Red flags

  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 42 months from the original
1 of 11Construction stages donefurthest along: Basement (if any), 0%
1 of 4Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

CITYOPIA WING -E is a Residential / Group Housing project by CITYOPIA VENTURES PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000027809 on 4 Jan 2021. Possession is promised by 31 Dec 2029. The completion date has moved by 42 months from the original filing. 3 of the 4 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameCITYOPIA WING -E
  • TypeResidential / Group Housing
  • Location
    • KOLKHE
    • PANVEL
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000027809
  • ReraGenie IDRG-MH-29064

Builder

  • NameCITYOPIA VENTURES PRIVATE LIMITED
  • Entity typeCompany
  • DirectorPRASHANT PRABHAKAR PATEKAR

Key dates

this monthRegisteredJan 2021First promiseJun 2026Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Jan 2021
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed114 files

Current status

75%3 of 4 units booked
0.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CITYOPIA WING -ENA51404

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

CITYOPIA WING -E: 9% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed460

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots460
Closed/Covered230
Open Space230

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,863 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO NAVI MUMBAI AIRPORT INFLUENCE NOTIFIED AREA (NAINA)
Permissible FSI19204.79
Proposed, not sanctioned2,262 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWODEHOUSE ROAD SETH M F PANDAY CHARI,BUILDING, 108-110, WOD,MUMBAI,400005 MAHARASHTRA
Estimated costRs 73.52 cr
Work done0.0%
BuildingWingEstimatedIncurred
CITYOPIA WING -ENARs 69.84 cr-
-NARs 3.68 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectstapl soyuz tallb architects
Engineerasc Associated Structural Engineers LLp
EngineerS K Consultants & Engineers
Chartered AccountantN B Sayed & Associates
Chartered AccountantPRANAV BHASKARAN & ASSOCIATES
PartnerRole in project
CITYOPIA VENTURES PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19052621009Jun 2026 → Dec 2029

Reason as filed by the promoterThe project is presently sanctioned up to Ground + 1st Floor under the existing Commencement Certificate (CC). We have submitted a revised proposal for development up to 32 floors, and the revised plans are currently under review and approval by the competent authority. Since construction beyond the approved level cannot be undertaken until the revised Commencement Certificate and related statutory approvals are obtained, the progress of the project has been affected. The delay is attributable to the time required for obtaining regulatory approvals from the concerned authorities and is beyond

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Cityopia Wing E as on June 2026.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 - Cityopia Wing - E-Signed.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 - Cityopia Wing E - 30062026Signed.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1 - Cityopia Wing E as on June 2026.pdf14 Jul 2026
Withdrawal Update Form 2File: Form 2 - Cityopia Wing E as on June 2026.pdf14 Jul 2026
Withdrawal Update Form 3File: Form 3 - Cityopia Wing E as on June 2026.pdf14 Jul 2026
Form 5 (FY 2024-2025)File: Form 5 - Cityopia Wing - E for FY 2024-25.pdf5 Jun 2026
Form 5 (FY 2023-2024)File: Form 5 - Cityopia Wing - E for FY 2023-24.pdf5 Jun 2026
Withdrawal Update Form 1File: Form 1 - Wing E 31 03 2026.pdf15 May 2026
Withdrawal Update Form 2File: Form - 2 Wing E 31 03 2026.pdf15 May 2026
Withdrawal Update Form 3File: Form - 3 - Wing E 31 03 2026.pdf15 May 2026
Form 1File: Form 1 - Cityopia Wing E as on Dec 2025.pdf11 Feb 2026
Form 2File: Form 2 - Cityopia Wing E as on Dec 2025.pdf11 Feb 2026
Form 3File: Form 3 - Cityopia Wing E as on Dec 2025.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Cityopia Wing E as on Dec 2025.pdf11 Feb 2026
Form 1File: Form 1 - Cityopia Wing E as on Sep 2025.pdf16 Oct 2025
Form 2File: Form 2 - Cityopia Wing E as on Sep 2025.pdf16 Oct 2025
Form 3File: Form 3 - Cityopia Wing E as on Sep 2025.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Cityopia Wing E as on Sep 2025.pdf16 Oct 2025
Form 1File: Form 1 - Cityopia Wing - E as on June 2025.pdf28 Jul 2025
Form 2File: Form 2 - Cityopia Wing - E as on June 2025.pdf28 Jul 2025
Form 3File: Form 3 - Cityopia Wing E 30-06-2025.pdf28 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Cityopia Wing - E as on June 2025.pdf28 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Cityopia Wing E as on Dec 2024.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Cityopia Wing E as on Dec2024.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Cityopia Wing - E as on Dec 2024.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Cityopia Wng E as on September 2024.pdf29 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cityopia Wing E 30-09-2024.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Cityopia Wing - E as on 30-09-2024.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Cityopia Wing - E as on June 2024.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cityopia Wing E 30-06-2024.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Cityopia Wing - E as on June 2024.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Cityopia Wing - E as on March 2024.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cityopia Wing E 31 -03-2024.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Cityopia Wing - E as on Dec 2023.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cityopia Wing E Dec 2023.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Cityopia Wing-E as on Dec 2023.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Cityopia Wing-E as on March 2023.pdf21 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Cityopia Wing-E as on June 2023.pdf21 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Cityopia Wing-E as on Sept 2023.pdf21 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Cityopia Wing - E as on Sep 2023.pdf23 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Cityopia Wing - E as on Sep 2023.pdf23 Nov 2023
Disclosure of sold/ booked inventoryFile: Draft CIRCULAR 29.pdf1 Nov 2023
Declaration about Commencement CertificateFile: Draft FORMAT D (32).pdf31 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate Wing E Oct 2023.pdf31 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Draft Form 2A (FY 2020-21).pdf31 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Draft Form 2A (FY 2021-22).pdf31 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Draft Form 2A (FY 2022-23).pdf31 Oct 2023
Building plan approvalFile: Page 1 and 2.pdf29 Sep 2023
Building plan approvalFile: Page 3, 4 and 5.pdf29 Sep 2023
Building plan approvalFile: Page 6, 7 and 8.pdf29 Sep 2023
Building plan approvalFile: Page 9, 10 and 11.pdf29 Sep 2023
Building plan approvalFile: Page 12, 13 and 14.pdf29 Sep 2023
Building plan approvalFile: Page 15, 16, 17 and 18.pdf29 Sep 2023
Building plan approvalFile: Page 19 and 20.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 1 and 2.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 3, 4 and 5.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 6, 7 and 8.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 9, 10 and 11.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 12, 13 and 14.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 15, 16, 17 and 18.pdf29 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Page 19 and 20.pdf29 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: Ammended CC.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 as on 2022-23.pdf1 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Cityopia Wing E as on June 2023.pdf26 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Cityopia Wing E as on June 2023.pdf26 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Cityopia Wing E Dec 2022.pdf21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Form 3 Cityopia Wing E March 2023.pdf21 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CVPL_E wing_31032023_architects certificate.pdf18 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Cityopia Wing E as on September 2022.pdf10 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Cityopia Wing E as on September 2022.pdf10 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Certificate 099.pdf30 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cityopia Wing E Form 2- June 2022.pdf30 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cityopia Wing E June 2022.pdf30 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cityopia Wing E - Form 2 - 31-03-2022_compressed.pdf23 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cityopia Wing E_ March 2022.pdf23 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cityopia Wing E Form 2- 31st December 2021.pdf12 May 2022

How this compares with Raigarh

75%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 42 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CITYOPIA WING -E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANVEL5,900+ in Raigarh

2 kmCITYOPIA WING -ECompleted 32Lapsed / revoked 10Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: CITYOPIA VENTURES PRIVATE LIMITED

CITYOPIA VENTURES PRIVATE LIMITED has 1 registration on MahaRERA, including CITYOPIA WING -E. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CITYOPIA WING -E is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CITYOPIA WING -E?

The registered promoter entity is CITYOPIA VENTURES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CITYOPIA WING -E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CITYOPIA WING -E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CITYOPIA WING -E?

The professionals named in the filing: Architect: stapl soyuz tallb architects; Engineer: asc Associated Structural Engineers LLp; Engineer: S K Consultants & Engineers; Chartered Accountant: N B Sayed & Associates; Chartered Accountant: PRANAV BHASKARAN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CITYOPIA WING -E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CITYOPIA WING -E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CITYOPIA WING -E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.