Home / Browse projects / Mysore, Karnataka / COURTYARD
COURTYARD
By OXYGEN BUILD VENTURES PVT LTD.,
RG-KA-79387 · RERA PRM/KA/RERA/1268/378/PR/171118/001830
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
COURTYARD is a Residential/Group Housing project by OXYGEN BUILD VENTURES PVT LTD., in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/171118/001830 on 18 Nov 2017. Possession is promised by 15 Jul 2020. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameCOURTYARD
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- RERA no.PRM/KA/RERA/1268/378/PR/171118/001830
- ReraGenie IDRG-KA-79387
Builder
- NameOXYGEN BUILD VENTURES PVT LTD.,
- Entity typeCompany
- CINU45205KA2011PTC059553
- Authorized SignatoryThumilan C
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on18 Nov 2017
- Promised completion15 Jul 2020
- Revised completionRevised to 15 Jul 2020 (originally 15 Jul 2019)
- Buildings1 building record
- Documents filed50 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Courtyard | - | - | - | 23 | 0 | 23 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed50
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/171118/001830 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Oxygen Certification of Incorporation.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed.pdf | - |
| CA Certificate for Funds UtilizationFile: CA certificate - fund utilized.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required.pdf | - |
| AffidavitFile: Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: Encumbrance Certificate.pdf | - |
| Consent letter from 2/3rd of AllotteesFile: Consent Letter.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: Affidavit Under Sec 18.pdf | - |
| Document 2File: CC.pdf | - |
| Document 3File: Bank Statement.pdf | - |
| Commencement Certificate | - |
| Approved Building Plan | - |
| Approved Layout Plan | - |
| Proforma For Sale Deed | - |
| Proforma of Sale Agreement | - |
| Sale Deed | - |
| Approved Section Of Building | - |
| Area Development Plan Of Project Area | - |
| Allotment Letter | - |
| Broucher | - |
| Noc | - |
| Project Specifications | - |
| Encumbrance Certificate | - |
| Khatha | - |
| JDA | - |
| Balance Sheet 2015 - 2016File: Balance Sheet.jpg | - |
| Balance Sheet 2014 - 2015File: Balance Sheet.jpg | - |
| Balance Sheet 2013 - 2014File: Balance Sheet.jpg | - |
| Audited Profit and Loss Statement 2015 - 2016File: Audited Profit and Loss Statement.jpg | - |
| Audited Profit and Loss Statement 2014 - 2015File: Audited Profit and Loss Account.jpg | - |
| Audited Profit and Loss Statement 2013 - 2014File: Audited Profit and Loss Statement.jpg | - |
| Director's Report 2015 - 2016File: Director Report.pdf | - |
| Director's Report 2014 - 2015File: Director Report.pdf | - |
| Director's Report 2013 - 2014File: Director Report.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statement.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash Flow Statement.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor Report.pdf | - |
| Auditor's Report 2014 - 2015File: Auditor Report.pdf | - |
| Auditor's Report 2013 - 2014File: Auditor report.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR.jpg | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR.jpg | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR.jpg | - |
| Form B Affidavit | - |
| Prospectus/BrochureFile: Final Brochure.pdf | - |
| Advertisement Copy 1File: Advertisement.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_171118_001830.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep COURTYARD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: OXYGEN BUILD VENTURES PVT LTD.,
OXYGEN BUILD VENTURES PVT LTD., has 2 registrations on RERA Karnataka, including Hasiru and COURTYARD. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if COURTYARD is delayed beyond 15 Jul 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of COURTYARD?
The registered promoter entity is OXYGEN BUILD VENTURES PVT LTD.,, a company as per the filing. Its CIN U45205KA2011PTC059553 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in COURTYARD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in COURTYARD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback