CITY AARADHYA

By CITY REAL ESTATE

RG-KA-49855 · RERA PRM/KA/RERA/1257/334/PR/190626/002632

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 52 documents Report an error

CITY AARADHYA is a Mixed Development project by CITY REAL ESTATE in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/190626/002632 on 26 Jun 2019. Possession is promised by 30 Sep 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameCITY AARADHYA
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/190626/002632
  • ReraGenie IDRG-KA-49855

Builder

  • NameCITY REAL ESTATE
  • Entity typePartnership Firm
  • Authorized SignatorySHRIKANTH KAMATH
  • OthersP. RAGHAVENDRA KUDVA
  • DirectorsY. RAVINDRA RAO, SHRIKANTH KAMATH
  • Other registrations4 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredJun 2019First promiseDec 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Jun 2019
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CITY AARADHYA-----43

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,391 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.68 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEAM 2
EngineerANAND BHAT

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/190626/002632 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CERIFICATE OF REGISTRATION.jpg-
Commencement Certificate-
Approved Building Plan-
Layout Plan-
Proforma of Sale Deed-
Proforma of Sale Agreement-
Sale Deed-
Approved Building Plan-
Project Specification-
Updated EC-
AFFIDAVIT-
Khatha-
MOU OF AARADHYA-
Conversion Certificate-
Relinguish Deed-
NOC from Fire Department-
NOC from KSPCB-
Unnamed document-
Structural Safety Certificate-
Approved Building Plan-
Layout Plan-
Legal Openion-
Balance Sheet 2017 - 2018File: Balance Sheet - 2017-18.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet - 2016-17.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet - 2015-16.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit & Loss Account - 2017-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss Account - 2016-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss Account - 2015-16.pdf-
Auditor's Report 2017 - 2018File: Auditor Report - 2017-18.pdf-
Auditor's Report 2016 - 2017File: Auditor Report - 2016-17.pdf-
Auditor's Report 2015 - 2016File: Auditor Report - 2015-16.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR Acknowledgement - 2017-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR Acknowledgement - 2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR Acknowledgement - 2015-16.pdf-
Form B-
Prospectus/BrochureFile: City Aaradhya.jpg-
Advertisement Copy 1File: Advertisement copy - City Aaradhya.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_190626_002632.xlsx-
Stability CertificateFile: OCCUPATION CERTIFICATE.pdf-
NOC issued by the Fire Force department after completion of workFile: Fire noc.pdf-
Occupancy CertificateFile: OCCUPATION CERTIFICATE.pdf-
Consent for operation issued by KSPCBFile: KSPCB NOC (4).pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift Commission Letter.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: MESCOM NOC.jpeg-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Declaration on Water Supply.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: form6 Engineer Completion.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: form6 Engineer Completion.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Registered sale deed-Conveyance deed_compressed.pdf-
Architect certificate for having completed the work(in format no 5)File: Form 5 Architect Completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: FORM 4 CA Completion.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: form6 Engineer Completion.pdf-
AFFUDAVITFile: Affidavit for completion.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 9 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep CITY AARADHYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmCITY AARADHYAOther 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: CITY REAL ESTATE

CITY REAL ESTATE has 5 registrations on RERA Karnataka, including CITY COMPLEX and CITY DEEP. Its filings declare 5 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if CITY AARADHYA is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CITY AARADHYA?

The registered promoter entity is CITY REAL ESTATE, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CITY AARADHYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CITY AARADHYA?

The professionals named in the filing: Architect: TEAM 2; Engineer: ANAND BHAT. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CITY AARADHYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CITY AARADHYA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CITY AARADHYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.