Home / Browse projects / Raigarh, Maharashtra / DATTA VIHAR
DATTA VIHAR
RG-MH-33949 · RERA P52000013719 · Last updated on MahaRERA portal: 13 Jun 2024
Source: official MahaRERA filing
Red flags
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DATTA VIHAR is a Residential / Group Housing project by MAITREE BUILDERS in Raigarh, Maharashtra, registered with MahaRERA as P52000013719 on 23 Oct 2017. The registration is recorded completed; possession was promised by 30 Mar 2021.
At a glance
Project
- NameDATTA VIHAR
- TypeResidential / Group Housing
- Location
- Near Kudave road
- Palaspe
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000013719
- ReraGenie IDRG-MH-33949
Builder
- NameMAITREE BUILDERS
- Entity typePartnership
- PartnersSUNIL KRUSHNAJI PARANJAPE, MADANMOHAN BALDEO INGAWALE
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on23 Oct 2017
- Promised completion30 Mar 2021
- Revised completionNone
- Buildings2 building records
- Documents filed46 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING 1 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING 2 | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 13 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 13 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
| Internal Walls Internal Plaster Floorings within Flats Doors and Windows to each flats | Yes | 100% |
Parking filed17
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING 1 | 7 | 3 | 10 |
| BUILDING 2 | 7 | 0 | 7 |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ARVIND LAXMAN PATIL PATKAR | Panvel | Raigarh |
| AARTI DINESH NAYAK | Panvel | Raigarh |
| GAYATRI GIRISH PHADAKE | Panvel | Raigarh |
| KANCHAN CHINTAMAN OZE | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHITECT DINESH VENKATESH NAYAK |
| Engineer | RAHUL RAMNATH SASHTE |
| Partner | Role in project |
|---|---|
| MAITREE BUILDERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPOST FACTO
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Oct 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 13 Jun 2024
Documents filed46
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 13 Jun 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 .pdf | 13 Jun 2024 |
| Declaration in FORM BFile: FORM B.pdf | 12 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 12 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 1.pdf | 12 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_compressed.pdf | 12 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A_compressed.pdf | 12 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A_compressed.pdf | 12 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_compressed.pdf | 12 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_compressed.pdf | 12 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_compressed.pdf | 12 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold .pdf | 12 Jun 2024 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 12 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 22-23_compressed.pdf | 12 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 23-24_compressed.pdf | 12 Jun 2024 |
| OtherFile: Extention Request Letter.pdf | 11 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 F Y 2020-21.pdf | 8 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 F Y 2021-22.pdf | 8 Apr 2023 |
| OtherFile: Letter to MahaRERA Authority.pdf | 8 Apr 2023 |
| OtherFile: Affidavit_compressed.pdf | 14 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Maitree Builders Audit Certificate 19-20.pdf | 17 Jan 2023 |
| OtherFile: OC Application.pdf | 23 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Maitree Builders Audit Certificate 19-20.pdf | 30 Sep 2020 |
| Certificates of CA (Form 5)File: Form 5 - Maitree Builders.pdf | 30 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 18 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_compressed.pdf | 18 Sep 2019 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 18 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 1 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_compressed.pdf | 1 Sep 2019 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 1 Sep 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 19 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Plinth Certificate.pdf | 19 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 29-12-2018 - Form 1-ilovepdf-compressed.pdf | 19 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 29-12-2018 - Form 2-ilovepdf-compressed.pdf | 19 Jan 2019 |
| Certificates of CA (Form 3)File: Form 3- Maitree Builders.pdf | 19 Jan 2019 |
| Certificates of CA (Form 5)File: Form 5.pdf | 19 Jan 2019 |
| Declaration in FORM BFile: FORM B DECLARATION NOTARISED.pdf | 11 Oct 2017 |
| Building plan approvalFile: NAINA CC AND PERMISSIONS.pdf | 6 Oct 2017 |
| Layout approvalFile: LAYOUT PLAN APPROVED BY CIDCO-NAINA (3).pdf | 6 Oct 2017 |
| PAN CardFile: PAN CARD.pdf | 6 Oct 2017 |
| Copy of the legal title reportFile: CERTIFICATE OF TITLE.pdf | 6 Oct 2017 |
| Details of encumbrancesFile: Search Report (3).pdf | 6 Oct 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN APPROVED BY CIDCO-NAINA (3).pdf | 6 Oct 2017 |
| Building Plan Approval (IOD)File: NAINA CC AND PERMISSIONS.pdf | 6 Oct 2017 |
| Certificates of CA (Form 3)File: Form 3 - Maitree Builders CA CERTIFICATE.pdf | 6 Oct 2017 |
| Proforma of Allotment letterFile: DRAFT SALE AGREEMENT AND ALOTTMENT LETTER.pdf | 6 Oct 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 46 filed documents as one ZIP, foldered, with a manifest
Keep DATTA VIHAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Palaspe5,900+ in Raigarh
Filed coordinates, straight-line distance. 57 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: MAITREE BUILDERS
MAITREE BUILDERS has 1 registration on MahaRERA, including DATTA VIHAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if DATTA VIHAR is delayed beyond 30 Mar 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DATTA VIHAR?
The registered promoter entity is MAITREE BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DATTA VIHAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DATTA VIHAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DATTA VIHAR?
The professionals named in the filing: Architect: ARCHITECT DINESH VENKATESH NAYAK; Engineer: RAHUL RAMNATH SASHTE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DATTA VIHAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.