Home / Browse projects / Dakshina Kannada, Karnataka / CITY GATE

Registration approved Mixed Development project

CITY GATE

By MS BAWA BUILDERS

RG-KA-48991 · RERA PRM/KA/RERA/1257/334/PR/220104/004628 · Last updated on RERA Karnataka portal: 1 Jan 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2022Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 99 documents Report an error

CITY GATE is a Mixed Development project by MS BAWA BUILDERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/220104/004628 on 4 Jan 2022. Possession is promised by 26 Dec 2022.

At a glance

Project

  • NameCITY GATE
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/220104/004628
  • ReraGenie IDRG-KA-48991

Builder

  • NameMS BAWA BUILDERS
  • Entity typePartnership Firm
  • Authorized SignatoryABDUL KHADER K
  • OthersABDUL SAMAD RAFHI, MOHAMMED RASHID
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJan 2022PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Jan 2022
  • Promised completion26 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed99 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CITY GATE-----72

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 1 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 1 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,449 sq m
Named landowners4
LandownerVillageDistrict
MOHAMMAD NIZAMUDDIN SAYED--
MOHAMMED SALEEM ABOOBACKER--
Herold Pinto--
ABDUL WAHAD CHOUGULEY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTHOSH SHETTY
EngineerANAND BHAT

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed99

As listed on the registration, under the names the promoter filed them with; the newest 80 of 99 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/220104/004628 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Proforma sale agreement by including certain clausesFile: city gate proforma agreement of sale.pdf1 Jan 2022
Proforma sale deed by including certain clausesFile: city gate proforma sale deed.pdf1 Jan 2022
clarification by promoterFile: city gate clarification.pdf1 Jan 2022
profroma of agreement of saleFile: agreement for sale-proforma.pdf15 Dec 2021
proforma of sale deedFile: sale deed-proforma.pdf15 Dec 2021
clalrifcation by promoterFile: BB RERA.pdf15 Dec 2021
WATER NOCFile: city gate water noc.pdf1 Dec 2021
POWER NOCFile: CITY GATE MESCOME NOC.pdf1 Dec 2021
CLARIFICATION BY PROMOTERFile: Clarification by promoter.pdf1 Dec 2021
WATER & MESCOM NOCFile: WATER & POWER NOC.pdf1 Dec 2021
khatha register in the name of md. saleem abubkar & othersFile: katha.pdf26 Oct 2021
paratition deed of sushanthFile: PARTITION DEED OF SUSHANTH_compressed.pdf26 Oct 2021
sale deed of herald pintoFile: SALE DEED HERALD PINTO_compressed.pdf26 Oct 2021
sale deed of mohamed and othersFile: SALE DEED OF MOHAMED AND OTHER_compressed.pdf26 Oct 2021
clarification -second noticeFile: clarification-second notice.jpeg26 Oct 2021
city gate bank account detailsFile: city gate bank account.pdf26 Oct 2021
mescom noc and water supply nocFile: clarification-second notice.jpeg26 Oct 2021
Bank account name should be as per bank account direction circularFile: city gate clarification.pdf8 Oct 2021
Audited P&L account and Balance sheet with UDIN NUMBERFile: Audit report balance sheet profit & loss with udin number.pdf8 Oct 2021
conversion orderFile: conversion order.pdf8 Oct 2021
sale deed and title deedFile: JDA AGREEMNET FOR 37 29 CENTS_compressed.pdf8 Oct 2021
SANCTION PLANFile: approved building plan.pdf8 Oct 2021
relinquishment deedFile: Relinquishment Deed.pdf8 Oct 2021
POLLUTION NOCFile: pollution board noc.pdf8 Oct 2021
Power supplyFile: MESCOM TEMPARORY CONNECTION.pdf8 Oct 2021
REASON FOR DELAYFile: reason for delay.pdf8 Oct 2021
STP in the project is to be clarified by the promoterFile: STP noc by pollution board.pdf8 Oct 2021
SINGLE LAYOUTFile: single layout for 37 29 cents.pdf8 Oct 2021
CLARIFICATION BY PROMOTERFile: city gate clarification.pdf8 Oct 2021
CertificateFile: Certificate of Registration.PDF-
2 Commencement Certificate-
9 Approved Building Plan-
3 Approved Layout Plan-
13 Proforma for Sale Deed-
10 Proforma of Agreement for Sale-
4 Sale Deed & RTC-
11 Approved Section of Buildding Infrastructure Plan of Plotting-
5 Area Development Plan of Project Area-
12 Proforma Allotment Letter-
6 City Gate Brochure-
7 Project Speicification-
8 Encumbrance Certificate-
Notarised Affidavit-
JD Affidavit cum Declaration-
Khatha-
14 Collaboration Agrement Develp Agrememnt JDA-
1 Any other documents-
2 Conversion Certificate-
Unnamed document-
3 Utilisation Certificate-
2 Transfer of Development Right Certificate-
1 Relinquishment Deed-
3 Fire Force Department-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
7 Existing Layout Plan-
20 Existing Section Plan and Specification-
8 Change of Land Use-
Unnamed document-
Balance Sheet 2019 - 2020File: FY 20 21 Balance Sheet.pdf-
Balance Sheet 2018 - 2019File: FY 19 20 Balance Sheet.pdf-
Balance Sheet 2017 - 2018File: FY 18 19 Balance Sheet.pdf-
Audited Profit and Loss Statement 2019 - 2020File: FY 20 21 Profit & Loss.pdf-
Audited Profit and Loss Statement 2018 - 2019File: FY 19 20 Profit & Loss.pdf-
Audited Profit and Loss Statement 2017 - 2018File: FY 18 19 Profit & Loss.PDF-
Director's Report 2019 - 2020File: FY 20 21 Directors Report.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep CITY GATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmCITY GATEOther 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 29 registered projects within 2 km.

Builder: MS BAWA BUILDERS

MS BAWA BUILDERS has 3 registrations on RERA Karnataka, including CITY GATE and RUBY COMMERCIAL CENTRE. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if CITY GATE is delayed beyond 26 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CITY GATE?

The registered promoter entity is MS BAWA BUILDERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CITY GATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CITY GATE?

The professionals named in the filing: Architect: SANTHOSH SHETTY; Engineer: ANAND BHAT. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CITY GATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CITY GATE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CITY GATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.