Home / Browse projects / Thane, Maharashtra / DB Ozone
DB Ozone
By NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED
RG-MH-20636 · RERA P51700003433 · Last updated on MahaRERA portal: 21 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 71 complaints at MahaRERA
- Completion date moved by 60 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DB Ozone is a Residential / Group Housing project by NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700003433 on 5 Aug 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 60 months from the original filing. 71 complaints are on record with the regulator.
At a glance
Project
- NameDB Ozone
- TypeResidential / Group Housing
- Location
- General A K Vaidya Marg
- Goregaon East
- Mira-Bhayandar (M Corp.)
- Thane
- 400063
- Pincode400063
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700003433
- ReraGenie IDRG-MH-20636
Builder
- NameNEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED
- Entity typeCompany
- DirectorsVINOD KUMAR GOENKA, HIFZURREHMAN KADIWAL
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Aug 2017
- Promised completion30 Dec 2024
- Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2019)
- Buildings25 building records
- Documents filed315 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 28 | NA | 25 | 0 | 0 | 0 | 0 |
| Building No 1 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 2 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 3 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 4 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 7 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 8 | NA | 25 | 0 | 0 | 0 | 0 |
| Building No 6 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 9 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 10 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 11 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 12 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 14 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 15 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 16 | NA | 25 | 0 | 0 | 0 | 0 |
| Building No 17 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 18 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 20 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 21 | NA | 25 | 0 | 0 | 0 | 0 |
| Building No 22 | NA | 25 | 0 | 0 | 0 | 0 |
| Building No 23 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 24 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 27 | NA | 26 | 0 | 0 | 0 | 0 |
| Building No 29 | NA | 24 | 0 | 0 | 0 | 0 |
| Building No 30 | NA | 26 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 21 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 25 buildings; the table lists the first 20.
186 of 275 construction stages are filed complete across 25 buildings. The stage furthest along is Staircases, at 99%.
Building No 2894%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 78% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 82% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 76% |
Building No 1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 799%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 89% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Building No 899%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 93% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Building No 698%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 79% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Building No 999%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 87% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Building No 1099%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 88% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Building No 1197%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 72% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Building No 1296%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Building No 1497%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 81% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Building No 1596%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 73% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 97% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Building No 1697%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 81% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Building No 1797%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 81% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
Building No 1895%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 78% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 78% |
Building No 2094%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 77% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 91% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 77% |
Building No 2194%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 91% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 77% |
Building No 2294%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 77% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 96% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 91% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 77% |
Progress on shared amenities16
As on 21 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 55% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 70% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 75% |
| Solid Waste Management And Disposal | Yes | 30% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 40% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Other facilities | Yes | 0% |
Parking filed1563
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building No 28 | 80 | 80 |
| Building No 1 | 66 | 66 |
| Building No 2 | 66 | 66 |
| Building No 3 | 66 | 66 |
| Building No 4 | 66 | 66 |
| Building No 7 | 66 | 66 |
| Building No 8 | 48 | 48 |
| Building No 6 | 85 | 85 |
| Building No 9 | 66 | 66 |
| Building No 10 | 66 | 66 |
| Building No 11 | 62 | 62 |
| Building No 12 | 50 | 50 |
| Building No 14 | 56 | 56 |
| Building No 15 | 39 | 39 |
| Building No 16 | 48 | 48 |
| Building No 17 | 56 | 56 |
| Building No 18 | 74 | 74 |
| Building No 20 | 66 | 66 |
| Building No 21 | 48 | 48 |
| Building No 22 | 48 | 48 |
| Building No 23 | 66 | 66 |
| Building No 24 | 62 | 62 |
| Building No 27 | 62 | 62 |
| Building No 29 | 66 | 66 |
| Building No 30 | 85 | 85 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Avinash Mhatre & Associates |
| Architect | BK Engineers & Consultant |
| Engineer | JW CONSULTANTS LLP |
| Partner | Role in project |
|---|---|
| NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) The Applicant states that the project was delayed on account of various factors as below : i. There was non-availability of sand for the construction of the project as mining was banned in all Coastal Regulated areas across the State of Maharashtra. ii. The Quarrying for stones was simultaneously banned in the State by the Environment Ministry resulting into non-availability of stones on construction and which correspondingly caused delay in completion of the project. iii. In view of the Hon’ble Bombay High Court in PIL No. 138 of 2006 on account of the ban, the stone Vendors were unable to
Reason as filed by the promoter* The Status of Construction of Building no. 1,2,3,4,6,7,8,9,10 are at final stage of Completion. Installation of lift is going on in building nos. 11,12,14,16 &17 and will be ready to handover for fit out Possession in the month of January 2020. The other facilities/amenities such as Electricity, Water connection, Fire Fighting, Solar Panel, Children’s Play area already functional. The Photographs of the same are annexed herewith as Annexure A. * The NBFC crisis has been a tip of the iceberg of the ongoing headwinds faced by the real estate industry with the slower receivable cycles and furth
Litigation declared30
| Case | Court | Status |
|---|---|---|
| Complaint No 12/184/2012 | State Commission Maharashtra | Disposed off |
| SC Suit No 206/2014 | City Civil Court Sr Div Thane | Matter pending |
| SCS No 346 of 2013/2013 | City Civil Court Sr Div Thane | Disposed Off |
| CC No 647/15/2015 | State Commission Maharashtra | Disposed Off |
| Complaint No 16/657/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/658/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/659/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/662/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/661/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/664/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/660/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/656/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/712/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/713/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/665/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/666/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/710/2016 | State Commission Maharashtra | Matter kept for evidence |
| Complaint No 16/709/2016 | State Commission Maharashtra | Matter kept for evidence |
| CC No 887/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/893/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/892/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/825/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/896/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/823/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/895/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/890/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/891/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/826/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/888/2016 | State Commission Maharashtra | Disposed Off |
| CC No 16/885/2016 | State Commission Maharashtra | Disposed Off |
Complaints filed with MahaRERA71
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000078930 | Mrs.Trupti Bhavesh Panchal & Mr.Bhavesh Harish Panchal | Neelkamal Realtors Suburban Private Limited | 10/05/2019 |
| CC006000000001214 | Rashmikant Triloki Singh | Neelkamal Relators Suburban Private Limited | 12/10/2017 |
| CC006000000000910 | CHARIT KAPIL | NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED | 02/01/2018 |
| CC006000000044468 | Brian Aranha | Neelkamal Realtors Suburban Pvt. Ltd | 14/05/2018 |
| CC006000000044049 | Navneet Bagga | Neelkamal Realtors Suburban Private Limited | 09/04/2018 |
| CC006000000001154 | Mangla Prasad Ramposh Singh | M/s. Neelkamal Relators Suburban Private Limited | 10/10/2017 |
| CC006000000001133 | SINCLAIR MONIZ | Neelkamal Realtors Suburban Private Limited | 07/10/2017 |
| CC006000000001277 | Kalpesh H Chheda | Neelkamal Realtors Suburban Pvt. Ltd. | 09/11/2017 |
| CC006000000001342 | Ashok Jadav | Deepak D'souza | 24/10/2017 |
| CC006000000001394 | Omkar Ramesh Dabholkar | M/s. Neelkamal RelatorsSuburban Pvt. Ltd. | 12/11/2017 |
| CC006000000001464 | NITIN PRABHAKAR CHAVAN | MR.BALWA | 25/10/2017 |
| CC006000000001559 | Keshavlal B. Upadhyay | Neelkamal Realtors Suburban Private Limited | 29/10/2017 |
| CC006000000001740 | Bhupendra vira | Neelkamal Realtors Suburban pvt ltd | 08/11/2017 |
| CC006000000001744 | chandrakant shetty | Neelkamal Realtors | 09/11/2017 |
| CC006000000012488 | Gilbert Fernandes/Ulanda Fernandes | NEELKAMAL REALTORS SUBURBAN PVT.LTD | 20/02/2018 |
| CC006000000012579 | ASHISH R PANDEY | NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED | 23/12/2017 |
| CC006000000012580 | VIKAS R PANDEY | NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED | 23/12/2017 |
| CC006000000022906 | MANOJKUMAR BHANUPRAKASH SHUKLA | NEELKAMAL REALTORS SUBURBAN PVT LTD | 05/02/2018 |
| CC006000000130995 | MR. VIJAY B. SINGH | NEELKAMAL REALTORS SUBURBAN PVT LTD | 22/09/2019 |
| CC006000000151224 | VINAYKUMAR SHARDA YADAV | NEELKAMAL REALTORS SUBURBAN PVT. LTD. | 10/10/2019 |
| CC006000000023603 | Swanand Vishwas Haldankar | Neelkamal Realtors Suburban Private Limited | 05/03/2018 |
| CC006000000044376 | Shailendra Tripathi | Neelkamal Realtors Suburban Pvt. Ltd. | 02/05/2018 |
| CC006000000054701 | SANGAM RAMAKANT TIWARI | NEELKAMAL REALTORS SUBURBAN PVT LIMITED | 31/05/2018 |
| CC006000000055283 | MRS. SANDHYA AGARWAL | NEELKAMAL REALTORS SUBURBAN PVT. LTD. | 16/07/2018 |
| CC006000000055667 | PRAVEEN K HARKAWAT | NEELKAMAL REALTORS SUBURBAN PVT LTD | 20/05/2019 |
| CC006000000055865 | Abhishek Soni | Neelkamal Relators Suburban Private Limited | 18/09/2018 |
| CC006000000056524 | Shruti Mehta | Neelkamal Realtors Suburban Private Limited | 11/10/2018 |
| CC006000000057117 | Jagdish Bhoja Shetty | Neelkamal Realtors Suburban Pvt Ltd | 11/12/2018 |
| CC006000000057199 | Shweta Yogesh Nainani | Jessie Kuruvilla | 31/01/2019 |
| CC006000000057178 | GANESH G MANJREKAR | M/S NEELKAMMAL REALTORS SUBURBAN PVT LTD | 06/12/2018 |
| CC006000000057897 | Bhartendu Vatsya | Neelkamal Realtors Suburban Private Limited | 30/01/2019 |
| CC006000000057460 | Ramesh Lanka and Padmaja Lanka | Neelkamal Realtors Suburban Pvt Ltd | 26/12/2018 |
| CC006000000057540 | gopal b shetty | neelkamal realtors suburban pvt ltd | 29/01/2019 |
| CC006000000057708 | ANIL BHUPATBHAI GOHIL | NEELKAMALREALTORS SUBURBAN PVT LTD | 17/01/2019 |
| CC006000000057903 | ROHAN KISAN PATIL | Neelkamal Realtors Suburban Pvt.Ltd | 19/03/2019 |
| CC006000000110670 | YESHWANT RAMCHANDRA WARERKAR | Neelkamal Realtors Suburban Pvt ltd | 23/08/2019 |
| CC006000000195012 | abhishek ashok Goyal | Neelkamal Realtors subhurban pvt ltd | 24/11/2020 |
| CC006000000078485 | Munir Khan | Neelkamal Realtors Suburban Rvt Ltd,DB Ozone Mira Road | 16/05/2019 |
| CC006000000100189 | Jagruti N jinadra | Neelkamal Realtors Suburban Pvt Ltd | 17/07/2019 |
| CC006000000079336 | RAJESH MOTIRAM CHHABRIA AND NEETA RAJESH CHHABRIA | NEELKAMAL REALTORS SUBURBAN PVT. LTD. | 17/05/2019 |
| CC006000000110765 | REGINA MERCY DCOSTA | NEELKAMAL REALTORS PVT LTD | 31/08/2019 |
| CC006000000110766 | RAMSEY ANGELO DCOSTA | NEELKAMAL REALTORS PVT LTD | 31/08/2019 |
| CC006000000079192 | RAKESH SHETTY | NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED | 09/05/2019 |
| CC006000000100335 | UMESH MANGATRAM GUPTA | M/s. NEELKAMAL REALTORS SUBURBAN PRIVATE LTD. | 10/09/2019 |
| CC006000000110692 | NARESH MURARI LAL AGARWAL | Neelkamal Realtors Suburban Pvt Ltd | 26/08/2019 |
| CC006000000120949 | SANGEETA NAGDA | M/S. NEELKAMAL REALTORS (SUBURBAN) PVT. LTD. | 17/09/2019 |
| CC006000000161436 | Rajat Narang | Rajat Narang | 06/11/2019 |
| CC006000000171822 | Abhishek Jain | DB REALTY | 21/12/2019 |
| CC006000000192344 | Mr Saurabh Masekar | Neelkamal Realtors Suburban Pvt Ltd | 05/02/2020 |
| CC006000000192426 | Manoj Gangwani, Dilip Gangwani, Vandana Gangwani, Umesh gangwani | NEELKAMAL REALTORS SUBURBAN PVT LTD | 05/03/2020 |
| CC006000000192694 | Santosh Kumar Lal Giri | Neelkamal Realtors Suburban Private Limited | 26/02/2020 |
| CC006000000192789 | SANJU SINGH | Shahid balwa | 06/03/2020 |
| CC006000000193220 | G SATISH | M/s. NEELKAMAL REALTORS PVT LTD. | 01/06/2020 |
| CC006000000193317 | Adv S J Lavte | Neelkamal Realtors Suburban Pvt Ltd | 12/11/2020 |
| CC006000000194156 | Swapnil Shiwalay | M/s Neelkamal Relators suburbon Pvt Ltd | 25/09/2020 |
| CC006000000194272 | HARESH M. VISHWAKARMA | Neelkamal Realtors Suburban Pvt. Ltd | 08/10/2020 |
| CC006000000197440 | Rakesh R. Dalmia | Neelkamal Realtors Suburban Pvt. Ltd. | 30/06/2021 |
| CC006000000195389 | Ketan Ashokrao Nage | Neelkamal Realtors Suburban Private Limited | 10/10/2022 |
| CC006000000196895 | Mr Dulichand Baid | M/s Neelkamal Realtors Suburban Pvt Ltd | 05/05/2021 |
| CC006000000196896 | Mrs Sushila Baid | M/s Neelkamal Realtors Suburban Pvt Ltd | 05/05/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed315
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 315 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-1-18.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-19-38-1-10.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-19-38-11-20.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-39-54.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-1-15.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-16-30.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-31-45.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-46-60.pdf | 21 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 20240330 March 2023 Form 5.pdf | 21 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 202203 Quality Assurance Certtificate.pdf | 16 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220930 FORM 1.pdf | 1 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20221231 FORM 1.pdf | 1 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20220930 FORM 2.pdf | 1 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20221231 FORM 2.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 01.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 02.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 03.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 04.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 05.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 06.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 07.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 08.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 09.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 10.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 11.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 12.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 13.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 14.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 01.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 02.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 03.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 04.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 05.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 06.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 07.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 08.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 09.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 10.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 11.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 12.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: 13.pdf | 1 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 20220930 FORM 5.pdf | 1 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01.pdf | 13 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02.pdf | 13 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 03.pdf | 13 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01.pdf | 13 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02.pdf | 13 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 03.pdf | 13 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2 DB Ozone March 2022.pdf | 12 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2 DB Ozone June 2022.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 1.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 2.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 3.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 4.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 5.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 6.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 7.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 8.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 9.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 10.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 11.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 12.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 1.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 2.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 3.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 4.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 5.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 6.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 7.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 8.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 9.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 10.pdf | 12 Sep 2022 |
| Certificates of CA (Form 3)File: 11.pdf | 12 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20200929 FORM 5.pdf | 3 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20210907 FORM 5.pdf | 3 Jun 2022 |
| Form 2AFile: 202203 Quality Assurance Certtificate.pdf | 20 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210702 FORM 1 _compressed.pdf | 11 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20211004 FORM 1 _compressed.pdf | 11 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220117 FORM 1_compressed.pdf | 11 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20210805 FORM 2-II.pdf | 11 May 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| DB Ozone - Mumbai | Village Dahisar Near Dahisar Check Naka Mumbai 400068 | 240 | Completed | Dec 2015 | Late, Dec 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 315 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep DB Ozone on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Goregaon East7,600+ in Thane
Filed coordinates, straight-line distance. 65 registered projects within 2 km.
Elysian Tower C, D, E
Oberoi Realty Limited
Elysian Tower B
Oberoi Realty Limited
Elysian Tower A
Oberoi Realty Limited
Sheetal Sangam
DGS Township Pvt Ltd
SEJAL SQUARE
ALCHEMI DEVELOPERS PRIVATE LIMITED
Mehta Marquina 1978
Shreeram Builders
See every Thane project, with the district possession charts
Builder: NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED
NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED has 1 registration on MahaRERA, including DB Ozone. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that DB Ozone shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if DB Ozone is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DB Ozone?
The registered promoter entity is NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DB Ozone?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against DB Ozone?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for DB Ozone?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DB Ozone?
The professionals named in the filing: Architect: Avinash Mhatre & Associates; Architect: BK Engineers & Consultant; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DB Ozone?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback