Home / Browse projects / Palghar, Maharashtra / Cosmos Legend

Registration lapsed No litigation declared Others project

Cosmos Legend

By Cosmos Associates

RG-MH-56256 · RERA P99000006962 · Last updated on MahaRERA portal: 3 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 55 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2022Possession promised55 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 97%
1Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

Cosmos Legend is a Others project by Cosmos Associates in Palghar, Maharashtra, registered with MahaRERA as P99000006962 on 16 Aug 2017. Possession was promised by 30 Mar 2022 and is now 55 months past that date. The completion date has moved by 36 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCosmos Legend
  • TypeOthers
  • Location
    • Chikhal Dongre Road
    • Virar
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000006962
  • ReraGenie IDRG-MH-56256

Builder

  • NameCosmos Associates
  • Entity typePartnership
  • PartnersAnup Ashok Mehta, Jayesh Vinaychand Doshi, Cosmos Skyline Homes Pvt Ltd Company, Cosmos Prime Projects Ltd Company, Manish Gyanchand Mehta

Key dates

55 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toMar 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Mar 2022
  • Revised completionRevised to 30 Mar 2022 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Cosmos AssociatesNA340000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 97%.

Cosmos Associates: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.48%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.47%

Progress on shared amenities15

As on 3 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes97%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes85%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes32%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered18

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,607 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI18384.81
Proposed, not sanctioned18,385 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManik Motwani Marg, Fort, Mumbai - 400 001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Wade and Associates
EngineerNimisha Structural Design Academy
PartnerRole in project
Cosmos Associates-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000006288Mar 2019 → Sep 2021

Reason as filed by the promoterDear Sir, Due to following two major reason we are asking for extension. 1. Covid 19 which have made situation beyond our control to manage pending work. 2. We have applied to VVCMC in Sept 2019 which is still awaited from their side. You are requested to accept our extension application for 12 months. Detailed application is attached herewith. Also attaching consent taken from allottees.

EXT99000002414Mar 2019 → Mar 2020

Reason as filed by the promoterProject work completed & applied for Occupancy Certificate

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000022971Mr. Akshaya Navnitlal ShahCosmos Associates22/01/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Apr 2025

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_compressed.pdf3 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc letter.pdf19 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc letter 2nd page.pdf19 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc letter.pdf19 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc letter 2nd page.pdf19 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf29 Dec 2023
Certificates of CA (Form 3)File: fORM 3.pdf18 Dec 2023
OtherFile: order.pdf21 Sep 2023
Certificates of CA (Form 5)File: RERA Form 5 - Cosmos Associates - FY 21-22.pdf8 Apr 2023
Certificates of CA (Form 3)File: Form 3.pdf5 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate FORM - 5 18-19.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2 Certificates of CA (Form 5).pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 3 Certificates of CA (Form 5).pdf28 Mar 2023
Certificates of CA (Form 5)File: CA Certificate FORM - 5 19-20.pdf23 Jan 2023
Certificates of CA (Form 5)File: CA Certificate FORM - 5 20-21.pdf23 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Cosmos Associates Format A.pdf12 Sep 2022
CERSAI detailsFile: cersai.pdf10 Sep 2022
Declaration about Commencement CertificateFile: Format D Declaration.pdf25 Jul 2022
OtherFile: Format D Declaration.pdf25 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Cosmos Associates Form 2A quality assurance 19-20 (1).pdf6 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Cosmos Associates 2020-21.pdf6 Jul 2022
Disclosure of sold/ booked inventoryFile: COSMOS LEGEND.pdf2 Jul 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: legend.pdf24 Jun 2021
OtherFile: Application.pdf5 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf19 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf19 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Legend architect Certificate.pdf9 Aug 2019
Certificates of CA (Form 5)File: FORM 5.pdf31 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect.pdf21 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Legend Engineer Certificate.pdf21 Mar 2018
Building plan approvalFile: Legend Commencement Certificate(1).pdf31 Jul 2017
Layout approvalFile: Floor plan A wing Legend.pdf31 Jul 2017
Layout approvalFile: Floor plan b wing legend.pdf31 Jul 2017
PAN CardFile: Cosmos Associates PAN.pdf31 Jul 2017
Copy of the legal title reportFile: Legend Title Certificate (1).pdf31 Jul 2017
Details of encumbrancesFile: Legend Encumbrance letter.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Floor plan A wing Legend.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Floor plan b wing legend.pdf31 Jul 2017
Building Plan Approval (IOD)File: Legend Commencement Certificate(1).pdf31 Jul 2017
Declaration in FORM BFile: FORM B COSMOS ASSOCIATES.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate legend(1).pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Cosmos Legend Engineer Report (1).pdf31 Jul 2017
Certificates of CA (Form 3)File: resize-Cosmos Legend Form 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Akhil Allottment letter COSMOS LEGEND.pdf31 Jul 2017
Proforma of Allotment letterFile: Akhil Cosmos Legend Draft Agreement for RERA.pdf31 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 36 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Cosmos Legend on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Virar3,200+ in Palghar

2 kmCosmos LegendCompleted 37Lapsed / revoked 20Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: Cosmos Associates

Cosmos Associates has 1 registration on MahaRERA, including Cosmos Legend. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that Cosmos Legend shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Cosmos Legend is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Cosmos Legend?

The registered promoter entity is Cosmos Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Cosmos Legend?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Cosmos Legend?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Cosmos Legend?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Cosmos Legend?

The professionals named in the filing: Architect: Ajay Wade and Associates; Engineer: Nimisha Structural Design Academy. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Cosmos Legend?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Cosmos Legend. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Cosmos Legend to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.