Home / Browse projects / Raigarh, Maharashtra / CLOUD CASTLE

Completed No litigation declared Mixed project

CLOUD CASTLE

By JKS HOMES

RG-MH-38124 · RERA P52000046316 · Last updated on MahaRERA portal: 13 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 16 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Aug 2026Possession promisedregistration recorded completed
9 of 11Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
23 of 39Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 149 documents Report an error

CLOUD CASTLE is a Mixed project by JKS HOMES in Raigarh, Maharashtra, registered with MahaRERA as P52000046316 on 22 Jun 2022. The registration is recorded completed; possession was promised by 31 Aug 2026. The completion date has moved by 16 months from the original filing. 16 of the 39 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCLOUD CASTLE
  • TypeMixed
  • Location
    • PUSHPAK NODE
    • VAHAL
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000046316
  • ReraGenie IDRG-MH-38124

Builder

  • NameJKS HOMES
  • Entity typePartnership
  • GSTIN27AARFJ3558M1ZK
  • PartnersKISHOR BECHARA PATEL, KRISHNA YASHAVANT SALUNKHE, NAVIN RAJA RAVARIYA

Key dates

this monthRegisteredJun 2022First promiseApr 2025Revised toAug 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Jun 2022
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 15 Apr 2025)
  • Buildings1 building record
  • Documents filed149 files

Current status

41%16 of 39 units booked
100.0%Work done, per cost certificate

Figures as on 13 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CLOUD CASTLENA7732638

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

CLOUD CASTLE82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered18

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area600 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025
LandownerVillageDistrict
PRAKASH PANDURANG PATILUlaweRaigarh
RAJUBAI PRAKASH PATILUlaweRaigarh

Approvals and building plan

Sanctioning authorityCity And Industrial Development Corporation Of Maharashtra Limited
Permissible FSI1821.89
Proposed, not sanctioned1,465 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCBD BELAPUR 400614
Estimated costRs 3.30 cr
Cost incurredRs 3.30 cr
Work done100.0%
BuildingWingEstimatedIncurred
CLOUD CASTLENARs 3.30 crRs 3.30 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSheetal Architects
EngineerImpact Designerr
EngineerSHAHAJI TANPURE
Chartered AccountantManish k Ramawati and company
Chartered AccountantRSL & Co
PartnerRole in project
JKS HOMES-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000028273Apr 2025 → Jul 2025

Reason as filed by the promoterSeveral critical external work such as site preparation, plastering, utility installations, and lift setup-have been delayed due to the need for coordination with external agencies and additional preparatory requirements. These factors have significantly impacted our ability to meet the original project timeline. Delays from utility providers and local authorities have had a cascading effect on overall progress. Additionally, we are seeking extra time to complete the Occupancy Certificate (OC) process, as we are currently awaiting final approvals for the required NOCs.

EA07082502338Apr 2025 → Oct 2025

Reason as filed by the promoterWe would like to bring to your kind attention that while we have successfully obtained the No Objection Certificate (NOC) for the project and have completed all construction and development work, we have applied for OC and yet to be received the Occupation Certificate (OC) from the concerned government authorities which is beyond developer authority.

EA26122519026Apr 2025 → Mar 2026

Reason as filed by the promoterThe project is 100% physically completed, and the delay is solely due to pending statutory approvals, particularly the Fire NOC. The OC process was delayed because the PWD online portal used for NOC applications became non-functional, requiring a temporary shift to manual submissions, followed by re-submission once the portal was restored. These procedural changes caused a delay of approximately six months. All required applications and site visits have been completed, and all NOCs have been received except the Fire NOC, which is expected shortly. Additional time is therefore sought only to co

EA26062621559Apr 2025 → Aug 2026

Reason as filed by the promoterThe project is complete and has received its Occupation Certificate (OC). However, a technical discrepancy exists on the MahaRERA portal where a plot is visible that does not exist in the approved/sanctioned plans. To rectify this system error, a formal Change Application must be filed with MahaRERA. The project registration extension is being requested solely to allow sufficient time to complete this administrative correction and ensure the portal records match the approved project documents.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602300RAVI APPASO DESHPANDEJKS HOMES18/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Jul 2026

Documents filed149

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: new flatten.pdf13 Jul 2026
Completion CertificateFile: Declaration about plot.pdf8 Jul 2026
Occupational CertificateFile: Flatten Plan.pdf8 Jul 2026
Withdrawal Update Form 1File: Form 1 Q4.pdf4 Jul 2026
Withdrawal Update Form 2File: Form 2 cloud castle.pdf4 Jul 2026
Withdrawal Update Form 3File: Form 3 Q4.pdf4 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A_Cloud Castle_FY 24-25..pdf4 Jul 2026
Withdrawal Update Form 1File: Form 1_compressed.pdf24 Jun 2026
Withdrawal Update Form 2File: Form 2 cloud castle.pdf24 Jun 2026
Withdrawal Update Form 3File: Form 3_Cloud Castle_Sept 25_scanned.pdf24 Jun 2026
Withdrawal Update Form 1File: Form 1_compressed.pdf26 Dec 2025
Withdrawal Update Form 1File: Form 1_compressed.pdf26 Dec 2025
Withdrawal Update Form 2File: Form 2 cloud castle (1).pdf26 Dec 2025
Withdrawal Update Form 2File: Form 2 cloud castle.pdf26 Dec 2025
Withdrawal Update Form 3File: Form 3_Cloud Castle_Sept 25_scanned.pdf26 Dec 2025
Withdrawal Update Form 3File: Form 3_Cloud Castle_Sept 25_scanned.pdf26 Dec 2025
Withdrawal Update Form 1File: form 1 cloud castle.pdf10 Sep 2025
Withdrawal Update Form 1File: form 1 cloud castle.pdf10 Sep 2025
Withdrawal Update Form 2File: form 2 cloud castle.pdf10 Sep 2025
Withdrawal Update Form 2File: form 2 cloud castle.pdf10 Sep 2025
Withdrawal Update Form 3File: Form 3_Cloud Castle_June-25..pdf10 Sep 2025
Withdrawal Update Form 3File: Form 3_Cloud Castle_June-25..pdf10 Sep 2025
Form 2A (FY 2022-2023)File: form 2ASAHAJI.pdf2 Sep 2025
Form 2A (FY 2024-2025)File: form 2ASAHAJI.pdf2 Sep 2025
Form 2A (FY 2023-2024)File: form 2ASAHAJI.pdf2 Sep 2025
Form 5 (FY 2024-2025)File: Form 5_Cloud Castle_FY 24-25.pdf2 Sep 2025
Form 5 (FY 2022-2023)File: Cloud Castle- Form 5 FY 22-23.pdf21 Aug 2025
Form 5 (FY 2023-2024)File: form 5 23-24.pdf21 Aug 2025
Form 1File: Form 1.pdf20 Aug 2025
Form 2File: form 2.pdf20 Aug 2025
Form 3File: Self Declaration.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure (2).pdf20 Aug 2025
Form 1File: Form 1.pdf20 Aug 2025
Form 2File: Engineers certificate 30-9-23.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Signed Disclosure of Sold inventory .pdf20 Aug 2025
Form 1File: Form 1-PLOT 118 SEC -24 -PUSHPAK.pdf20 Aug 2025
Form 2File: Form 2 Engineer Certificate .pdf20 Aug 2025
Form 3File: Self Declaration for withdrawal .pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Plot 118.pdf20 Aug 2025
Form 1File: Architect FORM 1.pdf20 Aug 2025
Form 2File: Form 2.pdf20 Aug 2025
Form 3File: Form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure JKS.pdf20 Aug 2025
Form 1File: Form 1 - Dec 24 [Final].pdf20 Aug 2025
Form 2File: Form 2 - Dec 24.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: disclosure.pdf20 Aug 2025
Form 1File: form 1.pdf20 Aug 2025
Form 2File: FORM 2 FINAL.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: disclosure sold.pdf20 Aug 2025
Form 1File: Architect FORM 1.pdf20 Aug 2025
Form 2File: Form 2.pdf20 Aug 2025
Form 3File: Form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure JKS.pdf20 Aug 2025
Form 1File: Form 1-PLOT 118 SEC -24 -PUSHPAK.pdf20 Aug 2025
Form 2File: Form 2 Engineer Certificate .pdf20 Aug 2025
Form 3File: Self Declaration for withdrawal .pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Plot 118.pdf20 Aug 2025
Form 1File: Form 1.pdf20 Aug 2025
Form 2File: Engineers certificate 30-9-23.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Signed Disclosure of Sold inventory .pdf20 Aug 2025
Form 1File: Form 1.pdf20 Aug 2025
Form 2File: Engineers certificate 30-9-23.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Signed Disclosure of Sold inventory .pdf20 Aug 2025
Form 1File: Form 1.pdf20 Aug 2025
Form 2File: Engineers certificate 30-9-23.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Signed Disclosure of Sold inventory .pdf20 Aug 2025
Form 1File: Form 1.pdf20 Aug 2025
Form 2File: Engineers certificate 30-9-23.pdf20 Aug 2025
Form 3File: form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Signed Disclosure of Sold inventory .pdf20 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 cloud castle march 2025.pdf30 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Cloud Castle_31-03-2025.pdf30 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 march 2025 quater.pdf30 May 2025
Disclosure of sold/ booked inventoryFile: sept quater sold unsold cloud castle.pdf30 May 2025

How this compares with Raigarh

41%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 16 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CLOUD CASTLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VAHAL5,900+ in Raigarh

Builder: JKS HOMES

JKS HOMES has 1 registration on MahaRERA, including CLOUD CASTLE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CLOUD CASTLE is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CLOUD CASTLE?

The registered promoter entity is JKS HOMES, a partnership as per the filing. Its GSTIN 27AARFJ3558M1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CLOUD CASTLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CLOUD CASTLE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CLOUD CASTLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CLOUD CASTLE?

The professionals named in the filing: Architect: Sheetal Architects; Engineer: Impact Designerr; Engineer: SHAHAJI TANPURE; Chartered Accountant: Manish k Ramawati and company; Chartered Accountant: RSL & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CLOUD CASTLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CLOUD CASTLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CLOUD CASTLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.