COSMOS HORIZON PHASE II
RG-MH-68301 · RERA P51700017557 · Last updated on MahaRERA portal: 30 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
COSMOS HORIZON PHASE II is a Residential / Group Housing project by Concorde Developers in Thane, Maharashtra, registered with MahaRERA as P51700017557 on 28 Aug 2018. Possession was promised by 30 Mar 2024 and is now 31 months past that date.
At a glance
Project
- NameCOSMOS HORIZON PHASE II
- TypeResidential / Group Housing
- Location
- POKHRAN ROAD 1
- MAJIVADE
- Thane (M Corp.)
- Thane
- 400606
- Pincode400606
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700017557
- ReraGenie IDRG-MH-68301
Builder
- NameConcorde Developers
- Entity typePartnership
- PartnersPradeep Ghisulal Rathod, Pankaj Ghisulal Rathod, Sanjay Chandan Parekh, Cosmos Skyline Homes Pvt Ltd Cosmos Skyline Homes Pvt Ltd, Cosmos Prime Projects Ltd Cosmos Prime Projects Ltd, Manish Gyanchand Mehta, Suresh Yedba Jantre
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on28 Aug 2018
- Promised completion30 Mar 2024
- Revised completionNone
- Buildings2 building records
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING 5 SUNLITE | NA | 30 | 0 | 0 | 0 | 0 |
| BUILDING 6 MOONLITE | NA | 30 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING 5 SUNLITE91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING 6 MOONLITE91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed182
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING 5 SUNLITE | 167 | 7 | 174 |
| BUILDING 6 MOONLITE | 1 | 7 | 8 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUVARNA GHOSH |
| Engineer | AJAY MAHALE & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Concorde Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 May 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Aug 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 May 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 May 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Jun 2024
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form 3 March 24_compressed.pdf | 30 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A quality assurance 2024.pdf | 9 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -5.pdf | 6 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -6.pdf | 6 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 18 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 7 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bldg no 6 ARCHITECT CERTIFICATE.pdf | 7 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 23 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 12 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 30 Mar 2023 |
| Certificates of CA (Form 3)File: Form 3 FY 2021-22_11zon.pdf | 29 Mar 2023 |
| CERSAI detailsFile: CERSAI.pdf | 10 Sep 2022 |
| Declaration about Commencement CertificateFile: Declaration CC.pdf | 14 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf | 14 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 14 Jun 2022 |
| Certificates of CA (Form 3)File: Form 3.pdf | 14 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf | 14 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Declaration.pdf | 6 Jun 2022 |
| Certificates of CA (Form 3)File: Form 3 2019-20.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA FORM - 5 FY 2019-20.pdf | 28 Jun 2021 |
| Proforma of Allotment letterFile: DRAFT - COSMOS HORIZON RERA AGREEMENT FOR SALE - FOR 2BHK.pdf | 2 Feb 2021 |
| OtherFile: Architect Certificate moonlight.pdf | 15 Oct 2020 |
| OtherFile: Architect Certificate- sunlite.pdf | 15 Oct 2020 |
| Details of Restarting of Construction work post lockdownFile: Concorde Developers COVID Declaration.pdf | 23 Jun 2020 |
| OtherFile: Architect Certificate sunlite March 2020.pdf | 16 Jun 2020 |
| OtherFile: Architect certificate moonlite March 2020.pdf | 16 Jun 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - concorde Developers.pdf | 21 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 Bldg no 5.pdf | 26 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 Bdg no 6.pdf | 26 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 (Bldg no 5).pdf | 26 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 (Bldg no 6).pdf | 26 Sep 2019 |
| Details of encumbrancesFile: No Encumbrance Certificate.pdf | 20 Aug 2018 |
| Proforma of Allotment letterFile: Bldg No 5 6 RERA AGreement.pdf | 20 Aug 2018 |
| Proforma of Allotment letterFile: Horizon Allotment For Bldg No 5 6.pdf | 20 Aug 2018 |
| Layout approvalFile: Resized FLOOR PLAN 2-ilovepdf-compressed-ilovepdf-compressed.pdf | 17 Aug 2018 |
| Layout approvalFile: New FLOOR PLAN 1-ilovepdf-compressed compressed.pdf | 17 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: Resized FLOOR PLAN 2-ilovepdf-compressed-ilovepdf-compressed.pdf | 17 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: New FLOOR PLAN 1-ilovepdf-compressed compressed.pdf | 17 Aug 2018 |
| Declaration in FORM BFile: FORM B DATED 09-07-2018-ilovepdf-compressed.pdf | 17 Aug 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_reduce.pdf | 17 Aug 2018 |
| Certificates of CA (Form 3)File: Form 3_reduce (1).pdf | 17 Aug 2018 |
| OtherFile: PLINTH CERTIFICATE Bldg 5 and 6.pdf | 17 Aug 2018 |
| OtherFile: IOD.pdf | 17 Aug 2018 |
| OtherFile: DECLARATION DATED 20-06-2018-ilovepdf-compressed.pdf | 17 Aug 2018 |
| Building plan approvalFile: IOD.pdf | 25 May 2018 |
| PAN CardFile: Concorde Dev.PDF | 25 May 2018 |
| Copy of the legal title reportFile: TITLE CERTIFICATE (1).pdf | 25 May 2018 |
| Building Plan Approval (IOD)File: IOD.pdf | 25 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: cc1.pdf | 25 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: cc2.pdf | 25 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 .pdf | 25 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 .pdf | 25 May 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 52 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep COSMOS HORIZON PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAJIVADE7,600+ in Thane
Filed coordinates, straight-line distance. 394 registered projects within 2 km.
Jai Bhavani Chs Ltd SRA Project
HEER REALTY VENTURES PVT LTD
Glorio Grand Central
Ekdant Constructions and Developers Privat
Veer Hills
Yash Infra
L and T Realty Evara Heights T1
ELANTE PROPERTIES PRIVATE LIMITED
Tenx District 9 Tower B
Raymond Realty Limited
MAHAVIR VISTA AND VISTA POINT
VINAYAK DEVELOPERS
See every Thane project, with the district possession charts
Builder: Concorde Developers
Concorde Developers has 2 registrations on MahaRERA, including Cosmos Horizon and COSMOS HORIZON PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that COSMOS HORIZON PHASE II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if COSMOS HORIZON PHASE II is delayed beyond 30 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of COSMOS HORIZON PHASE II?
The registered promoter entity is Concorde Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in COSMOS HORIZON PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for COSMOS HORIZON PHASE II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at COSMOS HORIZON PHASE II?
The professionals named in the filing: Architect: SUVARNA GHOSH; Engineer: AJAY MAHALE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in COSMOS HORIZON PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback