ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / DGS HEIGHTS

Registered No litigation declared Residential / Group Housing project

DGS HEIGHTS

By D.G.BUILDERS

RG-MH-00293 · RERA P51800000052 · Last updated on MahaRERA portal: 1 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 96 months
  • 6 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 96 months from the original
5 of 11Construction stages donefurthest along: Staircases, 25%
2 of 33Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

DGS HEIGHTS is a Residential / Group Housing project by D.G.BUILDERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000052 on 19 Jun 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 96 months from the original filing. 31 of the 33 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameDGS HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • AAREY ROAD
    • GOREGAON EAST
    • Borivali
    • Mumbai Suburban
    • 400063
  • Pincode400063
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000052
  • ReraGenie IDRG-MH-00293

Builder

  • NameD.G.BUILDERS
  • Entity typePartnership
  • PartnersISHWARDEV DUDHNATH SHUKLA, SURAJDEV DUDHNATH SHUKLA

Key dates

this monthRegisteredJun 2017First promiseDec 2018Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Jun 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed88 files

Current status

94%31 of 33 units booked
91.5%Work done, per cost certificate

Figures as on 1 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHEETAL VILLANA20029433

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 25%.

SHEETAL VILLA: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area864 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMuncipal Corporation Greater Mumbai
Permissible FSI2084.0
Proposed, not sanctioned1,384 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOREGAON EAST MUMBAI 400063
Estimated costRs 68.34 cr
Cost incurredRs 62.51 cr
Work done91.47%
BuildingWingEstimatedIncurred
SHEETAL VILLANARs 34.17 crRs 31.26 cr
-NARs 34.17 crRs 31.26 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJIT J UDANI J UDANI
EngineerHIREN TANNA
Chartered AccountantMs Vinay Tiwari & Associates
PartnerRole in project
D.G.BUILDERS-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005672Dec 2018 → Apr 2020

Reason as filed by the promoterTo, The Maharera, SRA Building , Bandra (East), Mumbai Subject : Extension of Project Completion date u/s 7(3) of the act Project Registration Number - P5180000052 Project Name : DGS Heights SRO registration number - RPM/M/NR518000133 - NAREDCO Respected Sir, Find Enclosed herewith resolution of Purchasers/alottees of premises for extension of project completion date We have Completed Ground plus 1 floor and with obtaining of Part OC we have handed over possession to shop Purchasers allottees. Total number of Purchasers / allottees : 22 no`s Number of allottees resolved to extend date : 16 no`

EXT51800001437Dec 2018 → Apr 2020

Reason as filed by the promoterTo, The Maharera, SRA Building , Anant Kanekar Marg, Bandra East, Mumbai Subject : Application for extension of project Completion Date Project Registration No : P51800000052 Project : DGS HEIGHT Sir, We are registered under above mentioned number and seek extension of project completion date on following grounds. Facts : Project Applied : July 2017 Captioned project is a single building project and were projected for 18 super slabs. Expenses Made : Met within budget . A copy of revised from 3 is uploaded. Completed : We have completed construction of premises up to 10 super slabs are awaiting

EXT51800012804Dec 2018 → Mar 2023

Reason as filed by the promoterDUE TO SECOND WAVE OF LOCK DOWN

EXT51800009743Dec 2018 → Dec 2021

Reason as filed by the promoterAPPLICATION FOR EXTENSION OF PROJECT COMPLETION DATE U/S 7(3) (FORMAT -B) (Circular No 28-2021 date 8/3/2021) Date : June 2, 2021.. To, TheHon`ble Competent Authorities, Real Estate Regulation and Development Act 2016 MAHARERA, SRA Building, Anant Kanekar Marg, Mumbai Subject : Extension of Project U/s 7(3) of the Act of project registration number P51800000052 - Project name “ DGS HEIGHTS “ Dear Sir, Captioned project is a redevelopment project. Old occupants are rehabilitated in new building and balance premises are eligible for sale. Captioned project has completed its major part of constru

EXT51800017567Dec 2018 → Dec 2024

Reason as filed by the promoterwe are under process of getting full occupancy certificate we need extension till 31 dec 2024

EA27122519046Dec 2018 → Dec 2026

Reason as filed by the promoterDelay in government approvals

Litigation declared1

CaseCourtStatus
1820/2015CITY CIVIL COURT DINDOSHIDisposed off

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500256Chandrakala Rajeshkumar NairD.G.BUILDERS24/01/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Jun 2021

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 March-25 Villa (1).pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1 March-25 Villa (1).pdf1 Jun 2026
Withdrawal Update Form 1File: Form 1 30-06-25.pdf1 Jun 2026
Withdrawal Update Form 1File: Form 1 30-09-25.pdf1 Jun 2026
Withdrawal Update Form 1File: Form 1 30-12-25.pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-March-26-Height (2).pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-March-25 (3).pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-March-25 (3).pdf1 Jun 2026
Withdrawal Update Form 2File: Form 2 30-06-25.pdf1 Jun 2026
Withdrawal Update Form 2File: Form 2 30-09-25.pdf1 Jun 2026
Withdrawal Update Form 2File: Form 2 30-12-25.pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-MArch-26 (1).pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3- March-25 (1).pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3- March-25 (1).pdf1 Jun 2026
Withdrawal Update Form 3File: Form 3 30-06-25.pdf1 Jun 2026
Withdrawal Update Form 3File: Form 3 30-09-25.pdf1 Jun 2026
Withdrawal Update Form 3File: Form 3 30-12-25.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3-March-26 (1).pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-March-26-Height.pdf29 May 2026
Withdrawal Update Form 2File: Form-2-MArch-26.pdf29 May 2026
Withdrawal Update Form 3File: Form-3-March-26.pdf29 May 2026
Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf24 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf24 Jan 2026
Form 5 (FY 2022-2023)File: Form 5-Height-22-23.pdf24 Jan 2026
Form 5 (FY 2023-2024)File: Form 5-Height-23-24.pdf24 Jan 2026
Form 5 (FY 2024-2025)File: Form 5-Height-24-25.pdf24 Jan 2026
Form 1File: Form-1 March-25 Villa.pdf25 Nov 2025
Form 2File: Form-2-March-25.pdf25 Nov 2025
Form 3File: Form-3- March-25.pdf25 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ Unsold.pdf25 Nov 2025
Form 1File: Form-1 March-25 Villa.pdf25 Nov 2025
Form 2File: Form-2-March-25.pdf25 Nov 2025
Form 3File: Form-3- March-25.pdf25 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ Unsold.pdf25 Nov 2025
Declaration in FORM BFile: DEclaration Form-B_001.pdf12 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 NEW.pdf12 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Villa Form 2 NEW.pdf12 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) _1 (2 files merged).pdf12 Sep 2023
Disclosure of sold/ booked inventoryFile: 2 Disclosure of sold_ booked inventory_1 (2 files merged).pdf12 Sep 2023
Certificates of CA (Form 3)File: Villa Form 3 NEW.pdf12 Sep 2023
Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf12 Sep 2023
Details of encumbrances concerned to FinanceFile: No encumbrances Certificate LEGAL.pdf4 Jan 2023
Details of encumbrances concerned to LegalFile: No encumbrances Certificate LEGAL.pdf4 Jan 2023
Declaration about Commencement CertificateFile: declaration about comm cert.pdf4 Jan 2023
Declaration in FORM BFile: FORM B DGS HEIGHTS.pdf4 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: fORM 2A 2019-2020.pdf4 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla (7).pdf4 Jan 2023
Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf4 Jan 2023
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf4 Jan 2023
Certificates of CA (Form 3)File: Form-3-21-22.pdf24 Nov 2022
Certificates of CA (Form 3)File: FORM-3 DGS-F.pdf24 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance.pdf18 Nov 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold -Booked Inventory.pdf18 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf18 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: villa form-5 - 2020-2021.pdf7 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: villa form-5 - 2019-2020.pdf7 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: villa form-5 - 2020-2021.pdf7 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC-19 FLOORS.pdf3 Jun 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD ON 31-3-2021.pdf3 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VILLA OC G PLUS 1.pdf3 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: combinepdf_compressed (1).pdf4 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 VILLA 31-3-2019.pdf22 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: Villa CC.pdf18 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Villa-Form-no-2.pdf18 Oct 2019
Certificates of CA (Form 3)File: Form-3-Villa-31-3-2019.pdf18 Oct 2019
Certificates of CA (Form 3)File: Villa stock statement.pdf18 Oct 2019
Certificates of CA (Form 5)File: Villa-Form-5-31-3-2019.pdf18 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Villa - Architect ceritifcate - 08-02-2019.pdf8 Feb 2019
Certificates of CA (Form 5)File: Villa-Form-5-31-3-2018.pdf30 Sep 2018
Details of encumbrancesFile: Villa-revised-Encumb-cert.pdf11 Aug 2017
OtherFile: VILLA-CHANGE-OF-NAME-OF-PROJECT.pdf11 Aug 2017
Layout approvalFile: 30-3-2017-plan-approved-for-10-floors OG_Page_1.pdf16 Jun 2017
Building plan approvalFile: ramballi-iod-compressed.pdf16 Jun 2017
Layout approvalFile: 30-3-2017-plan-approved-for-10-floors_Page_2.pdf16 Jun 2017
Layout approvalFile: 30-3-2017-plan-approved-for-10-floors_Page_3.pdf16 Jun 2017
Copy of Layout Approval (in case of layout)File: 30-3-2017-plan-approved-for-10-floors OG_Page_1.pdf16 Jun 2017
Copy of Layout Approval (in case of layout)File: 30-3-2017-plan-approved-for-10-floors_Page_2.pdf16 Jun 2017
Copy of Layout Approval (in case of layout)File: 30-3-2017-plan-approved-for-10-floors_Page_3.pdf16 Jun 2017
Building Plan Approval (IOD)File: ramballi-iod-compressed.pdf16 Jun 2017
Copy of the legal title reportFile: villa title certificate-compress scan.pdf14 Jun 2017

How this compares with Mumbai Suburban

94%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 96 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DGS HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOREGAON EAST6,700+ in Mumbai Suburban

2 kmDGS HEIGHTSCompleted 144Lapsed / revoked 71Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 348 registered projects within 2 km.

Builder: D.G.BUILDERS

D.G.BUILDERS has 1 registration on MahaRERA, including DGS HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if DGS HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DGS HEIGHTS?

The registered promoter entity is D.G.BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DGS HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DGS HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DGS HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DGS HEIGHTS?

The professionals named in the filing: Architect: ABHIJIT J UDANI J UDANI; Engineer: HIREN TANNA; Chartered Accountant: Ms Vinay Tiwari & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DGS HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DGS HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DGS HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.