Home / Browse projects / Mumbai Suburban, Maharashtra / D Wing Building No. 1
D Wing Building No. 1
RG-MH-04431 · RERA P51800021865 · Last updated on MahaRERA portal: 14 May 2024
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
D Wing Building No. 1 is a Residential / Group Housing project by M/s. Nasar Associates in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800021865 on 8 Aug 2019. The registration is recorded completed; possession was promised by 30 Dec 2024.
At a glance
Project
- NameD Wing Building No. 1
- TypeResidential / Group Housing
- Location
- 15th Road
- Borivali West
- Borivali
- Mumbai Suburban
- 400092
- Pincode400092
- RERA no.P51800021865
- ReraGenie IDRG-MH-04431
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on8 Aug 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed63 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D Wing Building No 1 | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
D Wing Building No 1: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Aashish Solanki Architect |
| Engineer | Clint Dos Santos |
| Chartered Accountant | Jignesh Shah & Co |
| Partner | Role in project |
|---|---|
| M/s. Nasar Associates | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jul 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Jul 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Aug 2023
Documents filed63
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: No encombrance.pdf | 14 May 2024 |
| Details of encumbrances concerned to LegalFile: No encombrance.pdf | 14 May 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: NASAR ASSOCIATES D WING SUNSHINE OC.pdf | 17 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 25 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 25 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1MARCH2022.pdf | 13 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1SEP2022.pdf | 13 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2APRIL2022.pdf | 13 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2OCT2022.pdf | 13 Dec 2022 |
| Certificates of CA (Form 3)File: FORM3MARCH2022.pdf | 13 Dec 2022 |
| Certificates of CA (Form 3)File: FORM3SEP2022.pdf | 13 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM5MARCH2022.pdf | 13 Dec 2022 |
| Proforma of Agreement for saleFile: Sale Agreement.pdf | 7 Dec 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report.pdf | 7 Dec 2022 |
| Details of encumbrancesFile: ENCUMBRANCE ON PROJECT RERA.pdf | 7 Oct 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200249071775_For_Asset_Based_Search_07_10_2022_12_06_02_121.pdf | 7 Oct 2022 |
| Other - FinanceFile: ENCUMBRANCE ON PROJECT RERA.pdf | 7 Oct 2022 |
| Building plan approvalFile: D WING AMEND PLAN COVERING LETTER.pdf | 4 Jul 2022 |
| Building plan approvalFile: D WING AMEND PLAN.pdf | 4 Jul 2022 |
| Building Plan Approval (IOD)File: D WING AMEND PLAN COVERING LETTER.pdf | 4 Jul 2022 |
| Building Plan Approval (IOD)File: D WING AMEND PLAN.pdf | 4 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: D WING Further CC signed.pdf | 4 Jul 2022 |
| Details of encumbrancesFile: Letter Fullerton.pdf | 4 Mar 2022 |
| Building plan approvalFile: Amend letter signed.pdf | 14 Aug 2021 |
| Building plan approvalFile: Amend letter signed.pdf | 14 Aug 2021 |
| Building plan approvalFile: Drawing amended.pdf | 14 Aug 2021 |
| Building Plan Approval (IOD)File: Amend letter signed.pdf | 14 Aug 2021 |
| Building Plan Approval (IOD)File: Amend letter signed.pdf | 14 Aug 2021 |
| Building Plan Approval (IOD)File: Drawing amended.pdf | 14 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC revalidation.pdf | 9 Aug 2019 |
| Declaration in FORM BFile: Form B revised.pdf | 9 Aug 2019 |
| Layout approvalFile: Sheet 1.pdf | 20 Jul 2019 |
| Copy of Layout Approval (in case of layout)File: Sheet 1.pdf | 20 Jul 2019 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 20 Jul 2019 |
| Proforma of Allotment letterFile: Sale Agreement Draft.pdf | 20 Jul 2019 |
| Building plan approvalFile: covering.pdf | 18 Jul 2019 |
| Building plan approvalFile: Sheet 1.pdf | 18 Jul 2019 |
| Building plan approvalFile: SHeet 2.pdf | 18 Jul 2019 |
| Building plan approvalFile: Sheet 3.pdf | 18 Jul 2019 |
| Building plan approvalFile: Sheet 4.pdf | 18 Jul 2019 |
| Building plan approvalFile: Sheet 5.pdf | 18 Jul 2019 |
| Building plan approvalFile: Sheet 6.pdf | 18 Jul 2019 |
| Building plan approvalFile: Sheet 7.pdf | 18 Jul 2019 |
| PAN CardFile: Pan Card.pdf | 18 Jul 2019 |
| Copy of the legal title reportFile: title certificate.pdf | 18 Jul 2019 |
| Details of encumbrancesFile: No encumbrance.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: covering.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: Sheet 1.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: SHeet 2.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: Sheet 3.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: Sheet 4.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: Sheet 5.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: Sheet 6.pdf | 18 Jul 2019 |
| Building Plan Approval (IOD)File: Sheet 7.pdf | 18 Jul 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 18 Jul 2019 |
| Declaration in FORM BFile: Form B.pdf | 18 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Certificate.pdf | 18 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engg Certificate.pdf | 18 Jul 2019 |
| Certificates of CA (Form 3)File: FORM 3 CA Certificate.pdf | 18 Jul 2019 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Nasar Associates GST certificate.pdf | 18 Jul 2019 |
| OtherFile: DA part I.pdf | 18 Jul 2019 |
| OtherFile: DA part II.pdf | 18 Jul 2019 |
| OtherFile: NOC Society.pdf | 18 Jul 2019 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Nasar Enclave Sale Building A and B WingP51800028733 | Andheri West, Mumbai Suburban | 174 | Mar 2021 | Ongoing | Jun 2026 | Not delivered |
| D Wing Building No 1 | TPS III Borivali West Mumbai 400092 | 19 | - | Completed | Dec 2023 | Dec 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 63 filed documents as one ZIP, foldered, with a manifest
Keep D Wing Building No. 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Borivali West6,700+ in Mumbai Suburban
Hiranandani Bluecrest
SHODEN DEVELOPERS PRIVATE LIMITED
KANAKIA PRIVAASA TOWER 1 & 2
KANAKIA TRANSPARENT DEVELOPERS PRIVATE LIM
BHOOMI AIRAVAT
Bhoomi Shashwat Estate Private limited
Shraddha Paradise
Shraddha Prime Projects Limited
UNIQUE REGALIA
UNIQUE SHANTI DEVELOPERS LLP
NICCO VANASHRI AND NICCO HEIGHTS
NEW INDIA CONSTRUCTION COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: M/s. Nasar Associates
M/s. Nasar Associates has 3 registrations on MahaRERA, including D Wing Building No. 1 and Nasar Apartment Composite Building B Wing. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if D Wing Building No. 1 is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of D Wing Building No. 1?
The registered promoter entity is M/s. Nasar Associates, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in D Wing Building No. 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for D Wing Building No. 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at D Wing Building No. 1?
The professionals named in the filing: Architect: Aashish Solanki Architect; Engineer: Clint Dos Santos; Chartered Accountant: Jignesh Shah & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in D Wing Building No. 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback