Home / Browse projects / Palghar, Maharashtra / DHARTI COMPLEX
DHARTI COMPLEX
RG-MH-66705 · RERA P99000012496 · Last updated on MahaRERA portal: 8 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 54 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DHARTI COMPLEX is a Residential / Group Housing project by DHARTI BUILDWELL in Palghar, Maharashtra, registered with MahaRERA as P99000012496 on 1 Sep 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameDHARTI COMPLEX
- TypeResidential / Group Housing
- Location
- varangade
- Palghar
- 401501
- Pincode401501
- RERA no.P99000012496
- ReraGenie IDRG-MH-66705
Builder
- NameDHARTI BUILDWELL
- Entity typePartnership
- PartnersSanjay Sahabal Yadav, Dhiraj Ramkelavan yadav, Ashish Satyanarayan Yadav
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2021)
- Buildings6 building records
- Documents filed56 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DHARTI COMPLEX WING A BLDG-6 | NA | 5 | 0 | 0 | 0 | 0 |
| DHARTI COMPLEX WING B BLDG-5 | NA | 5 | 0 | 0 | 0 | 0 |
| DHARTI COMPLEX WING C BLDG 4 | NA | 5 | 0 | 0 | 0 | 0 |
| DHARTI COMPLEX WING D BLDG 3 | NA | 3 | 0 | 0 | 0 | 0 |
| DHARTI COMLEX WING E BLDG 2 | NA | 5 | 0 | 0 | 0 | 0 |
| DHARTI COMPLEX WING F BLDG 1 | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 8 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
48 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 90%.
DHARTI COMPLEX WING A BLDG-681%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DHARTI COMPLEX WING B BLDG-581%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DHARTI COMPLEX WING C BLDG 481%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DHARTI COMPLEX WING D BLDG 381%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DHARTI COMLEX WING E BLDG 281%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
DHARTI COMPLEX WING F BLDG 181%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 8 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 98% |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| DHARTI COMPLEX WING A BLDG-6 | 1 | 1 |
| DHARTI COMPLEX WING B BLDG-5 | 1 | 1 |
| DHARTI COMPLEX WING C BLDG 4 | 1 | 1 |
| DHARTI COMLEX WING E BLDG 2 | 1 | 1 |
| DHARTI COMPLEX WING F BLDG 1 | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHANTANU RAJARAM VICHARE |
| Engineer | SALLEM BOOTWALA |
| Partner | Role in project |
|---|---|
| DHARTI BUILDWELL | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. COVID PENDEMIC 2. UNAVAILABILITY OF LABOUR 3. SHORTAGE OF SAND SUPPLY DUE TO COVID. 4. SHORTAGE OF BRICK SUPPLY DUE TO LESS PRODUCTION OF BRICKS WHICH IS AFFECTED BY COVID.
Reason as filed by the promoter1) Delay in construction work due to local issues (Monopoly of material supply at unaffordable rate by the villagers and creating raucous and frightened the site labors causing no labor interested to come and work on site.)
Reason as filed by the promoter1. local supplier issue/monopoly of material supplier , timely not available material 2. locals contractors monopoly of various works due to which quality get affected sometimes few works nee repairs or recast .
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400780 | Gulab Vishwanath Yadav | DHARTI BUILDWELL | 15/11/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed56
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf | 8 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM NO 2 A.pdf | 7 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 ( UT ) .pdf | 7 Jan 2025 |
| Declaration in FORM BFile: Form B.pdf | 3 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From 1 .pdf | 3 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ( From -2 ) ENGINEER’S CERTIFICATE.pdf | 3 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From 1 .pdf | 28 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ( From -2 )ENGINEER’S CERTIFICATE.pdf | 28 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold Booked inventory .pdf | 28 Jul 2023 |
| Certificates of CA (Form 3)File: From 3.pdf | 28 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: From 5 .pdf | 28 Jul 2023 |
| Declaration in FORM BFile: From b.pdf | 26 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FROM 2A.pdf | 26 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold AND Unsold Unit.pdf | 15 May 2023 |
| Other - TechnicalFile: Activity - Task in Progress .pdf | 15 May 2023 |
| Declaration in FORM BFile: Form B Affidavit.pdf | 28 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf | 14 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form No 2A FINAL.pdf | 31 Jan 2023 |
| Declaration about Commencement CertificateFile: FORMAT-D.pdf | 24 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From_1.pdf | 24 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure_of_Sold_-_Booked_Inventory_.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: From_3.pdf | 24 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form_5.pdf | 24 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances.pdf | 25 Dec 2022 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances.pdf | 25 Dec 2022 |
| Declaration about Commencement CertificateFile: Declaration Certificate(1) .pdf | 25 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No 1.pdf | 25 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2.pdf | 25 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate(8).pdf | 25 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Sold List Dharti Complex (10).pdf | 25 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Unsold Unit Dharti Complex (9).pdf | 25 Dec 2022 |
| Certificates of CA (Form 3)File: From No-3.pdf | 25 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Rera Documents No 5(6).pdf | 25 Dec 2022 |
| Proforma of Agreement for saleFile: Agreement of SALE Draft.pdf | 25 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A 2020-21 FINAL.pdf | 25 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A FINAL 2019-20 FINAL.pdf | 9 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A FINAL.pdf | 9 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: DC SOLD INVENTORY.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM-5 DHARTI COMPLEX 17-18.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 DHARTI COMPLEX 18-19.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 DHARTI COMPLEX 19-20.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 DHARTI COMPLEX 20-21.pdf | 28 Jun 2021 |
| Proforma of Allotment letterFile: Dharti Complex RERA_FINAL_FORMAT Final.pdf | 30 Oct 2017 |
| Certificates of CA (Form 3)File: FORM-3 CA Certificate DB.pdf | 31 Jul 2017 |
| Building plan approvalFile: Building Plan.pdf | 30 Jul 2017 |
| Layout approvalFile: Layout.pdf | 30 Jul 2017 |
| PAN CardFile: DB pan card.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: title and search report DB.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: SELF DEC FOR ENCUM.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc and na DB.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: Form-B, DC.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 DC FINAL.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 Engineer_certificate_DB_Final.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: AFFIDAVIT FOR SALE AGREEMENT DC.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- All 56 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep DHARTI COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near varangade3,200+ in Palghar
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: DHARTI BUILDWELL
DHARTI BUILDWELL has 1 registration on MahaRERA, including DHARTI COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that DHARTI COMPLEX shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DHARTI COMPLEX is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DHARTI COMPLEX?
The registered promoter entity is DHARTI BUILDWELL, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DHARTI COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DHARTI COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DHARTI COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DHARTI COMPLEX?
The professionals named in the filing: Architect: SHANTANU RAJARAM VICHARE; Engineer: SALLEM BOOTWALA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DHARTI COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback