Home / Browse projects / Raigarh, Maharashtra / City Of Music Phase II

Registration lapsed No litigation declared Plotted project

City Of Music Phase II

By Nirvana Leisure Realty

RG-MH-61989 · RERA P52000016821 · Last updated on MahaRERA portal: 25 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 39 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
8 of 50Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

City Of Music Phase II is a Plotted project by Nirvana Leisure Realty in Raigarh, Maharashtra, registered with MahaRERA as P52000016821 on 18 Jun 2018. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 39 months from the original filing. 42 of the 50 units on this registration are recorded sold or booked. 4 complaints are on record with the regulator.

At a glance

Project

  • NameCity Of Music Phase II
  • TypePlotted
  • Location
    • KHOPOLI PALI ROAD
    • KHOPOLI
    • Bhilpada (khuravale)
    • Sudhagad
    • Raigarh
    • 410205
  • Pincode410205
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000016821
  • ReraGenie IDRG-MH-61989

Builder

  • NameNirvana Leisure Realty
  • Entity typePartnership
  • PartnersPravin Kumar Jugal Kishore Agarwal, Punit Pravin Kumar Agarwal, Varun Vinay Gupta
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

4 months past promisethis monthRegisteredJun 2018First promiseMar 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Jun 2018
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Mar 2023)
  • BuildingsNot stated in filing
  • Documents filed77 files

Current status

84%42 of 50 units booked
100.0%Work done, per cost certificate

Figures as on 25 Jul 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities17

As on 25 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes75%
Street LightingYes50%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes75%
Open ParkingYes75%
Riverside DeckYes80%
Common Swimming PoolYes100%

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,021 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Sep 2024
LandownerVillageDistrict
NIRVANA LEISURE REALTYAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityRAIGARH MUNCIPAL CORPORATION
Permissible FSI7785.17

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOKHANDWALA ANDHERI WEST
Estimated costRs 7.52 cr
Cost incurredRs 7.52 cr
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 4.86 crRs 4.86 cr
NA Plot Without StructureNARs 2.66 crRs 2.66 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEEPAK HIREMATH ASSOCIATES
ArchitectDEEPAK HIREMATH
EngineerNaik Associates
EngineerDEEPAK HIREMATH
Chartered AccountantSANJAY R SONI & ASSOCIATES
Chartered AccountantSANJAY SONI
PartnerRole in project
Nirvana Leisure Realty-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013999Mar 2023 → Mar 2024

Reason as filed by the promoterDue to flood in project there has been loss of material and labour

EXT52000024346Mar 2023 → Jun 2026

Reason as filed by the promoterThere has been a severe loss of materials and labour due to the flood in the project land resulting in delay. Due to lock down the construction work came to a halt for months apart from the labour migrancy to the native state resulting in shortage of labour. Apart from it due to lock resulting in loss in business and jobs

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12501239Charanpreet Singh SehgalNirvana Leisure Realty14/04/2025
CC12601097Richa Atendra PalNirvana Leisure Realty28/02/2026
CC12602125Rashneen Kaur AnandNirvana Leisure Realty10/04/2026
CC12604169Sanjukta DeyNirvana Leisure Realty03/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 COM phs 2 Mar 25.pdf25 Jul 2025
Form 2File: Form 2 COM ph 2 Mar 25.pdf25 Jul 2025
Form 3File: FORM 3 COM PHS II Mar 25.pdf25 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-inventory.pdf25 Jul 2025
Certificates of CA (Form 3)File: 14 Certificates of CA (Form 3).pdf11 Apr 2025
Certificates of CA (Form 3)File: 14 Certificates of CA (Form 3).pdf11 Apr 2025
Certificates of CA (Form 3)File: COM Form 3 Dec 251104_compressed.pdf11 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineers Certificate.pdf11 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: COM Form 3 Dec 25_compressed.pdf9 Apr 2025
Declaration in FORM BFile: FORM B notriesed.pdf8 Apr 2025
Certificates of CA (Form 3)File: Form 3 Jun 23.pdf7 Apr 2025
Certificates of CA (Form 3)File: Form 3 Sept 23.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf7 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Annual Report Com Revised.pdf7 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf5 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 24.pdf3 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SEPT 24.pdf3 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 DEC 24.pdf3 Apr 2025
Certificates of CA (Form 3)File: Form 3 DEC 24.pdf3 Apr 2025
Certificates of CA (Form 3)File: Form 3 DEC 24.pdf3 Apr 2025
Certificates of CA (Form 3)File: Form 3 SEPT 24.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Mar 24.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 24.pdf3 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 24.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A Year ending 2024.pdf3 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Mar 24.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jun 24.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Sept 24.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Dec 24.pdf12 Mar 2025
Certificates of CA (Form 3)File: Form 3 NLR For COM Phase II Jun 23.pdf12 Mar 2025
Certificates of CA (Form 3)File: Form 3 NLR For COM Phase II Sept 23.pdf12 Mar 2025
Certificates of CA (Form 3)File: Form 3 NLR For COM Phase II Dec 23.pdf12 Mar 2025
Certificates of CA (Form 3)File: Form 3 NLR For COM Phase II Sept 24.pdf12 Mar 2025
Certificates of CA (Form 3)File: Form 3 NLR For COM Phase II Dec 24.pdf12 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Mar 24.pdf12 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jun 24.pdf12 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Sept 24.pdf12 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Dec 24.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NLR Form 1 for Mar 23.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NLR Form 1 for Jun 23.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NLR Form 1 for Sept 23.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Dec 23.pdf13 Nov 2024
Certificates of CA (Form 3)File: NLR FORM 3 for Mar 23.pdf13 Nov 2024
Certificates of CA (Form 3)File: NLR Form 3 for Jun 23.pdf13 Nov 2024
Certificates of CA (Form 3)File: NLR FORM 3 for Sept 23.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NLR Form 2 for Mar 23.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NLR FORM 2 for Jun 23.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NLR Form 2 for Sept 23.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2023.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ( Enggineering).pdf20 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf20 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf12 Feb 2024
Declaration in FORM BFile: Form B extension.pdf13 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a Signed copy_compressed.pdf16 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form-5.pdf16 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclouser of Inventory.pdf11 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form-5.pdf11 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a Signed copy_compressed.pdf9 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of Interest New_compressed.pdf8 Mar 2023
Proforma of Agreement for saleFile: Agreement for Sale-Plot.pdf8 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for separate bank account.pdf8 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation in allotment letter.pdf8 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation in agreement for sale.pdf8 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200245059001_For_Asset_Based_Search_19_08_2022_17_17_22_565.pdf19 Aug 2022
PAN CardFile: NLR PAN CARD.pdf17 Aug 2022
Details of encumbrances concerned to LegalFile: Details of encumbrances.pdf17 Aug 2022
Declaration about Commencement CertificateFile: Commencement Certificate.pdf17 Aug 2022
Proforma of Allotment letterFile: Draft RERA Allotment and Agreement for Sale.pdf11 Jun 2018
Certificates of CA (Form 3)File: CA CERTIFICATE FOR PHASE II.pdf8 Jun 2018
Declaration in FORM BFile: Form B (1).pdf17 Apr 2018
Layout approvalFile: PLOT LAYOUT APPROVAL.pdf12 Apr 2018
Building plan approval or NA orderFile: NLR - NA Order IOD.pdf12 Apr 2018
Copy of the legal title reportFile: Title Report NLR.pdf12 Apr 2018
Details of encumbrancesFile: Encumberrance certificate.pdf12 Apr 2018
Copy of Layout Approval (in case of layout)File: PLOT LAYOUT APPROVAL.pdf12 Apr 2018
Building Plan Approval (IOD)File: NLR - NA Order IOD.pdf12 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: NLR - NA Order IOD.pdf12 Apr 2018

How this compares with Raigarh

84%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 39 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep City Of Music Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHOPOLI5,900+ in Raigarh

2 kmCity Of Music Phase IICompleted 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Nirvana Leisure Realty

Nirvana Leisure Realty has 4 registrations on MahaRERA, including City Of Music Phase I and City Of Music Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that City Of Music Phase II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if City Of Music Phase II is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of City Of Music Phase II?

The registered promoter entity is Nirvana Leisure Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in City Of Music Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against City Of Music Phase II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for City Of Music Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at City Of Music Phase II?

The professionals named in the filing: Architect: DEEPAK HIREMATH ASSOCIATES; Architect: DEEPAK HIREMATH; Engineer: Naik Associates; Engineer: DEEPAK HIREMATH; Chartered Accountant: SANJAY R SONI & ASSOCIATES; Chartered Accountant: SANJAY SONI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in City Of Music Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About City Of Music Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save City Of Music Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.