ReraGenieLog inGet a buyer report

Home / Browse projects / Amravati, Maharashtra / Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG

Completed No litigation declared Residential / Group Housing project

Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG

By Amravati Housing And Area Development Board Amravati

RG-MH-01324 · RERA P50300015120 · Last updated on MahaRERA portal: 8 Jun 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Amravati registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
296 of 4785Construction stages doneacross 436 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG is a Residential / Group Housing project by Amravati Housing And Area Development Board Amravati in Amravati, Maharashtra, registered with MahaRERA as P50300015120 on 31 Jan 2018. The registration is recorded completed; possession was promised by 30 Dec 2022.

At a glance

Project

  • NameConstruction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG
  • TypeResidential / Group Housing
  • Location
    • Old MHADA colony road
    • Akoli
    • Amravati (M Corp.)
    • Amravati
    • 444606
  • Pincode444606
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50300015120
  • ReraGenie IDRG-MH-01324

Builder

  • NameAmravati Housing And Area Development Board Amravati
  • Entity typePublic Authority
  • ChairpersonSubhash Namdeo Shinde
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2018PromisedDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Jan 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings436 building records
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ZNA50000
0NA00000
Building ANA50000
Building BNA50000
Building CNA50000
Building DNA50000
Building ENA50000
Building FNA50000
Building GNA50000
Building HNA50000
Building INA50000
Building JNA50000
Building KNA50000
Building LNA50000
Building MNA50000
Building NNA50000
Building ONA50000
Building PNA50000
Building QNA50000
Building RNA50000
Building SNA50000
Building TNA50000
Building UNA50000
Building VNA50000
Building WNA50000
Building XNA50000
Building YNA50000
Building M-1 ANA00000
Building M-1 BNA00000
Building M-2 ANA00000
Building M-2BNA00000
Building M-3 ANA00000
Building M-3 BNA00000
Building M-4 ANA00000
Building M-4 BNA00000
Building M-5 ANA00000
Building M-5 BNA00000
Building M-6 ANA00000
Building M-6 BNA00000
Building M-7 ANA00000
Building M-7 BNA00000
Building M-8 ANA00000
Building M-8 BNA00000
Building M-9 ANA00000
Building M-9 BNA00000
Building M-10 ANA00000
Building M-10 BNA00000
Building M-11 ANA00000
Building M-11 BNA00000
Building M-12 ANA00000
Building M-12 BNA00000
Building M-13 ANA00000
Building M-13 BNA00000
Building M-14 ANA00000
Building M-14 BNA00000
Building M-15 ANA00000
Building M-15 BNA00000
Building M-16 ANA00000
Building M-16 BNA00000
Building M-17 ANA00000
Building M-17 BNA00000
Building M-18 ANA00000
Building M-18 BNA00000
Building M-19 ANA20000
Building M-19 BNA20000
Building M-20 ANA00000
Building M-20 BNA00000
Building M-21 ANA00000
Building M-21 BNA00000
Building M-22 ANA00000
Building M-22 BNA00000
Building M-23 ANA00000
Building M-23 BNA00000
Building M-24 ANA00000
Building M-24 BNA00000
Building M-25 ANA00000
Building M-25 BNA00000
Building M-26 ANA00000
Building M-26 BNA00000
Building M-27 ANA00000
Building M-27 BNA00000
Building M-28 ANA00000
Building M-28 BNA00000
Building M-29 ANA00000
Building M-29 BNA00000
Building M-30 ANA00000
Building M-30 BNA00000
Building M-31 ANA00000
Building M-31 BNA00000
Building M-32 ANA00000
Building M-32 BNA00000
Building M-33 ANA00000
Building M-33 BNA00000
Building M-34 ANA00000
Building M-34 BNA00000
Building M-35 ANA00000
Building M-35 BNA00000
Building M-36 ANA00000
Building M-36 BNA00000
Building M-37 ANA00000
Building M-37 BNA00000
Building M-38 ANA20000
Building M-38 BNA20000
Building M-39 ANA00000
building M-39 BNA00000
Building M-40 ANA00000
Building M-40 BNA00000
Building M-41 ANA00000
Building M-41 BNA00000
Building M-42 ANA00000
Building M-42 BNA00000
Building M-43 ANA00000
Building M-43 BNA00000
Building M-44 ANA00000
Building M-44 BNA00000
Building M-45 ANA00000
Building M-45 BNA00000
Building M-46 ANA00000
Building M-47 ANA00000
Building M-48 ANA00000
Building M-48 BNA00000
Building M-49 ANA00000
Building M-49 BNA00000
Building M-50 ANA00000
Building M-50 BNA00000
Building M-51 ANA00000
Building M-51 BNA00000
Building M-52 ANA00000
Building M-52 BNA00000
Building M-53 ANA00000
Building M-53 BNA00000
Building M-54 ANA00000
Building M-54 BNA00000
Building M-55 ANA00000
Building M-55 BNA00000
Building M-56 ANA00000
Building M-56 BNA00000
Building M-57 ANA00000
Building M-57 BNA00000
Building M-58 ANA00000
Building M-58 BNA00000
Building M-59 ANA00000
Building M-59 BNA00000
Building M-60 ANA00000
BUilding M-60 BNA00000
Building M-61 ANA00000
Building M-61 BNA00000
Building M-62 ANA00000
Building M-62 BNA00000
Building M-63 ANA00000
Building M-63 BNA00000
Building M-64 ANA00000
Building M-64 BNA00000
Building M-65 ANA00000
Building M-65 BNA00000
Building M-66 ANA00000
Building M-66 BNA00000
Building M-67 ANA00000
Building M-67 BNA00000
Building M-68 ANA00000
Building M-68 BNA00000
Building M-69 ANA00000
Building M-69 BNA00000
Building M-70 ANA00000
Building M-70 BNA00000
Building M-71 ANA00000
Building M-71 BNA00000
Building M-72 ANA00000
Building M-72 BNA00000
Building M-73 ANA00000
Building M-73 BNA00000
Building M-74 ANA00000
Building M-74 BNA00000
Building M-75 ANA00000
Building M-75 BNA00000
Building M-76 ANA00000
Building M-76 BNA00000
Building M-77 ANA00000
Building M-77 BNA00000
Building M-78 ANA00000
Building M-78 BNA00000
Building M-79 ANA00000
Building M-79 BNA00000
Building M-80 ANA00000
Building M-80 BNA00000
Building M-81 ANA00000
Building M-81 BNA00000
Building M-82 ANA00000
Building M-82 BNA00000
Building M-83 ANA00000
Building M-83 BNA00000
Building M-84 ANA00000
Building M-84 BNA00000
Building M-85 ANA00000
Building M-85 BNA00000
Building M-86 ANA00000
Building M-86 BNA00000
Building M-87 ANA00000
Building M-87 BNA00000
Building M-88 ANA00000
Building M-88 BNA00000
Building M-89 ANA00000
Building M-89 BNA00000
Building M-90 ANA00000
Building M-90 BNA00000
Building M-91 ANA00000
Building M-91 BNA00000
Building M-92 ANA00000
Building M-93 ANA00000
Building M-93 BNA00000
Building M-94 ANA00000
Building M-94 BNA00000
Building M-95 ANA00000
Building M-95 BNA00000
Building M-96 ANA00000
Building M-96 BNA00000
Building M-97 ANA00000
Building M-97 BNA00000
Building M-98 ANA00000
Building M-98 BNA00000
Building M-99 ANA00000
Building M-99 BNA00000
Building M-100 ANA00000
Building M-100 BNA00000
Building M-101 ANA00000
Building M-101 BNA00000
Building M-102 ANA00000
Building M-102 BNA00000
Building M-103 ANA00000
Building M-103 BNA00000
Building M-104 ANA00000
Building M-104 BNA00000
Building M-105 ANA00000
Building M-105 BNA00000
Building M-106 ANA00000
Building M-106 BNA00000
Building M-107 ANA00000
Building M-107 BNA00000
Building M-108 ANA00000
Building M-109 ANA00000
Building M-109 BNA00000
Building M-110 ANA00000
Building M-110 BNA00000
Building M-111 ANA00000
Building M-111 BNA00000
Building M-112 ANA00000
Building M-112 BNA00000
Building M-113 ANA00000
Building M-113 BNA00000
Building M-114 ANA00000
Building M-114 BNA00000
Building M-115 ANA00000
Building M-115 BNA00000
Building M-116 ANA00000
Building M-116 BNA00000
Building M-117 ANA00000
Building M-117 BNA00000
Building M-118 ANA00000
Building M-118 BNA00000
Building M-119 ANA00000
Building M-119 BNA00000
Building M-120 ANA00000
Building M-120 BNA00000
Building M-121 ANA00000
Building M-121 BNA00000
Building M-122 ANA00000
Building M-122 BNA00000
Building M-123 ANA00000
Building M-123 BNA00000
Building M-124 ANA00000
Building M-124 BNA00000
Building M-125 ANA00000
Building M-125 BNA00000
Building M-126 ANA00000
Building M-126 BNA00000
Building M-127 ANA00000
Building M-127 BNA00000
Building M-128 ANA00000
Building M-128 BNA00000
Building M-129 ANA00000
Building M-129 BNA00000
Building M-130 ANA00000
Building M-130 BNA00000
Building M-131 ANA00000
Building M-131 BNA00000
Building M-132 ANA00000
Building M-132 BNA00000
Building M-133 ANA00000
Building M-133 BNA00000
Building M-134 ANA00000
Building M-134 BNA00000
Building M-135 ANA00000
Building M-135 BNA00000
Building M-136 ANA00000
Building M-136 BNA00000
Building M-137 ANA00000
Building M-137 BNA00000
Building M-138 ANA00000
Building M-138 BNA00000
Building M-139 ANA00000
Building M-139 BNA00000
Building M-140 ANA00000
Building M-140 BNA00000
Building M-141 ANA00000
Building M-141 BNA00000
Building M-142 ANA00000
Building M-142 BNA00000
Building M-143 ANA00000
Building M-143 BNA00000
Building M-144 ANA00000
Building M-144 BNA00000
Building M-145 ANA00000
Building M-145 BNA00000
Building M-146 ANA00000
Building M-146 BNA00000
Building M-147 ANA00000
Building M-147 BNA00000
Building M-148 ANA00000
Building M-148 BNA00000
Building M-149 ANA00000
Building M-149 BNA00000
Building M-150 ANA00000
Building M-150 BNA00000
Building M-151 ANA00000
Building M-151 BNA00000
Building M-152 ANA00000
Building M-152 BNA00000
Building M-153 ANA00000
Building M-153 BNA00000
Building M-154 ANA00000
Building M-154 BNA00000
Building M-155 ANA00000
Building M-155 BNA00000
Building M-156 ANA00000
Building M-156 BNA00000
Building M-157 ANA00000
Building M-157 BNA00000
Building M-158 ANA00000
Building M-158 BNA00000
Building M-159 ANA00000
Building M-159 BNA00000
Building M-160 ANA00000
Building M-160 BNA00000
Building M-161 ANA00000
Building M-161 BNA00000
Building M-162 ANA00000
Building M-162 BNA00000
Building M-163 ANA00000
Building M-163 BNA00000
Building M-164 ANA00000
Building M-164 BNA00000
Building M-165 ANA00000
Building M-165 BNA00000
Building M-166 ANA00000
Building M-166 BNA00000
Building M-167 ANA00000
Building M-167 BNA00000
Building M-168 ANA00000
Building M-168 BNA00000
Building M-169 ANA00000
Building M-169 BNA00000
Building M-170 ANA00000
Building M-170 BNA00000
Building M-171 ANA00000
Building M-171 BNA00000
Building M-172 ANA00000
Building M-172 BNA00000
Building M-173 ANA00000
Building M-173 BNA00000
Building M-174 ANA00000
Building M-174 BNA00000
Building M-175 ANA00000
Building M-175 BNA00000
Building M-176 ANA00000
Building M-176 BNA00000
Building M-177 ANA00000
Building M-177 BNA00000
Building M-178 ANA00000
Building M-178 BNA00000
Building M-179 ANA00000
Building M-179 BNA00000
Building M-180 ANA00000
Building M-180 BNA00000
Building M-181 ANA00000
Building M-181 BNA00000
Building M-182 ANA00000
Building M-182 BNA00000
Building M-183 ANA00000
Building M-183 BNA00000
Building M-184 ANA00000
Building M-184 BNA00000
Building M-185 ANA00000
Building M-185 BNA00000
Building M-186 ANA00000
Building M-186 BNA00000
Building M-187 ANA00000
Building M-188 ANA00000
Building M-189 ANA00000
Building M-189 BNA00000
Building M-190 ANA00000
Building M-190 BNA00000
Building M-191 ANA00000
Building M-191 BNA00000
Building M-192 ANA00000
Building M-192 BNA00000
Building M-193 ANA00000
Building M-193 BNA00000
Building M-194 ANA00000
Building M-194 BNA00000
Building M-195 ANA00000
Building M-195 BNA00000
Building M-196 ANA00000
Building M-196 BNA00000
Building M-197 ANA00000
Building M-197 BNA00000
Building M-198 ANA00000
Building M-198 BNA00000
Building M-199 ANA00000
Building M-199 BNA00000
Building M-200 ANA00000
Building M-200 BNA00000
Building M-201 ANA00000
Building M-201 BNA00000
Building M-202 ANA00000
Building M-202 BNA00000
Building M-203 ANA00000
Building M-204 ANA00000
Building M-204 BNA00000
Building M-205 ANA00000
Building M-205 BNA00000
Building M-206 ANA00000
Building M-206 BNA00000
Building M-207 ANA00000
Building M-207 BNA00000
Building M-208 ANA00000
Building M-208 BNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 8 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 436 buildings; the table lists the first 20.

296 of 4785 construction stages are filed complete across 436 buildings. The stage furthest along is Podiums (if any), at 0%.

Building Z91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
0Not stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Building A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building F91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building G91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building H91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building I91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building J91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building K91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building L91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building M91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building N91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building O91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building P91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building Q91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building R91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26
BuildingClosed/CoveredTotal
Building Z11
Building A11
Building B11
Building C11
Building D11
Building E11
Building F11
Building G11
Building H11
Building I11
Building J11
Building K11
Building L11
Building M11
Building N11
Building O11
Building P11
Building Q11
Building R11
Building S11
Building T11
Building U11
Building V11
Building W11
Building X11
Building Y11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area509,900 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI71302.54
Proposed, not sanctioned29,347 sq m
Buildings approved434
Buildings sanctioned25

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDhole Bunglow Near Amravati Railway Station Amravati 444601

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh V Dod
EngineerAmit M Gilda
PartnerRole in project
Amravati Housing And Area Development Board Amravati-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Jun 2023

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupancy Certificate .pdf8 Jun 2023
Layout approvalFile: Akoli layout.pdf16 Jul 2021
Copy of Layout Approval (in case of layout)File: Akoli layout.pdf16 Jul 2021
Certificates of CA (Form 5)File: Akoli.pdf20 Jun 2019
PAN CardFile: Pan card no MHADA.pdf2 Jan 2019
Certificates of CA (Form 5)File: Akoli Form 5.pdf2 Jan 2019
Building plan approvalFile: Building A.pdf20 Jan 2018
Building plan approvalFile: Building B.pdf20 Jan 2018
Building plan approvalFile: Building C.pdf20 Jan 2018
Building plan approvalFile: Building D.pdf20 Jan 2018
Building plan approvalFile: Building E.pdf20 Jan 2018
Building plan approvalFile: Building F.pdf20 Jan 2018
Building plan approvalFile: Building G.pdf20 Jan 2018
Building plan approvalFile: Building H.pdf20 Jan 2018
Building plan approvalFile: Building I.pdf20 Jan 2018
Building plan approvalFile: Building J.pdf20 Jan 2018
Building plan approvalFile: Building K.pdf20 Jan 2018
Building plan approvalFile: Building L.pdf20 Jan 2018
Building plan approvalFile: Building M.pdf20 Jan 2018
Building plan approvalFile: Building N.pdf20 Jan 2018
Building plan approvalFile: Building O.pdf20 Jan 2018
Building plan approvalFile: Building P.pdf20 Jan 2018
Building plan approvalFile: Building Q.pdf20 Jan 2018
Building plan approvalFile: Building R.pdf20 Jan 2018
Building plan approvalFile: Building S.pdf20 Jan 2018
Building plan approvalFile: Building T.pdf20 Jan 2018
Building plan approvalFile: Building U.pdf20 Jan 2018
Building plan approvalFile: Building V.pdf20 Jan 2018
Building plan approvalFile: Building W.pdf20 Jan 2018
Building plan approvalFile: Building X.pdf20 Jan 2018
Building plan approvalFile: Building Y.pdf20 Jan 2018
Copy of the legal title reportFile: Akoli Land Clearance NEW.PDF20 Jan 2018
Details of encumbrancesFile: Akoli encumbrance ertificate NEW.PDF20 Jan 2018
Building Plan Approval (IOD)File: Building A.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building B.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building C.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building D.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building E.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building F.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building G.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building H.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building I.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building J.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building K.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building L.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building M.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building N.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building O.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building P.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building Q.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building R.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building S.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building T.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building U.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building V.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building W.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building X.pdf20 Jan 2018
Building Plan Approval (IOD)File: Building Y.pdf20 Jan 2018
Declaration in FORM BFile: Akoli Form B NEW.PDF20 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Akoli EWS Plans Commesment ltrs 1.pdf19 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Akoli EWS Plans Commesment ltrs 2.pdf19 Jan 2018
Layout approvalFile: Akoli layout permission.pdf15 Jan 2018
Layout approvalFile: Akoli layout.pdf15 Jan 2018
Copy of Layout Approval (in case of layout)File: Akoli layout permission.pdf15 Jan 2018
Copy of Layout Approval (in case of layout)File: Akoli layout.pdf15 Jan 2018
Certificates of CA (Form 3)File: Akoli Form 3 PDF.PDF15 Jan 2018
Proforma of Allotment letterFile: Dekar Patra.PDF12 Jan 2018
Proforma of Allotment letterFile: Gala Watap.PDF12 Jan 2018
Proforma of Allotment letterFile: Taba Pavati.PDF12 Jan 2018

How this compares with Amravati

8%of Amravati projects moved their completion datethis one has not
33%of Amravati registrations have lapsed or been cancelledthis one is completed

Computed across the 450+ Amravati projects on ReraGenie, from their own filings.

Keep Construction of 674 EWS T/s 409 MIG T/s 104 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Akoli450+ in Amravati

2 kmConstruction of 674 EWS Completed 7Lapsed / revoked 1Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: Amravati Housing And Area Development Board Amravati

Amravati Housing And Area Development Board Amravati has 3 registrations on MahaRERA, including Construction of 268 EWS 20 MIG and 16 HIG T/s under PMAY at Buldhana and Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Amravati district page.

Frequently asked questions

What are my rights if Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG?

The registered promoter entity is Amravati Housing And Area Development Board Amravati, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG?

The professionals named in the filing: Architect: Nilesh V Dod; Engineer: Amit M Gilda. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Construction of 674 EWS T/s 409 MIG T/s 104 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.