Home / Browse projects / Mumbai Suburban, Maharashtra / DGS HEIGHTS
DGS HEIGHTS
By D.G.BUILDERS
RG-MH-00293 · RERA P51800000052 · Last updated on MahaRERA portal: 1 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 96 months
- 6 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DGS HEIGHTS is a Residential / Group Housing project by D.G.BUILDERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000052 on 19 Jun 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 96 months from the original filing. 31 of the 33 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameDGS HEIGHTS
- TypeResidential / Group Housing
- Location
- AAREY ROAD
- GOREGAON EAST
- Borivali
- Mumbai Suburban
- 400063
- Pincode400063
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800000052
- ReraGenie IDRG-MH-00293
Builder
- NameD.G.BUILDERS
- Entity typePartnership
- PartnersISHWARDEV DUDHNATH SHUKLA, SURAJDEV DUDHNATH SHUKLA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Jun 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2018)
- Buildings1 building record
- Documents filed88 files
Current status
Figures as on 1 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHEETAL VILLA | NA | 20 | 0 | 29 | 4 | 33 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 25%.
SHEETAL VILLA: 50% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 7% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 5% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHEETAL VILLA | NA | Rs 34.17 cr | Rs 31.26 cr |
| - | NA | Rs 34.17 cr | Rs 31.26 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ABHIJIT J UDANI J UDANI |
| Engineer | HIREN TANNA |
| Chartered Accountant | Ms Vinay Tiwari & Associates |
| Partner | Role in project |
|---|---|
| D.G.BUILDERS | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo, The Maharera, SRA Building , Bandra (East), Mumbai Subject : Extension of Project Completion date u/s 7(3) of the act Project Registration Number - P5180000052 Project Name : DGS Heights SRO registration number - RPM/M/NR518000133 - NAREDCO Respected Sir, Find Enclosed herewith resolution of Purchasers/alottees of premises for extension of project completion date We have Completed Ground plus 1 floor and with obtaining of Part OC we have handed over possession to shop Purchasers allottees. Total number of Purchasers / allottees : 22 no`s Number of allottees resolved to extend date : 16 no`
Reason as filed by the promoterTo, The Maharera, SRA Building , Anant Kanekar Marg, Bandra East, Mumbai Subject : Application for extension of project Completion Date Project Registration No : P51800000052 Project : DGS HEIGHT Sir, We are registered under above mentioned number and seek extension of project completion date on following grounds. Facts : Project Applied : July 2017 Captioned project is a single building project and were projected for 18 super slabs. Expenses Made : Met within budget . A copy of revised from 3 is uploaded. Completed : We have completed construction of premises up to 10 super slabs are awaiting
Reason as filed by the promoterDUE TO SECOND WAVE OF LOCK DOWN
Reason as filed by the promoterAPPLICATION FOR EXTENSION OF PROJECT COMPLETION DATE U/S 7(3) (FORMAT -B) (Circular No 28-2021 date 8/3/2021) Date : June 2, 2021.. To, TheHon`ble Competent Authorities, Real Estate Regulation and Development Act 2016 MAHARERA, SRA Building, Anant Kanekar Marg, Mumbai Subject : Extension of Project U/s 7(3) of the Act of project registration number P51800000052 - Project name “ DGS HEIGHTS “ Dear Sir, Captioned project is a redevelopment project. Old occupants are rehabilitated in new building and balance premises are eligible for sale. Captioned project has completed its major part of constru
Reason as filed by the promoterwe are under process of getting full occupancy certificate we need extension till 31 dec 2024
Reason as filed by the promoterDelay in government approvals
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1820/2015 | CITY CIVIL COURT DINDOSHI | Disposed off |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500256 | Chandrakala Rajeshkumar Nair | D.G.BUILDERS | 24/01/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jun 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jun 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Jun 2021
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1 March-25 Villa (1).pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Form-1 March-25 Villa (1).pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 30-06-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 30-09-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 30-12-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Form-1-March-26-Height (2).pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Form-2-March-25 (3).pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Form-2-March-25 (3).pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 30-06-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 30-09-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 30-12-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Form-2-MArch-26 (1).pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Form-3- March-25 (1).pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Form-3- March-25 (1).pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 30-06-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 30-09-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 30-12-25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Form-3-March-26 (1).pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Form-1-March-26-Height.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: Form-2-MArch-26.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: Form-3-March-26.pdf | 29 May 2026 |
| Form 2A (FY 2023-2024)File: Form 2A 2023-24.pdf | 24 Jan 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf | 24 Jan 2026 |
| Form 5 (FY 2022-2023)File: Form 5-Height-22-23.pdf | 24 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5-Height-23-24.pdf | 24 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5-Height-24-25.pdf | 24 Jan 2026 |
| Form 1File: Form-1 March-25 Villa.pdf | 25 Nov 2025 |
| Form 2File: Form-2-March-25.pdf | 25 Nov 2025 |
| Form 3File: Form-3- March-25.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ Unsold.pdf | 25 Nov 2025 |
| Form 1File: Form-1 March-25 Villa.pdf | 25 Nov 2025 |
| Form 2File: Form-2-March-25.pdf | 25 Nov 2025 |
| Form 3File: Form-3- March-25.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ Unsold.pdf | 25 Nov 2025 |
| Declaration in FORM BFile: DEclaration Form-B_001.pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 NEW.pdf | 12 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Villa Form 2 NEW.pdf | 12 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) _1 (2 files merged).pdf | 12 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: 2 Disclosure of sold_ booked inventory_1 (2 files merged).pdf | 12 Sep 2023 |
| Certificates of CA (Form 3)File: Villa Form 3 NEW.pdf | 12 Sep 2023 |
| Proforma of Agreement for saleFile: 1 Proforma of Allotment letter.pdf | 12 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: No encumbrances Certificate LEGAL.pdf | 4 Jan 2023 |
| Details of encumbrances concerned to LegalFile: No encumbrances Certificate LEGAL.pdf | 4 Jan 2023 |
| Declaration about Commencement CertificateFile: declaration about comm cert.pdf | 4 Jan 2023 |
| Declaration in FORM BFile: FORM B DGS HEIGHTS.pdf | 4 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: fORM 2A 2019-2020.pdf | 4 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla (7).pdf | 4 Jan 2023 |
| Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf | 4 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf | 4 Jan 2023 |
| Certificates of CA (Form 3)File: Form-3-21-22.pdf | 24 Nov 2022 |
| Certificates of CA (Form 3)File: FORM-3 DGS-F.pdf | 24 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance.pdf | 18 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold -Booked Inventory.pdf | 18 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 18 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: villa form-5 - 2020-2021.pdf | 7 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: villa form-5 - 2019-2020.pdf | 7 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: villa form-5 - 2020-2021.pdf | 7 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-19 FLOORS.pdf | 3 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD ON 31-3-2021.pdf | 3 Jun 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VILLA OC G PLUS 1.pdf | 3 Jun 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: combinepdf_compressed (1).pdf | 4 Feb 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 VILLA 31-3-2019.pdf | 22 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Villa CC.pdf | 18 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Villa-Form-no-2.pdf | 18 Oct 2019 |
| Certificates of CA (Form 3)File: Form-3-Villa-31-3-2019.pdf | 18 Oct 2019 |
| Certificates of CA (Form 3)File: Villa stock statement.pdf | 18 Oct 2019 |
| Certificates of CA (Form 5)File: Villa-Form-5-31-3-2019.pdf | 18 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Villa - Architect ceritifcate - 08-02-2019.pdf | 8 Feb 2019 |
| Certificates of CA (Form 5)File: Villa-Form-5-31-3-2018.pdf | 30 Sep 2018 |
| Details of encumbrancesFile: Villa-revised-Encumb-cert.pdf | 11 Aug 2017 |
| OtherFile: VILLA-CHANGE-OF-NAME-OF-PROJECT.pdf | 11 Aug 2017 |
| Layout approvalFile: 30-3-2017-plan-approved-for-10-floors OG_Page_1.pdf | 16 Jun 2017 |
| Building plan approvalFile: ramballi-iod-compressed.pdf | 16 Jun 2017 |
| Layout approvalFile: 30-3-2017-plan-approved-for-10-floors_Page_2.pdf | 16 Jun 2017 |
| Layout approvalFile: 30-3-2017-plan-approved-for-10-floors_Page_3.pdf | 16 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: 30-3-2017-plan-approved-for-10-floors OG_Page_1.pdf | 16 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: 30-3-2017-plan-approved-for-10-floors_Page_2.pdf | 16 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: 30-3-2017-plan-approved-for-10-floors_Page_3.pdf | 16 Jun 2017 |
| Building Plan Approval (IOD)File: ramballi-iod-compressed.pdf | 16 Jun 2017 |
| Copy of the legal title reportFile: villa title certificate-compress scan.pdf | 14 Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DGS HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GOREGAON EAST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 348 registered projects within 2 km.
Elysian Tower C, D, E
Oberoi Realty Limited
Elysian Tower B
Oberoi Realty Limited
Elysian Tower A
Oberoi Realty Limited
Sheetal Sangam
DGS Township Pvt Ltd
SEJAL SQUARE
ALCHEMI DEVELOPERS PRIVATE LIMITED
Mehta Marquina 1978
Shreeram Builders
See every Mumbai Suburban project, with the district possession charts
Builder: D.G.BUILDERS
D.G.BUILDERS has 1 registration on MahaRERA, including DGS HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if DGS HEIGHTS is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DGS HEIGHTS?
The registered promoter entity is D.G.BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DGS HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DGS HEIGHTS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DGS HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DGS HEIGHTS?
The professionals named in the filing: Architect: ABHIJIT J UDANI J UDANI; Engineer: HIREN TANNA; Chartered Accountant: Ms Vinay Tiwari & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DGS HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback