ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / CLAN CITY-EMERALD

Registration lapsed No litigation declared Residential / Group Housing project

CLAN CITY-EMERALD

By Supreme Construction and Developers Private Limited

RG-MH-20792 · RERA P52000003118 · Last updated on MahaRERA portal: 18 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date
  • 41 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
0 of 11Construction stages donefurthest along: Excavation, 75%
41Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

CLAN CITY-EMERALD is a Residential / Group Housing project by Supreme Construction and Developers Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000003118 on 4 Aug 2017. Possession was promised by 29 Mar 2024 and is now 31 months past that date. The completion date has moved by 12 months from the original filing. 41 complaints are on record with the regulator.

At a glance

Project

  • NameCLAN CITY-EMERALD
  • TypeResidential / Group Housing
  • Location
    • NH4
    • TALOJA
    • Rohinjan
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000003118
  • ReraGenie IDRG-MH-20792

Builder

  • NameSupreme Construction and Developers Private Limited
  • Entity typeCompany
  • Managing DirectorManulla Mehbullah Kanchwala
  • Other registrations8 more →
  • No longer live9 lapsed, de-registered or revoked

Key dates

31 months past promisethis monthRegisteredAug 2017First promiseMar 2023Revised toMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion29 Mar 2024
  • Revised completionRevised to 29 Mar 2024 (originally 30 Mar 2023)
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EMERALDNA390000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 75%.

EMERALD: 45% average across the applicable activities

ActivityProgress
Excavation75%
Basement (if any)75%
Podiums (if any)42%
Plinth75%
Stilt Floor38%
Slabs of Super Structure74%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.11%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.4%

Progress on shared amenities15

As on 18 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,303 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6278.69
Proposed, not sanctioned6,279 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAnchorage Bldg, 170-171, Central Avenue, Chembur Mumbai - 400 071

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDimesnsions Architects Pvt Ltd
EngineerShrikhande Consultants Pvt Ltd
PartnerRole in project
Supreme Construction and Developers Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000015088Mar 2023 → Mar 2024

Reason as filed by the promoterThis project has a special status as it is in collaboration with regional planning authority, MMRDA, constituted by the state Government. As per the role defined in the scheme, the developer is supposed to hand over constructed affordable houses, free of cost to MMRDA against the additional FSI and provision of all off site infrastructure to the project by MMRDA. We have paid total infrastructure charges amounting about Rs Six Crores to MMRDA 6 years back however MMRDA has completely failed to even start the works of water supply, sewage system and storm water drainage work. In the absence of

Litigation declared4

CaseCourtStatus
340,348,342,343,351,344,349/2017Bombay High CourtFINAL ORDER PASSED MATTER DISPOSED
77,79,84,80,75,74,76/2017Bombay High CourtFINAL ORDER PASSED MATTER DISPOSED
191,192,193,194,195,310,311/2017Bombay High CourtFINAL ORDER PASSED MATTER DISPOSED
20274/2017Bombay High CourtPending

Complaints filed with MahaRERA41

Case no.ComplainantRespondentFiled
CC006000000192447Karthik Bosco JuliusSupreme Construction and developers Pvt Ltd06/02/2020
CC006000000161261EMERALD BUYERS ASSOCIATIONSUPREME CONSTRUCTIONS AND DEVELOPERS PVT LTD15/10/2019
CC006000000251800Mr. Shrawan Kumar Yadav and Mrs. Suman DeviM/s. Supreme Construction and Developers Pvt. Ltd.11/07/2022
CC006000000303735Mr. Nitu Hariprasad Singh and Ms. Radha SinghM/s. Supreme Construction and Developers Pvt. Ltd.20/12/2022
CC006000000333804VIJAYEE VIKRANT SONIMANULLA MEHBULLAH KANCHWALA02/01/2023
CC006000000333915Mr Eknath Dhondibhau ThoratSupreme Construction and Developers Pvt Ltd09/01/2023
CC006000000333950Vinay Gopalji GajraSupreme Construction and Developers Pvt Ltd13/01/2023
CC006000000334050Mrs Samruddhi Santosh Kate and Mr Santosh Ramchandra KateSupreme Construction and Developers Pvt Ltd20/01/2023
CC006000000334088Roma Haresh KatariaSupreme Construction and Developers Private Limited24/01/2023
CC006000000344166VAISHALI Prakash SableSupreme construction and developers pvt ltd18/02/2023
CC006000000344197Karunendra Singh SachanSupreme Construction and Developers Pvt Ltd02/02/2023
CC006000000354379Mr Priyank Pavan Nanda and Mr Pavan NandaSupreme Construction and Developers Pvt Ltd16/02/2023
CC006000000354417Pradip SableSupreme construction and developers pvt ltd18/02/2023
CC006000000364530Anita Pradeep Kumar JaiswalSupreme Construction and Developers Pvt Ltd27/02/2023
CC006000000364533Anil Kumar Jaiswal and Suman JaiswalSupreme Construction and Developers Pvt Ltd27/02/2023
CC006000000364598Rekha Bhagwandas Narang and Bhagwandas Choithiram NarangSupreme Construction and Developers Pvt Ltd03/03/2023
CC006000000374938MR IMRAN LAYAK SHAIKH AND MRS SHAGUFTA IMRAN SHAIKHM/S SUPREME CONSTRUCTION AND DEVELOPERS PVT LTD28/03/2023
CC006000000375063Roopa santosh Palve and Santosh Narayan PalveSupreme Construction and developers Pvt Ltd01/04/2023
CC006000000375078Akhilesh R SharmaSupreme Construction and Developers Pvt Ltd02/04/2023
CC006000000375104Mr Parag Prakash JadhavSupreme Constructions and Developers Pvt Ltd04/04/2023
CC006000000395695Mr Vilas Krishna Dhopte and Mrs Jayashree Vilas DhopteSupreme Construction and Developers Pvt Ltd09/05/2023
CC006000000395784CAPT ROYCE FERNANDES MRS FLORINDA ROYCE FERNANDESM/S SUPREME CONSTRUCTION AND DEVELOPERS PVT LTD17/05/2023
CC006000000395814Mr Pradeep Thangavelu Vaniyan and Mrs Krishnapriya Prdeep VaniyanSupreme Construction and Developers Pvt Ltd15/05/2023
CC006000000395905Asha Vijay KanalSupreme Construction and Developers Pvt Ltd23/05/2023
CC006000000395980MR DHANANJAY VILAS KARAMBELKARM/S SUPREME CONSTRUCTION AND EVELOPERS PVT LTD30/06/2023
CC006000000396549JAY SHANKAR PRASAD SINGHM/S SUPREME CONSTRUCTION AND DEVELOPERS Pvt. Ltd.15/08/2023
CC006000000396590PAROMITA BHATTACHARYASUPREME CONSTRUCTIONS & DEVELOPMENT PVT LTD.14/07/2023
CC006000000397154SAMEER BARKAT ALI UNIASUPREME CONSTRUCTION AND DEVELOPER PVT LTD20/11/2023
CC006000000397175Vasundhara JoshiSupreme Construction and Developers Pvt Ltd21/08/2023
CC006000000397233Manila KumariSwarnakanta Ramsheran Bhalla24/08/2023
CC006000000397328Shailendra Kumar Mittal And Asha MittalSupreme Construction and Developers Pvt Ltd01/09/2023
CC006000000397356ANINDITA DEOGHARIASupreme Construction and Developers Private Limited06/09/2023
CC006000000397524Anil Sudhakar UnhawaneSupreme Construction & Developers Pvt. Ltd.18/09/2023
CC006000000429057Laveena S GangwaniSupreme Construction and Developers Pvt Ltd01/02/2024
CC006000000580854Kanchan SharmaSupreme Developers & Construction Pvt Ltd09/07/2024
CC006000000591476Shabbir Amir Ali DoctorSupreme Construction and Developers08/08/2024
CC12500624Kunjbihari Anant GuptaSupreme Construction and Developers Private Limited22/02/2025
CC12503027Pradeep Manglaprasad DubeySupreme Construction and Developers Private Limited28/08/2025
CC12503133Shital Ganpat JadhavSupreme Construction and Developers Private Limited05/09/2025
CC12503701Gurpreet Singh OberoiSupreme Construction and Developers Private Limited17/10/2025
CC12503844gajendera mangilal chandaliyaSupreme Construction and Developers Private Limited02/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf18 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate ok.pdf18 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate ok.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form -2A Engineer's Certificate Quality AssuranceF Y 20192020.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineer's Certificate Quality Assurance F Y 2020 2021.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engineer's Certificate Quality Assurance F Y 2021 2022.pdf18 Mar 2023
CERSAI detailsFile: CERSAI EMERALD.pdf18 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory EMERALD.pdf18 Mar 2023
Certificates of CA (Form 3)File: FORM 3 C A Certificate EMERALD.pdf18 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Ibrahim Mirza ok.pdf18 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organization Manulla Kanchwala ok.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Anual Audit Report of Statutory CA Emerald 18 19.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Anual Audit Report of Statutory CA Emerald 19 20.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Anual Audit Report of Statutory CA Emerald 20 21.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Anual Audit Report of Statutory CA Emerald 21 22.pdf18 Mar 2023
Certificates of CA (Form 5)File: RERA Form-5_T8_Emerald.pdf10 Apr 2019
Proforma of Allotment letterFile: RERA Agreement - WITHOUT SUBVENTION1.pdf18 Oct 2018
Proforma of Allotment letterFile: RERA Agreement -SUBVENTION1.pdf17 Oct 2018
Proforma of Allotment letterFile: draft agreement.pdf6 Sep 2018
Proforma of Allotment letterFile: Rera Agreement -NEW.pdf7 Mar 2018
Proforma of Allotment letterFile: Rera Agreement Draft Revised.pdf16 Aug 2017
Declaration in FORM BFile: FORM - B EMERALD.pdf2 Aug 2017
Layout approvalFile: Sheet-17.pdf26 Jul 2017
Layout approvalFile: Sheet-16.pdf26 Jul 2017
Layout approvalFile: Sheet-03.pdf26 Jul 2017
Building plan approvalFile: CC Copy.pdf26 Jul 2017
Layout approvalFile: Sheet-02.pdf26 Jul 2017
Layout approvalFile: Sheet-01.pdf26 Jul 2017
PAN CardFile: SUPREME - PAN.pdf26 Jul 2017
Copy of the legal title reportFile: 2013 Title Clearance.pdf26 Jul 2017
Details of encumbrancesFile: NO INCUMBRANCE -EMERALD.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Sheet-01.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Sheet-02.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Sheet-03.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Sheet-16.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Sheet-17.pdf26 Jul 2017
Building Plan Approval (IOD)File: CC Copy.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 -EMERALD.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - EMERALD.pdf26 Jul 2017
Certificates of CA (Form 3)File: FORM-3 EMERALD.pdf26 Jul 2017
Proforma of Allotment letterFile: Rera Agreement Draft.pdf26 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Draft.pdf26 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 12 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CLAN CITY-EMERALD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TALOJA5,900+ in Raigarh

2 kmCLAN CITY-EMERALDCompleted 21Lapsed / revoked 29Other 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 117 registered projects within 2 km.

Builder: Supreme Construction and Developers Private Limited

Supreme Construction and Developers Private Limited has 9 registrations on MahaRERA, including CLAN CITY - SAPPHIRE and CLAN CITY-TURQUOISE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that CLAN CITY-EMERALD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CLAN CITY-EMERALD is delayed beyond 29 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CLAN CITY-EMERALD?

The registered promoter entity is Supreme Construction and Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CLAN CITY-EMERALD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CLAN CITY-EMERALD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CLAN CITY-EMERALD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CLAN CITY-EMERALD?

The professionals named in the filing: Architect: Dimesnsions Architects Pvt Ltd; Engineer: Shrikhande Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CLAN CITY-EMERALD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CLAN CITY-EMERALD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CLAN CITY-EMERALD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.