Home / Browse projects / Raigarh, Maharashtra / City Of Music Phase III
City Of Music Phase III
RG-MH-29139 · RERA P52000027911 · Last updated on MahaRERA portal: 16 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 42 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
City Of Music Phase III is a Plotted project by Nirvana Leisure Realty in Raigarh, Maharashtra, registered with MahaRERA as P52000027911 on 15 Jan 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 42 months from the original filing. 68 of the 78 units on this registration are recorded sold or booked. 1 complaint is on record with the regulator.
At a glance
Project
- NameCity Of Music Phase III
- TypePlotted
- Location
- Khopoli Pali Road
- Khopoli
- Bhilpada (khuravale)
- Sudhagad
- Raigarh
- 410205
- Pincode410205
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000027911
- ReraGenie IDRG-MH-29139
Builder
- NameNirvana Leisure Realty
- Entity typePartnership
- PartnersPravin Kumar Jugal Kishore Agarwal, Punit Pravin Kumar Agarwal, Varun Vinay Gupta
- Other registrations3 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jan 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2023)
- BuildingsNot stated in filing
- Documents filed70 files
Current status
Figures as on 16 May 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 16 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 30% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 30% |
| Community Buildings | Yes | 75% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 30% |
| Open Parking | Yes | 40% |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Nirvana Leisure Realty | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 12.78 cr | Rs 12.78 cr |
| NA Plot Without Structure | NA | Rs 2.66 cr | Rs 2.66 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DEEPAK HIREMATH ASSOCIATES |
| Architect | DEEPAK HIREMATH |
| Engineer | Naik Associates |
| Engineer | DEEPAK HIREMATH |
| Chartered Accountant | SPKG & Co LLP |
| Chartered Accountant | SANJAY SONI |
| Partner | Role in project |
|---|---|
| Nirvana Leisure Realty | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to flood in project there has been loss of material and labour
Reason as filed by the promoterSevere loss of materials and labour due to the flood in the project land resulting in delay
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500483 | Manoj Dashrath Gupta | Nirvana Leisure Realty | 13/02/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed70
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1(architect certificate) Mar 26 Ready.pdf | 16 May 2026 |
| Form 2File: Form 2 Naik associates Mar 26 Ready.pdf | 16 May 2026 |
| Form 3File: FORM 3 NLR FOR COM PHASE III Mar 26 Ready.pdf | 16 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD INVENTORY REVISED.pdf | 16 May 2026 |
| Form 3File: Form 3 COM Phase III (signed).pdf | 17 Jul 2025 |
| Form 2File: Form 2 Jun 2024.pdf | 17 Jul 2025 |
| Form 1File: Form 1(architect certificate) Jun 24.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold book Sold Jun 2024.pdf | 17 Jul 2025 |
| Form 1File: Form 1 COM Phase III.pdf | 17 Jul 2025 |
| Form 2File: Form 2 Mar 2024.pdf | 17 Jul 2025 |
| Form 3File: FORM 3 PHASE III COM.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold booked & Sold..pdf | 17 Jul 2025 |
| Form 1File: Form 1(architect certificate) Dec 23.pdf | 17 Jul 2025 |
| Form 2File: Form 2 Dec 2023.pdf | 17 Jul 2025 |
| Form 3File: NLR FORM 3 for Mar 23.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold booked & Sold..pdf | 17 Jul 2025 |
| Form 1File: NLR Form 1 for Sept 23.pdf | 17 Jul 2025 |
| Form 2File: NLR Form 2 for Sept 23.pdf | 17 Jul 2025 |
| Form 3File: NLR FORM 3 for Sept 23.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold booked & Sold.pdf | 17 Jul 2025 |
| Form 1File: NLR Form 1 for Jun 23.pdf | 17 Jul 2025 |
| Form 2File: NLR FORM 2 for Jun 23.pdf | 17 Jul 2025 |
| Form 3File: NLR Form 3 for Jun 23.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold booked.pdf | 17 Jul 2025 |
| Form 1File: NLR Form 1 for Mar 23.pdf | 17 Jul 2025 |
| Form 2File: NLR Form 2 for Mar 23.pdf | 17 Jul 2025 |
| Form 3File: NLR FORM 3 for Mar 23.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold booked & Sold..pdf | 17 Jul 2025 |
| OthersFile: Form 5 Phase III COM Mar 23.pdf | 17 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM PHASE 3 COM.pdf | 29 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 COM Phase III.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 COM III.pdf | 18 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NLR Form 1 for Mar 23.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NLR Form 1 for Jun 23.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NLR Form 1 for Sept 23.pdf | 11 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NLR Form 2 for Mar 23.pdf | 11 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NLR FORM 2 for Jun 23.pdf | 11 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NLR Form 2 for Sept 23.pdf | 11 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NLR FORM 3 for Mar 23.pdf | 11 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NLR Form 3 for Jun 23.pdf | 11 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NLR FORM 3 for Sept 23.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 3 Phase III COM.pdf | 6 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 3 Phase III COM.pdf | 6 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf | 20 Feb 2024 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf | 20 Feb 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 20 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf | 20 Feb 2024 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf | 20 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter.pdf | 20 Feb 2024 |
| Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf | 20 Feb 2024 |
| Declaration in FORM BFile: From B.pdf | 18 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold book Sold.pdf | 18 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 CA Certifcate New.pdf | 18 Sep 2023 |
| PAN CardFile: 1 PAN Card.pdf | 16 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 16 Sep 2023 |
| CERSAI detailsFile: Cersai report.pdf | 16 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 CA Certifcate.pdf | 16 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold booked.pdf | 15 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: declaration letter for separate bank account.pdf | 15 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: declaration letter for Separate bank account.pdf | 15 Sep 2023 |
| Layout approvalFile: Layout.pdf | 24 Dec 2020 |
| Building plan approval or NA orderFile: NA order.pdf | 24 Dec 2020 |
| Copy of the legal title reportFile: Legal Title.pdf | 24 Dec 2020 |
| Details of encumbrancesFile: Encumbarance.pdf | 24 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 24 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: NA order.pdf | 24 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: NA order.pdf | 24 Dec 2020 |
| Declaration in FORM BFile: Form B.pdf | 24 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FOR PHASE III Compress.pdf | 24 Dec 2020 |
| Proforma of Allotment letterFile: Proforma of Agreement.pdf | 24 Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 70 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep City Of Music Phase III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khopoli5,900+ in Raigarh
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
TECTONA HILLS
SANTOSH KOLTE AND VASANT SALIAN
City Of Music Phase I
Nirvana Leisure Realty
RE CASA
R S Realties
SHREE GAJANAN TOWERS
OSWAL DEVELOPERS
SHUBHAM RESIDENCY
G D JAIN INFRA PROJECTS
Joy Villa Phase-I
SADANAND LAXMANRAO PATIL
See every Raigarh project, with the district possession charts
Builder: Nirvana Leisure Realty
Nirvana Leisure Realty has 4 registrations on MahaRERA, including City Of Music Phase I and City Of Music Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if City Of Music Phase III is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of City Of Music Phase III?
The registered promoter entity is Nirvana Leisure Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in City Of Music Phase III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against City Of Music Phase III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for City Of Music Phase III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at City Of Music Phase III?
The professionals named in the filing: Architect: DEEPAK HIREMATH ASSOCIATES; Architect: DEEPAK HIREMATH; Engineer: Naik Associates; Engineer: DEEPAK HIREMATH; Chartered Accountant: SPKG & Co LLP; Chartered Accountant: SANJAY SONI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in City Of Music Phase III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback