ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / DEVRAJ REGENCY 3

Registered No litigation declared Residential / Group Housing project

DEVRAJ REGENCY 3

By SHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED

RG-MH-17734 · RERA P51700066550 · Last updated on MahaRERA portal: 12 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
6 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 80%
80 of 94Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

DEVRAJ REGENCY 3 is a Residential / Group Housing project by SHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700066550 on 11 Jun 2024. Possession is promised by 31 Mar 2027. 14 of the 94 units on this registration are recorded sold or booked, and 6 of 33 construction stages are filed complete.

At a glance

Project

  • NameDEVRAJ REGENCY 3
  • TypeResidential / Group Housing
  • Location
    • STATION ROAD
    • VASHIND
    • Washind (CT)
    • Shahapur
    • Thane
    • 421601
  • Pincode421601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700066550
  • ReraGenie IDRG-MH-17734

Builder

  • NameSHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED
  • Entity typeCompany
  • DirectorDEVYANI DURGESH CHAUDHARI

Key dates

this monthRegisteredJun 2024PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Jun 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed69 files

Current status

15%14 of 94 units booked
49.5%Work done, per cost certificate

Figures as on 12 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA88281038
B WINGNA8735035
C WINGNA8721021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 12 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

A WING18%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING35%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C WING34%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed109

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots109
Closed/Covered3
Open Space106
BuildingClosed/CoveredOpen SpaceTotal
A WING13940
B WING13738
C WING13031

Land and ownership40

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,459 sq m
Land owned byThe promoter, with other names on the file
Named landowners40
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Dec 2025
LandownerVillageDistrict
SHEKHAR ASHOK PATHAREShahapur (CT)Thane
PRAVIN PRABHAKAR MANOREWashind (CT)Thane
SUBHASH PRABHAKAR MANOREWashind (CT)Thane
KALPANA SANTOSH MANOREKalyanThane
SATISH RAMCHANDR MANOREVada (CT)Palghar
RUPALI ROHIDAS CHAUDHARIKalyanThane
SONALI PRAMOD PAWARAngaonThane
NIKITA NITIN KHADKBANDMurbadThane
SUNIL RAJARAM MANOREMurbadThane
SUJAY RAJARAM MANORMurbadThane
BHARTI NANDKUMAR CHAUDHARIManiwaliRaigarh
BHAVNA SURESH KOTHIMBAREMurbadThane
RAJNI RAJARAM MANOREShahapur (CT)Thane
PRAMOD VASANT MANOREWashind (CT)Thane
SUDHIR GOPAL MANOREWashind (CT)Thane
PRAFUL GOPAL MANOREWashind (CT)Thane
RUCHITA RASIKLAL JAGEVada (CT)Palghar
VIJAY GOVIND MANOREBadlapur (M Cl)Thane
SADHANA PRAKASH MANOREWashind (CT)Thane
SHEEMA PANDURANG AMBAVANEVada (CT)Palghar
CHANDANI PRAKASH SHETEBhiwandi (M Corp.)Thane
MANISHA BALKRUSHN KHADAKBANBadlapur (M Cl)Thane
RAJENDRA GOVIND HARADWashind (CT)Thane
SANDEEP MADHUKAR THAKEKARWashind (CT)Thane
ARUN PANDURANG THAKEKARWashind (CT)Thane
GAJANAN SHANKAR THAKEKARWashind (CT)Thane
SANTOSH SANJAY THAKEKARWashind (CT)Thane
INDIRA SHANKAR THAKEKARWashind (CT)Thane
KRUSHNA SHANKAR THAKEKARChinchvali GoheRaigarh
SANJAY SHANKAR THAKEKARKhopoliRaigarh
ROHINI RAGHUNATH CHAUDHARIKhopoliRaigarh
RAJASHREE RAVIKANT GUJAREShahapur (CT)Thane
SEEMA EKNATH BHOPATRAOKarjatRaigarh
VEDIKA VITTHAL KHISMATRAOTitwalaThane
MALTI MADHUKAR THAKEKARWashind (CT)Thane
MANISH MADHUKAR THAKEKARWashind (CT)Thane
MILIND MADHUKAR THAKEKARWashind (CT)Thane
SADANAND PANDURANG THAKEKARThane (M Corp.)Thane
RAMESH PANDURANG THAKEKARWashind (CT)Thane
VIDYA VILAS THAKEKARWashind (CT)Thane

Approvals and building plan

Sanctioning authorityCollector and Town Planning Authority of Thane
Permissible FSI4658.57
Proposed, not sanctioned4,659 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMISHRA BHAVAN 75 STATION ROAD TITWALA 421605
Estimated costRs 8.95 cr
Cost incurredRs 4.43 cr
Work done49.49%
BuildingWingEstimatedIncurred
C WINGNARs 2.74 crRs 1.48 cr
A WINGNARs 2.73 crRs 1.48 cr
B WINGNARs 2.73 crRs 1.48 cr
-NARs 75.00 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVANEESH CONSULTANT
EngineerAVANEESH CONSULTANT
Chartered AccountantMANOJ PAL AND ASSOCIATES
PartnerRole in project
SHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Q3 Dec-25_compressed.pdf12 Feb 2026
Withdrawal Update Form 2File: Engineer Q3 Dec-25.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 Dec-2025.pdf12 Feb 2026
Form 1File: Architect Q1 Jun-24.pdf5 Dec 2025
Form 2File: Engineer Q1 Jun-24.pdf5 Dec 2025
Form 3File: Form 3 Final Jun-24.pdf5 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf5 Dec 2025
Form 1File: Architect Q2 Sep-24.pdf5 Dec 2025
Form 2File: Engineer Q2 Sep-24.pdf5 Dec 2025
Form 3File: Form 3 Final sep-24.pdf5 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf5 Dec 2025
Form 1File: Architect Q3 Dec-24.pdf5 Dec 2025
Form 2File: Engineer Q3 Dec-24.pdf5 Dec 2025
Form 3File: Form 3 Final Dec-24.pdf5 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec-24.pdf5 Dec 2025
Form 1File: Architect Q4 Mar-25.pdf5 Dec 2025
Form 2File: Engineer Q4 Mar-25.pdf5 Dec 2025
Form 3File: Form 3 Final Mar-25.pdf5 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar-25.pdf5 Dec 2025
Withdrawal Update Form 1File: Architect Q1 Jun-25.pdf5 Dec 2025
Withdrawal Update Form 1File: Architect Q2 Sep-25_compressed.pdf5 Dec 2025
Withdrawal Update Form 2File: Engineer Q1 Jun-25.pdf5 Dec 2025
Withdrawal Update Form 2File: Engineer Q2 Sep-25.pdf5 Dec 2025
Withdrawal Update Form 3File: Form 3 Final Jun-25.pdf5 Dec 2025
Withdrawal Update Form 3File: Form 3 Final Sep-25.pdf5 Dec 2025
Building plan approvalFile: HP2.pdf28 May 2024
Building plan approvalFile: HP3.pdf28 May 2024
Building plan approvalFile: HP4.pdf28 May 2024
Building plan approvalFile: HP5.pdf28 May 2024
Layout approvalFile: HP3.pdf28 May 2024
Layout approvalFile: HP4.pdf28 May 2024
Layout approvalFile: HP5.pdf28 May 2024
Copy of Layout Approval (in case of layout)File: HP3.pdf28 May 2024
Copy of Layout Approval (in case of layout)File: HP4.pdf28 May 2024
Copy of Layout Approval (in case of layout)File: HP5.pdf28 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HP2.pdf28 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HP3.pdf28 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HP4.pdf28 May 2024
Building Plan Approval / NA Order for plotted developmentFile: HP5.pdf28 May 2024
Other - LegalFile: HP1.pdf7 May 2024
Other - LegalFile: HP2.pdf7 May 2024
Other - LegalFile: HP3.pdf7 May 2024
Other - LegalFile: HP4.pdf7 May 2024
Other - LegalFile: HP5.pdf7 May 2024
Copy of the legal title reportFile: Title Report - 625-B.pdf6 May 2024
Other - TechnicalFile: Annexure A - Order.pdf19 Apr 2024
Building plan approvalFile: HP1.pdf15 Feb 2024
Layout approvalFile: HP1.pdf15 Feb 2024
Layout approvalFile: HP2.pdf15 Feb 2024
PAN CardFile: 1 PAN Card.pdf15 Feb 2024
Copy of the legal title reportFile: Title Report - Total.pdf15 Feb 2024
Details of encumbrances concerned to FinanceFile: ENCUMBERANCE - Finance Updated.pdf15 Feb 2024
Details of encumbrances concerned to FinanceFile: Legal Encumberance.pdf15 Feb 2024
Details of encumbrances concerned to LegalFile: ENCUMBERANCE - Finance Updated.pdf15 Feb 2024
Details of encumbrances concerned to LegalFile: Legal Encumberance.pdf15 Feb 2024
Copy of Layout Approval (in case of layout)File: HP1.pdf15 Feb 2024
Copy of Layout Approval (in case of layout)File: HP2.pdf15 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: HP1.pdf15 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Final.pdf15 Feb 2024
Declaration about Commencement CertificateFile: Commencement Declaration - Final.pdf15 Feb 2024
Declaration in FORM BFile: Form B.pdf15 Feb 2024
CERSAI detailsFile: ENCUMBERANCE Cresai.pdf15 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf15 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest letter - Devyani.pdf15 Feb 2024
Proforma of Allotment letterFile: allotment letter Final.pdf15 Feb 2024
Proforma of Agreement for saleFile: sales agreement.pdf15 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf15 Feb 2024
Deviation Report with respect to Allotment letterFile: Allotment Letter -Deviation.pdf15 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Sale Agreement -Deviation.pdf15 Feb 2024

How this compares with Thane

15%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DEVRAJ REGENCY 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASHIND7,600+ in Thane

2 kmDEVRAJ REGENCY 3Completed 21Lapsed / revoked 20Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 66 registered projects within 2 km.

Builder: SHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED

SHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED has 1 registration on MahaRERA, including DEVRAJ REGENCY 3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if DEVRAJ REGENCY 3 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DEVRAJ REGENCY 3?

The registered promoter entity is SHRIVIGHANHARTA REALTY (OPC) PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DEVRAJ REGENCY 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DEVRAJ REGENCY 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DEVRAJ REGENCY 3?

The professionals named in the filing: Architect: AVANEESH CONSULTANT; Engineer: AVANEESH CONSULTANT; Chartered Accountant: MANOJ PAL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DEVRAJ REGENCY 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DEVRAJ REGENCY 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DEVRAJ REGENCY 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.