Home / Browse projects / Mumbai Suburban, Maharashtra / Crystal Palladian 207

Registration lapsed Litigation declared Commercial project

Crystal Palladian 207

By Sri Sai Nidhi Realtors Private Limited

RG-MH-30199 · RERA P51800031122 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 2 cases
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 80%
49 of 188Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

Crystal Palladian 207 is a Commercial project by Sri Sai Nidhi Realtors Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031122 on 5 Oct 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 139 of the 188 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameCrystal Palladian 207
  • TypeCommercial
  • Location
    • LINK ROAD
    • GHATKOPAR WEST
    • Kurla
    • Mumbai Suburban
    • 400086
  • Pincode400086
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800031122
  • ReraGenie IDRG-MH-30199

Builder

  • NameSri Sai Nidhi Realtors Private Limited
  • Entity typeCompany
  • CINU45200MH2006PTC161449
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsJatin Mehta, Darshan Dhami
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

4 months past promisethis monthRegisteredOct 2021First promiseDec 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Oct 2021
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2025)
  • Buildings1 building record
  • Documents filed98 files

Current status

74%139 of 188 units booked
90.0%Work done, per cost certificate

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
86 CENTRAL BNA16130188188

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

86 CENTRAL B: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed297

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots297
Closed/Covered297

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area777 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jul 2025

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI6680.0
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot No D 19 Veer Building Dattaray Road Santacruz West Mumbai 400056
Estimated costRs 74.42 cr
Cost incurredRs 66.98 cr
Work done90.0%
BuildingWingEstimatedIncurred
86 CENTRAL BNARs 44.65 crRs 44.65 cr
-NARs 29.77 crRs 22.33 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEnclosurre
ArchitectVishwas Satodia
ArchitectVishwas Jivraj Satodia
EngineerDiwakar Pathak
EngineerRamesh Balayya Rapelli
Chartered AccountantJ W & Associates
Chartered AccountantSawant and Kadrekar
Chartered AccountantTolia & Associates
Chartered AccountantSawant & Kadrekar LLP
PartnerRole in project
Sri Sai Nidhi Realtors Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA02012619243Dec 2025 → Jun 2026

Reason as filed by the promoterWe, SRISAI NIDHI REALTORS PRIVATE LIMITED, promoters of the real estate project "Crystal Palladian 207", bearing RERA Registration No. P51800031122, hereby submit a request for extension of the project completion period by six (6) months. The project was originally scheduled for completion on 30.12.2025. However, due to the following unavoidable and unforeseen circumstances, the progress of work has been affected: 1. Delays in material supply for construction of Car Parking Space. Despite diligent efforts and continuous work, these circumstances have caused delays beyond our control. We assure

Litigation declared2

CaseCourtStatus
100381/2020City Civil CourtOngoing
695/2021High Court of BombayOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form -1.pdf14 May 2026
Withdrawal Update Form 1File: Form -1.pdf14 May 2026
Withdrawal Update Form 1File: Form -1.pdf14 May 2026
Withdrawal Update Form 2File: FORM 2 CP 207.pdf14 May 2026
Withdrawal Update Form 2File: FORM 2 CP 207.pdf14 May 2026
Withdrawal Update Form 2File: FORM 2 CP 207.pdf14 May 2026
Withdrawal Update Form 3File: FORM 3 CP 207.pdf14 May 2026
Withdrawal Update Form 3File: FORM 3 CP 207.pdf14 May 2026
Withdrawal Update Form 3File: FORM 3 CP 207.pdf14 May 2026
Withdrawal Update Form 1File: form 1.pdf23 Mar 2026
Withdrawal Update Form 2File: form 2.pdf23 Mar 2026
Withdrawal Update Form 3File: Form-3 1.pdf23 Mar 2026
Withdrawal Update Form 1File: FORM1.pdf2 Jan 2026
Withdrawal Update Form 2File: FORM2.pdf2 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf2 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf24 Dec 2025
Withdrawal Update Form 2File: FORM 2.pdf24 Dec 2025
Withdrawal Update Form 3File: FORM 3.pdf24 Dec 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2025 03 31.pdf22 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2025 12 31.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2024 12 31.pdf25 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Crystal Palladian 207 - 2024 12 31.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2024 12 31 - C P 207.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2024 12 31.pdf2 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2024 09 30.pdf30 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Crystal Palladian 207 - 2024 09 30.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - C P 207 - 2024 06 30.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - C P 207 - 2024 09 30.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2024 09 30.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Crystal Palladian 207 - FY 2023-24.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2024 06 30.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Crystal Palladian 207 - 2024 06 30.pdf12 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Crystal Palladian 207 - FY 2023-24.pdf6 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2024 06 30.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Crystal Palladian 207 - 2024 03 31.pdf18 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2024 03 31.pdf23 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2021 12 31.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2022 03 31.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2022 06 30.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2022 09 30.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2022 12 31.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2023 03 31.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2023 06 30.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2023 09 30.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2023 12 31.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory - 2024 03 31.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Crystal Palladian 207 - FY 2021-22.pdf11 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Crystal Palladian 207 - FY 2022-23.pdf11 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2021 12 31.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2022 03 31.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2022 06 30.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2022 09 30.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2022 12 31.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2023 03 31.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2023 06 30.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2023 09 30.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2023 12 31.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Crystal Palladian 207 - 2024 03 31.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 cp207 12 2022.pdf8 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - Crystal Palladian 207 - 31 12 2023.pdf6 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 - Crystal Palladian 207 - 31 12 2023.pdf5 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - Crystal Palladian 207 - 30 09 2023.pdf5 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5 - Crystal Palladian 207 - 2022-23.pdf5 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2023 09.pdf9 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: SSN - CC dated 5th april, 22.pdf26 Sep 2023
Proforma of Agreement for saleFile: Proforma - Agreement for sale - SSN CrystalPalladian207.pdf26 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Crystal Palladian 207 - March 23.pdf5 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Crystal Palladian 207 - June 23.pdf5 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - 2023 06.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Crystal Palladian 207 - March 2023.pdf3 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CP JUNE 2022.pdf7 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CP 207 SEPT 2022.pdf7 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CP DEC 2022.pdf7 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CRYSTAL PALLADIAN FORM 1 MARCH 2022.pdf13 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CRYSTAL PALLADIAN FORM 1 JUNE 2022.pdf13 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CRYSTAL PALLADIAN FORM 1 SEPT 2022.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Crystal palladian 207.pdf1 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Crystal Palladian 207 Dec 2021.pdf8 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Crystal Palladian 207 March 2022.pdf21 Jun 2022
Disclosure of sold/ booked inventoryFile: Crystal Palladian 207 MAY 2022.pdf14 Jun 2022

How this compares with Mumbai Suburban

74%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Crystal Palladian 207 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHATKOPAR WEST6,700+ in Mumbai Suburban

2 kmCrystal Palladian 207Completed 114Lapsed / revoked 65Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 284 registered projects within 2 km.

Builder: Sri Sai Nidhi Realtors Private Limited

Sri Sai Nidhi Realtors Private Limited has 3 registrations on MahaRERA, including 86 CENTRAL A and Crystal Palladian 207. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Crystal Palladian 207 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Crystal Palladian 207 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Crystal Palladian 207?

The registered promoter entity is Sri Sai Nidhi Realtors Private Limited, a company as per the filing. Its CIN U45200MH2006PTC161449 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Crystal Palladian 207?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Crystal Palladian 207?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Crystal Palladian 207?

The professionals named in the filing: Architect: Enclosurre; Architect: Vishwas Satodia; Architect: Vishwas Jivraj Satodia; Engineer: Diwakar Pathak; Engineer: Ramesh Balayya Rapelli; Chartered Accountant: J W & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Crystal Palladian 207?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Crystal Palladian 207. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Crystal Palladian 207 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.