ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / DELTA HOUSE

Registration lapsed No litigation declared Residential / Group Housing project

DELTA HOUSE

By RIGHT CHANNEL CONSTRUCTION PVT LTD

RG-MH-10820 · RERA P51800003828 · Last updated on MahaRERA portal: 9 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 42 months
  • 4 extensions taken
  • Rs 10.00 crore secured on the land, in favour of Sundaram Alternate Assets Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
10 of 11Construction stages donefurthest along: Installation of Lifts, 0%
26 of 177Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 162 documents Report an error

DELTA HOUSE is a Residential / Group Housing project by RIGHT CHANNEL CONSTRUCTION PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003828 on 6 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 42 months from the original filing. 151 of the 177 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameDELTA HOUSE
  • TypeResidential / Group Housing
  • Location
    • Ram Mandir Road
    • Goregaon East
    • Borivali
    • Mumbai Suburban
    • 400063
  • Pincode400063
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003828
  • ReraGenie IDRG-MH-10820

Builder

  • NameRIGHT CHANNEL CONSTRUCTION PVT LTD
  • Entity typeCompany
  • CINU45202MH2008PTC188854
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed162 files

Current status

85%151 of 177 units booked
81.7%Work done, per cost certificate

Figures as on 9 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DELTA HOUSE - A,B,C WingNA151516314177

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 0%.

DELTA HOUSE - A,B,C Wing: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed108

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots108
Closed/Covered108

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,159 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
Charge in favour ofSundaram Alternate Assets Limited
Secured amountRs 10.00 crore
CERSAI search filedYes
Declared on14 Jan 2026
LandownerVillageDistrict
RE FORM REALTYNavi Mumbai (M Corp.)Thane
Balwant Gelaram VyasBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI6109.19
Proposed, not sanctioned4,567 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Accord Commercial, Next to Vodafone Gallery, Goregoan East Railway Station
Estimated costRs 59.13 cr
Cost incurredRs 48.30 cr
Work done81.68%
BuildingWingEstimatedIncurred
DELTA HOUSE - A,B,C WingNARs 57.95 crRs 47.82 cr
-NARs 1.18 crRs 48.30 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Neve & Associates
EngineerS K Consultants & Engineers
Chartered AccountantN B Sayed & Associates
Chartered AccountantJIvesh Borole & Associates
PartnerRole in project
RIGHT CHANNEL CONSTRUCTION PVT LTD-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013629Dec 2022 → Dec 2023

Reason as filed by the promoterOn applicablility of DCR 2034, there were major changes in the approved plans of project such as tenants are to be given units of 305 sq. fts. instead of 269 sq. fts. earlier and due to this, sale plan also changed. All the amended NOCs were also required to be obtained. It took us some time to obtain permissions especially railway NOC (due to change in their policies) and in the meantime COVID-19 also spread it's effect. Even in this scenario, we have completed Ground + 12 slabs of sale building + brickwork upto 10 floors + internal plaster upto 8 floors and rehab building is completed to the

EXT51800018134Dec 2022 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51% allottees for purpose of extension of RERA registration period of the said project

EXT51800027779Dec 2022 → Dec 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements. We seek your understa

EA14012619439Dec 2022 → Jun 2026

Reason as filed by the promoterThe delay has occurred due to unforeseen circumstances, including procurement issues, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. The project work is 85% complete, as more particularly reflected in Form 1 (Architect’s Certificate) as on December 2025 Quarter. Only minor finishing works and statutory compliances remain to be completed. In order to complete the remaining formalities in an orderly and compliant manner, including application for Occupancy Certificate (OC) and obtaining the same, we respectfully see

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000429156Sandeep Kumar SinghRIGHT CHANNEL CONSTRUCTION PVT LTD07/02/2024
CC12400080Vanita ManianRIGHT CHANNEL CONSTRUCTION PVT LTD11/09/2024
CC12502237LUV RAJU SHUKLARIGHT CHANNEL CONSTRUCTION PVT LTD04/07/2025
CC12601285Nikhil Dattapal NeroyRIGHT CHANNEL CONSTRUCTION PVT LTD09/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed162

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 162 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: 1 Form 5 - Delta House 24-25.pdf9 Jun 2026
Layout approvalFile: 11-12.pdf18 Apr 2026
Building plan approvalFile: 11-12.pdf18 Apr 2026
Building plan approvalFile: 12.pdf18 Apr 2026
Building plan approvalFile: 13.pdf18 Apr 2026
Building plan approvalFile: 14-15.pdf18 Apr 2026
Building plan approvalFile: 16-17.pdf18 Apr 2026
Building plan approvalFile: 18-19.pdf18 Apr 2026
Building plan approvalFile: 20-21.pdf18 Apr 2026
Commencement certificateFile: Nesco Full CC.pdf18 Apr 2026
Withdrawal Update Form 1File: Form 1 of Delta House as on 31st March 2026.pdf18 Apr 2026
Withdrawal Update Form 2File: Form 2 of Delta House as on 31st March 2026.pdf18 Apr 2026
Withdrawal Update Form 3File: Form 3 of Delta House as on 31st March 2026.pdf18 Apr 2026
Withdrawal Update Form 1File: RERA - Jan-Mar 26 - Nesco.pdf17 Apr 2026
Withdrawal Update Form 2File: Form 2 of Delta House as on 31st March 2026.pdf17 Apr 2026
Withdrawal Update Form 3File: Form 3 of Delta House as on 31st March 2026.pdf17 Apr 2026
Withdrawal Update Form 1File: Form 1 - Delta House as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 2File: Form 2 - Delta House as on Dec 2025.pdf7 Feb 2026
Withdrawal Update Form 3File: Form 3 of Delta House as on 31st December 2025.pdf7 Feb 2026
Form 1File: Form 1.pdf7 Jan 2026
Form 2File: Form 2.pdf7 Jan 2026
Form 3File: Form 3 Signed_compressed (1).pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 (3).pdf7 Jan 2026
Form 1File: Form 1.pdf7 Jan 2026
Form 2File: Form 2.pdf7 Jan 2026
Form 3File: Form 3.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf7 Jan 2026
Form 1File: Form 1.pdf7 Jan 2026
Form 2File: Form 2.pdf7 Jan 2026
Form 3File: Form 3.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29.pdf7 Jan 2026
Other - TechnicalFile: Project PERT Overview SD - Copy_11zon (1).pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24__compressed.pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Delta House as on FY 23-24.pdf7 Mar 2025
Declaration in FORM BFile: Form B SD (2)_5_11zon.pdf5 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 NESCO RERA Oct to Dec 2024 SD.pdf5 Mar 2025
Certificates of CA (Form 3)File: Form 3 of Delta House as on 31st December 2024 SD_4_11zon.pdf5 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on Dec 2024 SD_3_11zon.pdf5 Mar 2025
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 -Delta House as on Dec 24 SD_9_11zon.pdf5 Mar 2025
Certificates of CA (Form 3)File: Form 3 - Delta House as on Sep 2024.pdf13 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on Sep 2024.pdf13 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Delta House as on Sep 2024.pdf30 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on June 2024.pdf27 Jul 2024
Certificates of CA (Form 3)File: Form 3 - Delta House as on 30th June 2024.pdf27 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf20 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf20 Jul 2024
Certificates of CA (Form 3)File: 7 Certificates of CA (Form 3).pdf20 Jul 2024
Details of encumbrancesFile: Financial Encumbrances_Delta House__compressed.pdf24 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 06 Form 1 Q4 DH 1.pdf18 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 07 Form 2 - Delta House as on March 2024 SD 1.pdf18 Jun 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 -Delta House as on March 2024 SD_11zon.pdf18 Jun 2024
Certificates of CA (Form 3)File: 08 Form 3 - Delta House as on March 2024 SD 1.pdf18 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24 1.pdf12 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on March 2024.pdf25 Apr 2024
Certificates of CA (Form 3)File: Form 3 - Delta House as on March 2024.pdf25 Apr 2024
Declaration in FORM BFile: Affidavit Cum Declaration - Form B.pdf7 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 23.pdf7 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 23.pdf7 Feb 2024
Declaration in FORM BFile: FORM -B (Promoter) 3.pdf2 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Delta House SD.pdf2 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on Dec 2023 SD.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20 1.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21 1.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22 1.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23 1.pdf2 Feb 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29.pdf2 Feb 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 SD.pdf2 Feb 2024
CERSAI detailsFile: DECLARATION of Cersai SD.pdf2 Feb 2024
Certificates of CA (Form 3)File: Form 3 - Delta House as on 31st December 2023 SD_compressed.pdf2 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Right Channel SD.pdf2 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Seperate Bank Account Details SD.pdf2 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on Dec 2023.pdf18 Jan 2024
Certificates of CA (Form 3)File: Form 3 - Delta House as on 31st December 2023.pdf18 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Delta House as on 30th September 2023 LH SD_compressed.pdf29 Dec 2023
Certificates of CA (Form 3)File: Form 3 - Delta House as on 30th September 2023 Scan SD_compressed.pdf29 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Delta House FY 2022-23 Scan SD.pdf29 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Apr 17 to Mar 18.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Apr 18 to Mar 19.pdf19 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Delta House as on March 2023.pdf18 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Delta House as on June 2023.pdf18 Dec 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
AABIEL PARADISENEAR FALSA BUSINESS PARK OPP MAXUS MALL Bhayandar West THANE 40110136CompletedDec 2014Late, Mar 2015
TRISHUL HEIGHTBANDARPAKADI OFF LINK ROAD KANDIVALI WEST31CompletedMar 2012Late, Aug 2014
KAILASH RAMKRIPAKAILASH RAMKRIPA BUILDING PLOT NO 6 KAILASH RAMPUR ROAD MALAD EAST MUMBAI 40009733CompletedFeb 2011Late, Mar 2011

How this compares with Mumbai Suburban

85%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DELTA HOUSE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon East6,700+ in Mumbai Suburban

2 kmDELTA HOUSECompleted 124Lapsed / revoked 60Abeyance 1Other 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 295 registered projects within 2 km.

Builder: RIGHT CHANNEL CONSTRUCTION PVT LTD

RIGHT CHANNEL CONSTRUCTION PVT LTD has 6 registrations on MahaRERA, including DELTA HOUSE and AABIEL AVENUE. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that DELTA HOUSE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DELTA HOUSE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DELTA HOUSE?

The registered promoter entity is RIGHT CHANNEL CONSTRUCTION PVT LTD, a company as per the filing. Its CIN U45202MH2008PTC188854 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DELTA HOUSE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DELTA HOUSE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DELTA HOUSE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DELTA HOUSE?

The professionals named in the filing: Architect: Sanjay Neve & Associates; Engineer: S K Consultants & Engineers; Chartered Accountant: N B Sayed & Associates; Chartered Accountant: JIvesh Borole & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DELTA HOUSE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DELTA HOUSE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DELTA HOUSE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.