAKERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DHRITI HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DHRITI HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DHRITI HOMES?

The professionals named in the filing: Architect: ATUL PATEL; Engineer: S R CONSULTANTSS; Chartered Accountant: KETAN RUPANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DHRITI HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DHRITI HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DHRITI HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.