COUNTRYSIDE PHASE III

By PATE DEVELOPERS

RG-MH-10933 · RERA P52100004089 · Last updated on MahaRERA portal: 5 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 60 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
24 of 29Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

COUNTRYSIDE PHASE III is a Plotted project by PATE DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100004089 on 7 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 60 months from the original filing. 5 of the 29 units on this registration are recorded sold or booked.

At a glance

Project

  • NameCOUNTRYSIDE PHASE III
  • TypePlotted
  • Location
    • SANGRUN GAOTHAN
    • SANGRUN
    • Sangarun
    • Haveli
    • Pune
    • 412115
  • Pincode412115
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004089
  • ReraGenie IDRG-MH-10933

Builder

  • NamePATE DEVELOPERS
  • Entity typePartnership
  • PartnersBALKRISHNA KASHINATH PATE, PRAMOD DATTATRAYA WANI, PUSHPA BALKRISHNA PATE, NILESH BALKRISHNA PATE
  • Other registrations3 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 31 Dec 2019)
  • BuildingsNot stated in filing
  • Documents filed37 files

Current status

17%5 of 29 units booked

Figures as on 5 Jan 2024, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities19

As on 5 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes30%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Multipurpose Hall with PantryYes0%
Kids Play AreaYes0%
Senior Citizen AreaYes0%
OUTDOOR FITNESS AREAYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,662 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PRABODH ARTHA SANCHAY PVT LTDPethPune

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTILAK ROAD, PUNE

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANKUR ASSOCIATES
PartnerRole in project
PATE DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013635Dec 2019 → Dec 2024

Reason as filed by the promoterRise in cost of raw materials, covid & other factors

EXT52100012195Dec 2019 → Dec 2022

Reason as filed by the promoterDue to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis

EXT52100005199Dec 2019 → Dec 2020

Reason as filed by the promoterThere is delay in the completion of the project due to following reasons which are beyond our direct control. 1. After Implementation of GST from July 2017 and repeated changes in the applicable provisions to real estate developers, lot of material orders had to be revised and reworked from time to time e.g. Lift (major long haul item), this has adversely affected the speed of our site work. 2. On the sale side, there is a slowdown in the demand for real estate after the implementation of GST and demonetization, resulting in lower volume of booking and sale for the project. With the revised re

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Jan 2024

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Countryside Completion.pdf5 Jan 2024
Certificates of CA (Form 3)File: Form 3_Phase III (9th Dec 2019).pdf6 Oct 2023
Certificates of CA (Form 3)File: Form 3_Countryside Phase 3 (3-3-2022)_compressed.pdf6 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Countryside PHASE lll FY 2021-22.pdf6 Oct 2023
Proforma of Agreement for saleFile: COUNTRYSIDE Agreement to Sale Phase 3 DRAFT.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (2021-22) Countryside - Phase 3.pdf29 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Declaration.pdf26 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (2020-21) Countryside - Phase 3.pdf21 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A (2020-21) Countryside - Phase 3.pdf21 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Countryside Phase III FY 2017-18.pdf21 Jul 2022
Details of encumbrances concerned to LegalFile: download.pdf18 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank.pdf18 Jul 2022
Deviation Report with respect to Allotment letterFile: allotment letter.pdf18 Jul 2022
Deviation Report with respect to model copy of AgreementFile: Agreement of Sale.pdf18 Jul 2022
Declaration about Commencement CertificateFile: Form D.pdf11 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf11 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold.pdf11 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 18-19.pdf11 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20.pdf11 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf11 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Countryside III.pdf22 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 COUNTRYSIDE III.pdf22 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Countryside Form 1 Phase III 31st Dec 17.pdf8 Feb 2018
Certificates of CA (Form 3)File: form_-2_-_phase_III Dec 17.pdf1 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Countryside III.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: countryside ph 3.pdf31 Jul 2017
Certificates of CA (Form 3)File: Countryside Phase 3 form 3.pdf31 Jul 2017
Declaration in FORM BFile: Countryside III Form B.pdf29 Jul 2017
Details of encumbrancesFile: Countryside III Encumbrance.pdf28 Jul 2017
Proforma of Allotment letterFile: COUNTRYSIDE III -OPEN PLOT.pdf28 Jul 2017
Building plan approval or NA orderFile: building plan.pdf24 Jul 2017
Layout approvalFile: building plan.pdf24 Jul 2017
PAN CardFile: pan.pdf24 Jul 2017
Copy of the legal title reportFile: title.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: building plan.pdf24 Jul 2017
Building Plan Approval (IOD)File: building plan.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: na.pdf24 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
FIESTASR NO 35 HISSA NO 2 AND PART63CompletedDec 2015Late, Jun 2016
SIGNORIYASR NO 1 HISSA NO 10 TO 16 PLOT NO 56 BAVDHAN PUNE 4110218CompletedDec 2014May 2014

How this compares with Pune

17%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep COUNTRYSIDE PHASE III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SANGRUN13,700+ in Pune

2 kmCOUNTRYSIDE PHASE IIICompleted 23Lapsed / revoked 11Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: PATE DEVELOPERS

PATE DEVELOPERS has 4 registrations on MahaRERA, including WEST COAST PARK PHASE II and COUNTRYSIDE PHASE 1. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that COUNTRYSIDE PHASE III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if COUNTRYSIDE PHASE III is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of COUNTRYSIDE PHASE III?

The registered promoter entity is PATE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in COUNTRYSIDE PHASE III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for COUNTRYSIDE PHASE III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at COUNTRYSIDE PHASE III?

The professionals named in the filing: Architect: ANKUR ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in COUNTRYSIDE PHASE III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About COUNTRYSIDE PHASE III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save COUNTRYSIDE PHASE III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.