Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 71 complaints at MahaRERA
  • Completion date moved by 60 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
186 of 275Construction stages doneacross 25 buildings; furthest along: Staircases, 99%
71Complaints at MahaRERAon this registration
Jump to the 315 documents Report an error

DB Ozone is a Residential / Group Housing project by NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700003433 on 5 Aug 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 60 months from the original filing. 71 complaints are on record with the regulator.

At a glance

Project

  • NameDB Ozone
  • TypeResidential / Group Housing
  • Location
    • General A K Vaidya Marg
    • Goregaon East
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 400063
  • Pincode400063
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003433
  • ReraGenie IDRG-MH-20636

Builder

  • NameNEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsVINOD KUMAR GOENKA, HIFZURREHMAN KADIWAL
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2019)
  • Buildings25 building records
  • Documents filed315 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 28NA250000
Building No 1NA240000
Building No 2NA240000
Building No 3NA240000
Building No 4NA240000
Building No 7NA240000
Building No 8NA250000
Building No 6NA260000
Building No 9NA240000
Building No 10NA240000
Building No 11NA260000
Building No 12NA260000
Building No 14NA240000
Building No 15NA260000
Building No 16NA250000
Building No 17NA240000
Building No 18NA260000
Building No 20NA240000
Building No 21NA250000
Building No 22NA250000
Building No 23NA240000
Building No 24NA260000
Building No 27NA260000
Building No 29NA240000
Building No 30NA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 21 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 25 buildings; the table lists the first 20.

186 of 275 construction stages are filed complete across 25 buildings. The stage furthest along is Staircases, at 99%.

Building No 2894%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises78%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.82%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.76%
Building No 1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 799%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises89%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Building No 899%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises93%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Building No 698%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises79%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Building No 999%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises87%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Building No 1099%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises88%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Building No 1197%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises72%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Building No 1296%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Building No 1497%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises81%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Building No 1596%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises73%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Building No 1697%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises81%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Building No 1797%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises81%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Building No 1895%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises78%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.78%
Building No 2094%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises77%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.91%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%
Building No 2194%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.91%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%
Building No 2294%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises77%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.91%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%

Progress on shared amenities16

As on 21 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes55%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes70%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes30%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes40%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Other facilitiesYes0%

Parking filed1563

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,563
Closed/Covered1,563
BuildingClosed/CoveredTotal
Building No 288080
Building No 16666
Building No 26666
Building No 36666
Building No 46666
Building No 76666
Building No 84848
Building No 68585
Building No 96666
Building No 106666
Building No 116262
Building No 125050
Building No 145656
Building No 153939
Building No 164848
Building No 175656
Building No 187474
Building No 206666
Building No 214848
Building No 224848
Building No 236666
Building No 246262
Building No 276262
Building No 296666
Building No 308585

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area38,401 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI165138.0
Proposed, not sanctioned161,994 sq m
Buildings approved25
Buildings sanctioned25

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Conwood House, Yashodham, General A K Vaidya Marg, Mumbai 400063

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAvinash Mhatre & Associates
ArchitectBK Engineers & Consultant
EngineerJW CONSULTANTS LLP
PartnerRole in project
NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010187Dec 2019 → Dec 2024

Reason as filed by the promoter1) The Applicant states that the project was delayed on account of various factors as below : i. There was non-availability of sand for the construction of the project as mining was banned in all Coastal Regulated areas across the State of Maharashtra. ii. The Quarrying for stones was simultaneously banned in the State by the Environment Ministry resulting into non-availability of stones on construction and which correspondingly caused delay in completion of the project. iii. In view of the Hon’ble Bombay High Court in PIL No. 138 of 2006 on account of the ban, the stone Vendors were unable to

EXT51700003914Dec 2019 → Dec 2020

Reason as filed by the promoter* The Status of Construction of Building no. 1,2,3,4,6,7,8,9,10 are at final stage of Completion. Installation of lift is going on in building nos. 11,12,14,16 &17 and will be ready to handover for fit out Possession in the month of January 2020. The other facilities/amenities such as Electricity, Water connection, Fire Fighting, Solar Panel, Children’s Play area already functional. The Photographs of the same are annexed herewith as Annexure A. * The NBFC crisis has been a tip of the iceberg of the ongoing headwinds faced by the real estate industry with the slower receivable cycles and furth

Litigation declared30

CaseCourtStatus
Complaint No 12/184/2012State Commission MaharashtraDisposed off
SC Suit No 206/2014City Civil Court Sr Div ThaneMatter pending
SCS No 346 of 2013/2013City Civil Court Sr Div ThaneDisposed Off
CC No 647/15/2015State Commission MaharashtraDisposed Off
Complaint No 16/657/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/658/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/659/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/662/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/661/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/664/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/660/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/656/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/712/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/713/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/665/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/666/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/710/2016State Commission MaharashtraMatter kept for evidence
Complaint No 16/709/2016State Commission MaharashtraMatter kept for evidence
CC No 887/2016State Commission MaharashtraDisposed Off
CC No 16/893/2016State Commission MaharashtraDisposed Off
CC No 16/892/2016State Commission MaharashtraDisposed Off
CC No 16/825/2016State Commission MaharashtraDisposed Off
CC No 16/896/2016State Commission MaharashtraDisposed Off
CC No 16/823/2016State Commission MaharashtraDisposed Off
CC No 16/895/2016State Commission MaharashtraDisposed Off
CC No 16/890/2016State Commission MaharashtraDisposed Off
CC No 16/891/2016State Commission MaharashtraDisposed Off
CC No 16/826/2016State Commission MaharashtraDisposed Off
CC No 16/888/2016State Commission MaharashtraDisposed Off
CC No 16/885/2016State Commission MaharashtraDisposed Off

Complaints filed with MahaRERA71

Case no.ComplainantRespondentFiled
CC006000000078930Mrs.Trupti Bhavesh Panchal & Mr.Bhavesh Harish PanchalNeelkamal Realtors Suburban Private Limited10/05/2019
CC006000000001214Rashmikant Triloki SinghNeelkamal Relators Suburban Private Limited12/10/2017
CC006000000000910CHARIT KAPILNEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED02/01/2018
CC006000000044468Brian AranhaNeelkamal Realtors Suburban Pvt. Ltd14/05/2018
CC006000000044049Navneet BaggaNeelkamal Realtors Suburban Private Limited09/04/2018
CC006000000001154Mangla Prasad Ramposh SinghM/s. Neelkamal Relators Suburban Private Limited10/10/2017
CC006000000001133SINCLAIR MONIZNeelkamal Realtors Suburban Private Limited07/10/2017
CC006000000001277Kalpesh H ChhedaNeelkamal Realtors Suburban Pvt. Ltd.09/11/2017
CC006000000001342Ashok JadavDeepak D'souza24/10/2017
CC006000000001394Omkar Ramesh DabholkarM/s. Neelkamal RelatorsSuburban Pvt. Ltd.12/11/2017
CC006000000001464NITIN PRABHAKAR CHAVANMR.BALWA25/10/2017
CC006000000001559Keshavlal B. UpadhyayNeelkamal Realtors Suburban Private Limited29/10/2017
CC006000000001740Bhupendra viraNeelkamal Realtors Suburban pvt ltd08/11/2017
CC006000000001744chandrakant shettyNeelkamal Realtors09/11/2017
CC006000000012488Gilbert Fernandes/Ulanda FernandesNEELKAMAL REALTORS SUBURBAN PVT.LTD20/02/2018
CC006000000012579ASHISH R PANDEYNEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED23/12/2017
CC006000000012580VIKAS R PANDEYNEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED23/12/2017
CC006000000022906MANOJKUMAR BHANUPRAKASH SHUKLANEELKAMAL REALTORS SUBURBAN PVT LTD05/02/2018
CC006000000130995MR. VIJAY B. SINGHNEELKAMAL REALTORS SUBURBAN PVT LTD22/09/2019
CC006000000151224VINAYKUMAR SHARDA YADAVNEELKAMAL REALTORS SUBURBAN PVT. LTD.10/10/2019
CC006000000023603Swanand Vishwas HaldankarNeelkamal Realtors Suburban Private Limited05/03/2018
CC006000000044376Shailendra TripathiNeelkamal Realtors Suburban Pvt. Ltd.02/05/2018
CC006000000054701SANGAM RAMAKANT TIWARINEELKAMAL REALTORS SUBURBAN PVT LIMITED31/05/2018
CC006000000055283MRS. SANDHYA AGARWALNEELKAMAL REALTORS SUBURBAN PVT. LTD.16/07/2018
CC006000000055667PRAVEEN K HARKAWATNEELKAMAL REALTORS SUBURBAN PVT LTD20/05/2019
CC006000000055865Abhishek SoniNeelkamal Relators Suburban Private Limited18/09/2018
CC006000000056524Shruti MehtaNeelkamal Realtors Suburban Private Limited11/10/2018
CC006000000057117Jagdish Bhoja ShettyNeelkamal Realtors Suburban Pvt Ltd11/12/2018
CC006000000057199Shweta Yogesh NainaniJessie Kuruvilla31/01/2019
CC006000000057178GANESH G MANJREKARM/S NEELKAMMAL REALTORS SUBURBAN PVT LTD06/12/2018
CC006000000057897Bhartendu VatsyaNeelkamal Realtors Suburban Private Limited30/01/2019
CC006000000057460Ramesh Lanka and Padmaja LankaNeelkamal Realtors Suburban Pvt Ltd26/12/2018
CC006000000057540gopal b shettyneelkamal realtors suburban pvt ltd29/01/2019
CC006000000057708ANIL BHUPATBHAI GOHILNEELKAMALREALTORS SUBURBAN PVT LTD17/01/2019
CC006000000057903ROHAN KISAN PATILNeelkamal Realtors Suburban Pvt.Ltd19/03/2019
CC006000000110670YESHWANT RAMCHANDRA WARERKARNeelkamal Realtors Suburban Pvt ltd23/08/2019
CC006000000195012abhishek ashok GoyalNeelkamal Realtors subhurban pvt ltd24/11/2020
CC006000000078485Munir KhanNeelkamal Realtors Suburban Rvt Ltd,DB Ozone Mira Road16/05/2019
CC006000000100189Jagruti N jinadraNeelkamal Realtors Suburban Pvt Ltd17/07/2019
CC006000000079336RAJESH MOTIRAM CHHABRIA AND NEETA RAJESH CHHABRIANEELKAMAL REALTORS SUBURBAN PVT. LTD.17/05/2019
CC006000000110765REGINA MERCY DCOSTANEELKAMAL REALTORS PVT LTD31/08/2019
CC006000000110766RAMSEY ANGELO DCOSTANEELKAMAL REALTORS PVT LTD31/08/2019
CC006000000079192RAKESH SHETTYNEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED09/05/2019
CC006000000100335UMESH MANGATRAM GUPTAM/s. NEELKAMAL REALTORS SUBURBAN PRIVATE LTD.10/09/2019
CC006000000110692NARESH MURARI LAL AGARWALNeelkamal Realtors Suburban Pvt Ltd26/08/2019
CC006000000120949SANGEETA NAGDAM/S. NEELKAMAL REALTORS (SUBURBAN) PVT. LTD.17/09/2019
CC006000000161436Rajat NarangRajat Narang06/11/2019
CC006000000171822Abhishek JainDB REALTY21/12/2019
CC006000000192344Mr Saurabh MasekarNeelkamal Realtors Suburban Pvt Ltd05/02/2020
CC006000000192426Manoj Gangwani, Dilip Gangwani, Vandana Gangwani, Umesh gangwaniNEELKAMAL REALTORS SUBURBAN PVT LTD05/03/2020
CC006000000192694Santosh Kumar Lal GiriNeelkamal Realtors Suburban Private Limited26/02/2020
CC006000000192789SANJU SINGHShahid balwa06/03/2020
CC006000000193220G SATISHM/s. NEELKAMAL REALTORS PVT LTD.01/06/2020
CC006000000193317Adv S J LavteNeelkamal Realtors Suburban Pvt Ltd12/11/2020
CC006000000194156Swapnil ShiwalayM/s Neelkamal Relators suburbon Pvt Ltd25/09/2020
CC006000000194272HARESH M. VISHWAKARMANeelkamal Realtors Suburban Pvt. Ltd08/10/2020
CC006000000197440Rakesh R. DalmiaNeelkamal Realtors Suburban Pvt. Ltd.30/06/2021
CC006000000195389Ketan Ashokrao NageNeelkamal Realtors Suburban Private Limited10/10/2022
CC006000000196895Mr Dulichand BaidM/s Neelkamal Realtors Suburban Pvt Ltd05/05/2021
CC006000000196896Mrs Sushila BaidM/s Neelkamal Realtors Suburban Pvt Ltd05/05/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed315

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 315 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-1-18.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-19-38-1-10.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-19-38-11-20.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - March 2023-39-54.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-1-15.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-16-30.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-31-45.pdf21 May 2025
Certificates of CA (Form 3)File: DB Ozone RERA Form 3 - June 2023_compressed-46-60.pdf21 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 20240330 March 2023 Form 5.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 202203 Quality Assurance Certtificate.pdf16 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220930 FORM 1.pdf1 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20221231 FORM 1.pdf1 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20220930 FORM 2.pdf1 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20221231 FORM 2.pdf1 Feb 2023
Certificates of CA (Form 3)File: 01.pdf1 Feb 2023
Certificates of CA (Form 3)File: 02.pdf1 Feb 2023
Certificates of CA (Form 3)File: 03.pdf1 Feb 2023
Certificates of CA (Form 3)File: 04.pdf1 Feb 2023
Certificates of CA (Form 3)File: 05.pdf1 Feb 2023
Certificates of CA (Form 3)File: 06.pdf1 Feb 2023
Certificates of CA (Form 3)File: 07.pdf1 Feb 2023
Certificates of CA (Form 3)File: 08.pdf1 Feb 2023
Certificates of CA (Form 3)File: 09.pdf1 Feb 2023
Certificates of CA (Form 3)File: 10.pdf1 Feb 2023
Certificates of CA (Form 3)File: 11.pdf1 Feb 2023
Certificates of CA (Form 3)File: 12.pdf1 Feb 2023
Certificates of CA (Form 3)File: 13.pdf1 Feb 2023
Certificates of CA (Form 3)File: 14.pdf1 Feb 2023
Certificates of CA (Form 3)File: 01.pdf1 Feb 2023
Certificates of CA (Form 3)File: 02.pdf1 Feb 2023
Certificates of CA (Form 3)File: 03.pdf1 Feb 2023
Certificates of CA (Form 3)File: 04.pdf1 Feb 2023
Certificates of CA (Form 3)File: 05.pdf1 Feb 2023
Certificates of CA (Form 3)File: 06.pdf1 Feb 2023
Certificates of CA (Form 3)File: 07.pdf1 Feb 2023
Certificates of CA (Form 3)File: 08.pdf1 Feb 2023
Certificates of CA (Form 3)File: 09.pdf1 Feb 2023
Certificates of CA (Form 3)File: 10.pdf1 Feb 2023
Certificates of CA (Form 3)File: 11.pdf1 Feb 2023
Certificates of CA (Form 3)File: 12.pdf1 Feb 2023
Certificates of CA (Form 3)File: 13.pdf1 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 20220930 FORM 5.pdf1 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01.pdf13 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02.pdf13 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 03.pdf13 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01.pdf13 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02.pdf13 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 03.pdf13 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2 DB Ozone March 2022.pdf12 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2 DB Ozone June 2022.pdf12 Sep 2022
Certificates of CA (Form 3)File: 1.pdf12 Sep 2022
Certificates of CA (Form 3)File: 2.pdf12 Sep 2022
Certificates of CA (Form 3)File: 3.pdf12 Sep 2022
Certificates of CA (Form 3)File: 4.pdf12 Sep 2022
Certificates of CA (Form 3)File: 5.pdf12 Sep 2022
Certificates of CA (Form 3)File: 6.pdf12 Sep 2022
Certificates of CA (Form 3)File: 7.pdf12 Sep 2022
Certificates of CA (Form 3)File: 8.pdf12 Sep 2022
Certificates of CA (Form 3)File: 9.pdf12 Sep 2022
Certificates of CA (Form 3)File: 10.pdf12 Sep 2022
Certificates of CA (Form 3)File: 11.pdf12 Sep 2022
Certificates of CA (Form 3)File: 12.pdf12 Sep 2022
Certificates of CA (Form 3)File: 1.pdf12 Sep 2022
Certificates of CA (Form 3)File: 2.pdf12 Sep 2022
Certificates of CA (Form 3)File: 3.pdf12 Sep 2022
Certificates of CA (Form 3)File: 4.pdf12 Sep 2022
Certificates of CA (Form 3)File: 5.pdf12 Sep 2022
Certificates of CA (Form 3)File: 6.pdf12 Sep 2022
Certificates of CA (Form 3)File: 7.pdf12 Sep 2022
Certificates of CA (Form 3)File: 8.pdf12 Sep 2022
Certificates of CA (Form 3)File: 9.pdf12 Sep 2022
Certificates of CA (Form 3)File: 10.pdf12 Sep 2022
Certificates of CA (Form 3)File: 11.pdf12 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20200929 FORM 5.pdf3 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20210907 FORM 5.pdf3 Jun 2022
Form 2AFile: 202203 Quality Assurance Certtificate.pdf20 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210702 FORM 1 _compressed.pdf11 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20211004 FORM 1 _compressed.pdf11 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220117 FORM 1_compressed.pdf11 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20210805 FORM 2-II.pdf11 May 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
DB Ozone - MumbaiVillage Dahisar Near Dahisar Check Naka Mumbai 400068240CompletedDec 2015Late, Dec 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 60 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DB Ozone on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon East7,600+ in Thane

2 kmDB OzoneCompleted 18Lapsed / revoked 13Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 65 registered projects within 2 km.

Builder: NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED

NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED has 1 registration on MahaRERA, including DB Ozone. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that DB Ozone shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DB Ozone is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DB Ozone?

The registered promoter entity is NEELKAMAL REALTORS SUBURBAN PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DB Ozone?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DB Ozone?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DB Ozone?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DB Ozone?

The professionals named in the filing: Architect: Avinash Mhatre & Associates; Architect: BK Engineers & Consultant; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DB Ozone?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DB Ozone. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DB Ozone to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.