Home / Browse projects / Thane, Maharashtra / COSMOS HORIZON PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

COSMOS HORIZON PHASE II

By Concorde Developers

RG-MH-68301 · RERA P51700017557 · Last updated on MahaRERA portal: 30 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

COSMOS HORIZON PHASE II is a Residential / Group Housing project by Concorde Developers in Thane, Maharashtra, registered with MahaRERA as P51700017557 on 28 Aug 2018. Possession was promised by 30 Mar 2024 and is now 31 months past that date.

At a glance

Project

  • NameCOSMOS HORIZON PHASE II
  • TypeResidential / Group Housing
  • Location
    • POKHRAN ROAD 1
    • MAJIVADE
    • Thane (M Corp.)
    • Thane
    • 400606
  • Pincode400606
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700017557
  • ReraGenie IDRG-MH-68301

Builder

  • NameConcorde Developers
  • Entity typePartnership
  • PartnersPradeep Ghisulal Rathod, Pankaj Ghisulal Rathod, Sanjay Chandan Parekh, Cosmos Skyline Homes Pvt Ltd Cosmos Skyline Homes Pvt Ltd, Cosmos Prime Projects Ltd Cosmos Prime Projects Ltd, Manish Gyanchand Mehta, Suresh Yedba Jantre
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

31 months past promisethis monthRegisteredAug 2018PromisedMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Aug 2018
  • Promised completion30 Mar 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 5 SUNLITENA300000
BUILDING 6 MOONLITENA300000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

BUILDING 5 SUNLITE91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING 6 MOONLITE91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 30 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed182

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots182
Closed/Covered168
Open Space14
BuildingClosed/CoveredOpen SpaceTotal
BUILDING 5 SUNLITE1677174
BUILDING 6 MOONLITE178

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area477 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7841.25
Proposed, not sanctioned7,841 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGEORGE MANSION, UTALSAR, THANE WEST - 400601

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUVARNA GHOSH
EngineerAJAY MAHALE & ASSOCIATES
PartnerRole in project
Concorde Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Aug 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jun 2024

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3 March 24_compressed.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A quality assurance 2024.pdf9 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -5.pdf6 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 -6.pdf6 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf18 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf7 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bldg no 6 ARCHITECT CERTIFICATE.pdf7 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf23 Jan 2024
Certificates of CA (Form 3)File: Form 3.pdf12 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf30 Mar 2023
Certificates of CA (Form 3)File: Form 3 FY 2021-22_11zon.pdf29 Mar 2023
CERSAI detailsFile: CERSAI.pdf10 Sep 2022
Declaration about Commencement CertificateFile: Declaration CC.pdf14 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf14 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf14 Jun 2022
Certificates of CA (Form 3)File: Form 3.pdf14 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf14 Jun 2022
Disclosure of sold/ booked inventoryFile: Declaration.pdf6 Jun 2022
Certificates of CA (Form 3)File: Form 3 2019-20.pdf28 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA FORM - 5 FY 2019-20.pdf28 Jun 2021
Proforma of Allotment letterFile: DRAFT - COSMOS HORIZON RERA AGREEMENT FOR SALE - FOR 2BHK.pdf2 Feb 2021
OtherFile: Architect Certificate moonlight.pdf15 Oct 2020
OtherFile: Architect Certificate- sunlite.pdf15 Oct 2020
Details of Restarting of Construction work post lockdownFile: Concorde Developers COVID Declaration.pdf23 Jun 2020
OtherFile: Architect Certificate sunlite March 2020.pdf16 Jun 2020
OtherFile: Architect certificate moonlite March 2020.pdf16 Jun 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - concorde Developers.pdf21 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 Bldg no 5.pdf26 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 Bdg no 6.pdf26 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 (Bldg no 5).pdf26 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificates Form 1 (Bldg no 6).pdf26 Sep 2019
Details of encumbrancesFile: No Encumbrance Certificate.pdf20 Aug 2018
Proforma of Allotment letterFile: Bldg No 5 6 RERA AGreement.pdf20 Aug 2018
Proforma of Allotment letterFile: Horizon Allotment For Bldg No 5 6.pdf20 Aug 2018
Layout approvalFile: Resized FLOOR PLAN 2-ilovepdf-compressed-ilovepdf-compressed.pdf17 Aug 2018
Layout approvalFile: New FLOOR PLAN 1-ilovepdf-compressed compressed.pdf17 Aug 2018
Copy of Layout Approval (in case of layout)File: Resized FLOOR PLAN 2-ilovepdf-compressed-ilovepdf-compressed.pdf17 Aug 2018
Copy of Layout Approval (in case of layout)File: New FLOOR PLAN 1-ilovepdf-compressed compressed.pdf17 Aug 2018
Declaration in FORM BFile: FORM B DATED 09-07-2018-ilovepdf-compressed.pdf17 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_reduce.pdf17 Aug 2018
Certificates of CA (Form 3)File: Form 3_reduce (1).pdf17 Aug 2018
OtherFile: PLINTH CERTIFICATE Bldg 5 and 6.pdf17 Aug 2018
OtherFile: IOD.pdf17 Aug 2018
OtherFile: DECLARATION DATED 20-06-2018-ilovepdf-compressed.pdf17 Aug 2018
Building plan approvalFile: IOD.pdf25 May 2018
PAN CardFile: Concorde Dev.PDF25 May 2018
Copy of the legal title reportFile: TITLE CERTIFICATE (1).pdf25 May 2018
Building Plan Approval (IOD)File: IOD.pdf25 May 2018
Commencement Certificates / NA Order for plotted developmentFile: cc1.pdf25 May 2018
Commencement Certificates / NA Order for plotted developmentFile: cc2.pdf25 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 .pdf25 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 .pdf25 May 2018

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep COSMOS HORIZON PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAJIVADE7,600+ in Thane

2 kmCOSMOS HORIZON PHASE IICompleted 175Lapsed / revoked 63Other 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 394 registered projects within 2 km.

Builder: Concorde Developers

Concorde Developers has 2 registrations on MahaRERA, including Cosmos Horizon and COSMOS HORIZON PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that COSMOS HORIZON PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if COSMOS HORIZON PHASE II is delayed beyond 30 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of COSMOS HORIZON PHASE II?

The registered promoter entity is Concorde Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in COSMOS HORIZON PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for COSMOS HORIZON PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at COSMOS HORIZON PHASE II?

The professionals named in the filing: Architect: SUVARNA GHOSH; Engineer: AJAY MAHALE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in COSMOS HORIZON PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About COSMOS HORIZON PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save COSMOS HORIZON PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.