Home / Browse projects / Pune, Maharashtra / Dev Bhumi
Dev Bhumi
RG-MH-35485 · RERA P52100080972 · Last updated on MahaRERA portal: 17 Apr 2026
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Dev Bhumi is a Plotted project by Mr Ashok Dnyanoba kale in Pune, Maharashtra, registered with MahaRERA as P52100080972 on 11 Sep 2025. The registration is recorded completed; possession was promised by 31 Dec 2025. 0 of the 66 units on this registration are recorded sold or booked.
At a glance
Project
- NameDev Bhumi
- TypePlotted
- Location
- Pur
- Purandhar
- Pune
- 412301
- Pincode412301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100080972
- ReraGenie IDRG-MH-35485
Builder
- NameMr Ashok Dnyanoba kale
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on11 Sep 2025
- Promised completion31 Dec 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed92 files
Current status
Figures as on 17 Apr 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 17 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mr Amit D Kamthe | Fursungi | Pune |
| Mr Akshay P Jagtap | Ashtapur | Pune |
| Mr Vishal P Jagtap | Ashtapur | Pune |
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | IPSA Design Consultant |
| Engineer | Rutuja Jagdale |
| Chartered Accountant | CA Deepak Pardeshi |
| Partner | Role in project |
|---|---|
| Mr Ashok Dnyanoba kale | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Dec 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 May 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Feb 2026
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Devbhumi (1).pdf | 17 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Devbhumi.pdf | 17 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Devbhumi.pdf | 17 Apr 2026 |
| Withdrawal Update Form 1File: Architect Latter 1 (2).pdf | 13 Apr 2026 |
| Withdrawal Update Form 2File: COMMITMENT CERTIFICATE.pdf | 13 Apr 2026 |
| Withdrawal Update Form 3File: Dev Bhumi RERA 31-12-24 (2).pdf | 13 Apr 2026 |
| Completion CertificateFile: Email Devbhumi.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Architect Latter 1 (2).pdf | 28 Nov 2025 |
| Withdrawal Update Form 2File: COMMITMENT CERTIFICATE.pdf | 28 Nov 2025 |
| Withdrawal Update Form 3File: Dev Bhumi RERA 31-12-24 (2).pdf | 28 Nov 2025 |
| Completion CertificateFile: 20251125100313.pdf | 28 Nov 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: D3-Dev bhumi.pdf | 20 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: D3-Dev bhumi.pdf | 20 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: D3-Dev bhumi.pdf | 20 May 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Mouje- Pur Taluka Purander Dist Pune bppmrdareraGmail.pdf | 26 Jan 2025 |
| Other - FinanceFile: Declaration- Dev Bhumi (1).pdf | 26 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Mouje- Pur Taluka Purander Dist Pune bppmrdareraGmail.pdf | 26 Jan 2025 |
| Other - FinanceFile: Declaration- Dev Bhumi (1).pdf | 26 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Mouje- Pur Taluka Purander Dist Pune bppmrdareraGmail.pdf | 26 Jan 2025 |
| Other - FinanceFile: Declaration- Dev Bhumi (1).pdf | 26 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal (Form 3) (62) (1).pdf | 8 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Dev bhumi.pdf | 8 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal (Form 3) (62) (1).pdf | 8 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Dev bhumi.pdf | 8 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal (Form 3) (62) (1).pdf | 8 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Dev bhumi.pdf | 8 Jan 2025 |
| Layout approvalFile: SANCTION PLAN 1_1.pdf | 30 Dec 2024 |
| Building plan approval or NA orderFile: SANCTION PLAN 2_2_compressed.pdf | 30 Dec 2024 |
| Layout approvalFile: SANCTION PLAN 1_1.pdf | 30 Dec 2024 |
| Building plan approval or NA orderFile: SANCTION PLAN 2_2_compressed.pdf | 30 Dec 2024 |
| Layout approvalFile: SANCTION PLAN 1_1.pdf | 30 Dec 2024 |
| Building plan approval or NA orderFile: SANCTION PLAN 2_2_compressed.pdf | 30 Dec 2024 |
| PAN CardFile: Pan card- AK.pdf | 30 Dec 2024 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (27) (1).pdf | 30 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance-AK.pdf | 30 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: SANCTION PLAN 1_1.pdf | 30 Dec 2024 |
| Proforma of Allotment letterFile: SKMBT_C28024122604070.pdf | 30 Dec 2024 |
| Declaration in FORM BFile: SKMBT_C28024122604050.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Latter 1 (1).pdf | 30 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMITMENT CERTIFICATE.pdf | 30 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 2_2_compressed.pdf | 30 Dec 2024 |
| Declaration about Commencement CertificateFile: Format D-Dev bhumi.pdf | 30 Dec 2024 |
| CERSAI detailsFile: SKMBT_C28024122604081.pdf | 30 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: SKMBT_C28024122604090.pdf | 30 Dec 2024 |
| Deviation Report with respect to Allotment letterFile: SKMBT_C28024122604083.pdf | 30 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance-AK.pdf | 30 Dec 2024 |
| Other - TechnicalFile: SKMBT_C28024122604080.pdf | 30 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: SKMBT_C28024122604084.pdf | 30 Dec 2024 |
| Proforma of Agreement for saleFile: AFS-devbhumi 26 01.pdf | 30 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-AK.pdf | 30 Dec 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: SKMBT_C28024122604091.pdf | 30 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secured Unsecured.pdf | 30 Dec 2024 |
| PAN CardFile: Pan card- AK.pdf | 30 Dec 2024 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (27) (1).pdf | 30 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance-AK.pdf | 30 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: SANCTION PLAN 1_1.pdf | 30 Dec 2024 |
| Proforma of Allotment letterFile: SKMBT_C28024122604070.pdf | 30 Dec 2024 |
| Declaration in FORM BFile: SKMBT_C28024122604050.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Latter 1 (1).pdf | 30 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMITMENT CERTIFICATE.pdf | 30 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 2_2_compressed.pdf | 30 Dec 2024 |
| Declaration about Commencement CertificateFile: Format D-Dev bhumi.pdf | 30 Dec 2024 |
| CERSAI detailsFile: SKMBT_C28024122604081.pdf | 30 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: SKMBT_C28024122604090.pdf | 30 Dec 2024 |
| Deviation Report with respect to Allotment letterFile: SKMBT_C28024122604083.pdf | 30 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance-AK.pdf | 30 Dec 2024 |
| Other - TechnicalFile: SKMBT_C28024122604080.pdf | 30 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: SKMBT_C28024122604084.pdf | 30 Dec 2024 |
| Proforma of Agreement for saleFile: AFS-devbhumi 26 01.pdf | 30 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-AK.pdf | 30 Dec 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: SKMBT_C28024122604091.pdf | 30 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secured Unsecured.pdf | 30 Dec 2024 |
| PAN CardFile: Pan card- AK.pdf | 30 Dec 2024 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (27) (1).pdf | 30 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance-AK.pdf | 30 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: SANCTION PLAN 1_1.pdf | 30 Dec 2024 |
| Proforma of Allotment letterFile: SKMBT_C28024122604070.pdf | 30 Dec 2024 |
| Declaration in FORM BFile: SKMBT_C28024122604050.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Latter 1 (1).pdf | 30 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMITMENT CERTIFICATE.pdf | 30 Dec 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
Keep Dev Bhumi on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pur13,700+ in Pune
Priyvardhini Bildcon
Priyvardhini Bildcon LLP
Wonder County
GREEN COLLIS LLP
Kanishka Grand Plaza
Platinum Lifespace Developers
NARAYAN BAUG
HBCL INFRA
Passport
Urban Realty
Shapoorji Pallonji Treetopia Phase 1
Manjri Horse Breeders' Farm Private Limite
Builder: Mr Ashok Dnyanoba kale
Mr Ashok Dnyanoba kale has 1 registration on MahaRERA, including Dev Bhumi. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Dev Bhumi is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Dev Bhumi?
The registered promoter entity is Mr Ashok Dnyanoba kale, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Dev Bhumi?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Dev Bhumi?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Dev Bhumi?
The professionals named in the filing: Architect: IPSA Design Consultant; Engineer: Rutuja Jagdale; Chartered Accountant: CA Deepak Pardeshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Dev Bhumi?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback