Home / Browse projects / Nagpur, Maharashtra / CRYSTAL PALACE

De-registered No litigation declared Residential / Group Housing project

CRYSTAL PALACE

By SAFA INFRA

RG-MH-03765 · RERA P50500030847 · Last updated on MahaRERA portal: 7 Dec 2024

Source: official MahaRERA filing

Red flags

  • De-registered
  • Possession 34 months past the filed date
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

CRYSTAL PALACE is a Residential / Group Housing project by SAFA INFRA in Nagpur, Maharashtra, registered with MahaRERA as P50500030847 on 20 Sep 2021. Possession was promised by 31 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameCRYSTAL PALACE
  • TypeResidential / Group Housing
  • Location
    • KORADI ROAD
    • ARYA NAGAR
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440030
  • Pincode440030
  • RERA no.P50500030847
  • ReraGenie IDRG-MH-03765

Builder

  • NameSAFA INFRA
  • Entity typePartnership
  • PartnersMOHAMMAD SHAFIK RAFIK AHMED SHAIKH, FIROJ AHEMAD IMADUL HUSSAIN SHAIKH
  • Declared earlier projects3 →

Key dates

34 months past promisethis monthRegisteredSep 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on20 Sep 2021
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed94 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CRYSTAL PALACENA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

CRYSTAL PALACE: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 7 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area381 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityNAGPUR IMPROVEMENT TRUST
Permissible FSI975.48
Proposed, not sanctioned975 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR Floor U NO A23 and 24 JP Exotica Circle NO 24 C S NO 2587 Gondvana chowk rajnagar 440013

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAJID KHAN
EngineerGulab Gaus Asif
Chartered AccountantCA ANKIT TALREJA
Chartered AccountantCA SUMIT AGRAWAL
PartnerRole in project
SAFA INFRA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500018556Dec 2023 → Dec 2024

Reason as filed by the promoterDECLARATION AND UNDERTAKING Project Details : Registration Number : P50500030847. CRYSTAL PALACE: CTS No.472, , Koradi Road, Arya Nagar,Village Nagpur, Taluka and District: Nagpur -440030;. The undersigned Authorised Signatory/Promoter hereby do Declare and Undertake as under:- 1) That project CRYSTAL PALACE on : CTS No.472, , Koradi Road, Arya Nagar,Village Nagpur, Taluka and District: Nagpur -440030; is completed 97% and the promoter will be applying for the completion of the project within 4 months from this day as the project is delayed due to various unforeseen circumstances, effects of t

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Oct 2024

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Crystel Palace Form 5.pdf7 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Crystal Palace_Form-2-Engineers Certificate_Sept-24.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_SEP-24.pdf23 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: CRYSTAL PALACE_RERA_Form 2A_MAR-24.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_MAR-24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_JUNE-24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_JUNE-24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_SEP-24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_SEP-24.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_SEP-24.pdf18 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM-4.pdf18 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Crystel Palace March 2024.pdf29 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Crystal Palace June 2024.pdf29 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Crystal Palace Form 1 June 2024.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf22 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5_MAR-22_.pdf20 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5_MAR-23_.pdf20 Feb 2024
Details of encumbrances concerned to FinanceFile: ENCUM_FINANCE_Prepared_Safa.pdf19 Feb 2024
Details of encumbrances concerned to FinanceFile: ENCUM_Legal_Prepared_Safa.pdf19 Feb 2024
Details of encumbrances concerned to LegalFile: ENCUM_FINANCE_Prepared_Safa.pdf19 Feb 2024
Details of encumbrances concerned to LegalFile: ENCUM_Legal_Prepared_Safa.pdf19 Feb 2024
Declaration about Commencement CertificateFile: form d (2) Safa.pdf19 Feb 2024
Declaration in FORM BFile: FORM-B.pdf19 Feb 2024
CERSAI detailsFile: Cersai Declaration_Safa.pdf19 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Firoz.pdf19 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Intreest Declaration -Shafik.pdf19 Feb 2024
Proforma of Allotment letterFile: Allotment Letter _Safa.pdf19 Feb 2024
Proforma of Agreement for saleFile: ATS- Safa.pdf19 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Disclosure_SAFA (2).pdf19 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation Report - ALLOTMENT LETTER _Safa.pdf19 Feb 2024
Deviation Report with respect to model copy of AgreementFile: ATS DEVIATION REPORT -Prepared_Safa.pdf19 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_SEP-22.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_DEC-22.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_MAR-23.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_JUNE-23.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_SEP-23.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_DEC-23.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_CRYSTAL PALACE_SEP-21.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_DEC-21.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_CRYSTAL PALACE_MAR-22.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_JUNE-22.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_JUNE-22.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_CRYSTAL PALACE_SEP-22.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_DEC-22.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_MAR-23.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1_CRYSTAL PALACE_JUNE-23.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_SEP-23.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-3_CRYSTAL PALACE_DEC-23.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_DEC-21.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_MAR-22.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_JUNE-22.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_SEP-22.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_DEC-22.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_JUNE-23.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_SEP-23.pdf9 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_CRYSTAL PALACE_DEC-23.pdf9 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A_CRYSTAL PALACE_MAR-22.pdf9 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A_CRYSTAL PALACE_MAR-23.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_CRYSTAL PALACE_JUNE-22.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_SEP-21.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_DEC-21.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_MAR-22.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_JUNE-22.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_SEP-22.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_DEC-22.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_MAR-23.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_JUNE-23.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_SEP-23.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_CRYSTAL PALACE_DEC-23.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TapScanner 03-22-2023-11꞉13.pdf3 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 Form 2.pdf3 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 Form 2.pdf3 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Crystal Palace qtr2 RERA 01-Apr-2023 19-52-37_compressed.pdf3 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Crystal Palace - qtr3 01-Apr-2023 19-47-12_compressed.pdf3 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera Certificate_q1_Fy 22-23_compressed.pdf17 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed.pdf17 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf25 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf25 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3_compressed.pdf25 Mar 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
KINGSWAY HEIGHTSPLOT NO. 15 ARYA NAGAR8CompletedJun 2021Jun 2021
ALI HEIGHTSPLOT NO. 5 & 6 ARYA NAGAR8CompletedJul 2019Jul 2019
ADIL HEIGHTSPLOT NO. 183 & 184 OM NAGAR8CompletedJun 2018Jun 2018

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CRYSTAL PALACE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ARYA NAGAR2,800+ in Nagpur

Builder: SAFA INFRA

SAFA INFRA has 1 registration on MahaRERA, including CRYSTAL PALACE. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that CRYSTAL PALACE shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CRYSTAL PALACE is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CRYSTAL PALACE?

The registered promoter entity is SAFA INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CRYSTAL PALACE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CRYSTAL PALACE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CRYSTAL PALACE?

The professionals named in the filing: Architect: SAJID KHAN; Engineer: Gulab Gaus Asif; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: CA SUMIT AGRAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CRYSTAL PALACE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CRYSTAL PALACE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CRYSTAL PALACE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.