ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / City AAdhya

Registration approved No litigation declared Mixed Development project

City AAdhya

By City Real Estate

RG-KA-33153 · RERA PRM/KA/RERA/1257/334/PR/280324/006761 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Feb 2027Possession promisedno revision filed
17 of 19Construction stages donefurthest along: Fire prevention and fire fighting..., 0%
7 of 36Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 111 documents Report an error

City AAdhya is a Mixed Development project by City Real Estate in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/280324/006761 on 28 Mar 2024. Possession is promised by 8 Feb 2027. 29 of the 36 units on this registration are recorded sold or booked, and 17 of 19 construction stages are filed complete.

At a glance

Project

  • NameCity AAdhya
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/280324/006761
  • ReraGenie IDRG-KA-33153

Builder

  • NameCity Real Estate
  • Entity typePartnership Firm
  • GSTIN29AAHFC7361F1ZB
  • Authorized SignatoryShrikanth Kamath
  • Other registrations4 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredMar 2024PromisedFeb 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Mar 2024
  • Promised completion8 Feb 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed111 files

Current status

81%29 of 36 units booked
12.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CITY AADHYA-----36

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 19 construction stages are filed complete. The stage furthest along is Fire prevention and fire fighting fitting and fixture with..., at 0%.

Building: 89% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work100%
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsNoNot applicable
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasYes0%
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
Neeraja Anantpadmakar Ayya--
Neeraja Anantpadmakar Ayya--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.75 cr
Cost incurredRs 1.06 cr
Spent of the estimate12.14%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 8.55 crRs 82.77 lakh
On-site expenditure-Consultants FeesRs 20.00 lakhRs 12.85 lakh
Payment of taxes-Rs 10.65 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNANDAN BHAT
EngineerGokul Raj
Chartered AccountantRajaram Shenoy Gurupura

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed111

As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/280324/006761 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CITY AADHYA CA CERTIFICATE.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: City Aadhya Architect Certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: City Aadhya Engineer Certificate.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CITY AADHYA CA CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: CITY AADHYA ARCHITECT CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: CITY AADHYA ENGINEER CERTIFICATE.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q4 FY 25-26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form no 5 Architech certificate.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form no 6 Engineer certificate.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: form 4 CA Q3 FY 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
profit and loss account, balance sheet & ITR, 2020-21File: FS 2021.pdf27 Mar 2024
profit and loss account, balance sheet & ITR, 2021-22File: FS 2022.pdf27 Mar 2024
profit and loss account, balance sheet & ITR, 2022-23File: FS 2023.pdf27 Mar 2024
form -1 CA certificateFile: FORM 1 CA CERTIFICATE.pdf27 Mar 2024
sources of fundsFile: City Aadhya Source of fund.pdf27 Mar 2024
CA SELF ATTESTED KYC ADHAR & MEMBERSHIPFile: CA self attesed KYC.pdf27 Mar 2024
GST CERTIFICATEFile: GST.pdf27 Mar 2024
RTCFile: RTC.pdf27 Mar 2024
MRFile: MR.pdf27 Mar 2024
title deed of the land ownerFile: title deed landowner.pdf27 Mar 2024
EC 2009-2024File: EC 2009-2024.pdf27 Mar 2024
EC 2013-2024File: EC 2013-2024.pdf27 Mar 2024
Single plot layout orderFile: City Aadhya Single Site.pdf27 Mar 2024
certified carpet area calculationFile: City Aadhya Carpet Area Statement.pdf27 Mar 2024
CDP mapFile: CDP PLAN.pdf27 Mar 2024
VILAGE MAPFile: village map-site highlited.pdf27 Mar 2024
commencement certificateFile: City Aadhya License.pdf27 Mar 2024
KSPCB CFEFile: pollution noc.pdf27 Mar 2024
ARCHITECT COAFile: architect COA.pdf27 Mar 2024
ARCHITECT CERTIFICATE FORM 2File: form 2 architect certificate.pdf27 Mar 2024
ARCHITECT CERTIFICATE FORM 5File: form 5 architect certificate.pdf27 Mar 2024
self attested copy of the Engineer license certificateFile: self atetsted engineer licence.pdf27 Mar 2024
CERTIFIED Amenities and Common areaFile: amenties and common area certified by engineer.pdf27 Mar 2024
Engineer certificate FORM 6File: engineer certificate form 6.pdf27 Mar 2024
STP DRAWING -CERTIFIED BY ENGINEERFile: stp plan certified by engineer.pdf27 Mar 2024
KLD STP DRAWINGFile: stp drawing.pdf27 Mar 2024
SELF ATTESED MESCOM NOCFile: Self attested Electricity Noc.pdf27 Mar 2024
SELF ATTESTED WATER NOCFile: Self attested Water Noc.pdf27 Mar 2024
MESCOM FEE RECEIPTFile: Mescom Noc Fees Receipt - City Aadhya.pdf27 Mar 2024
Land cost calculation sheetFile: City Aadhya Land cost Calculation Sheet.pdf27 Mar 2024
proforma of the Allotment letterFile: Proforma allotment letter.pdf27 Mar 2024
PROFORMA AOSFile: proforma AOS.pdf27 Mar 2024
estimated cost of construction certified by the EngineerFile: estimation cost by engineer.pdf27 Mar 2024
project specificationFile: City Aadhya - Specification.pdf27 Mar 2024
AFFIDAVIT 3(1)File: City Aadhya - Affidavit 3(1).pdf27 Mar 2024
IDYA VILLAGE MAPFile: iddya village map.pdf27 Mar 2024
CLARIFICATIONFile: Clarification on notice.pdf27 Mar 2024
fire force notificationFile: FIRE NOC-notification.pdf27 Mar 2024
RTC, survey 63/37 & 63/38-
Mutation, survey 63/37 & 63/38-
Encumbrance Certificate, survey 63/37 & 63/38-
Conversion/Alienation Order, survey 63/37 & 63/38-
JDA, survey 63/37 & 63/38-
Khatha, survey 63/37 & 63/38-
RTC, survey 63/39-
Mutation, survey 63/39-
Encumbrance Certificate, survey 63/39-
Conversion/Alienation Order, survey 63/39-
JDA, survey 63/39-
Khatha, survey 63/39-
Registration CertificateFile: CRE Certificate Of Registration .pdf-
Partnership DeedFile: CRE Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM 1 CA CERTIFICATE.pdf-
Certificate issued by Architect Form 2File: FORM-2 ARCHITECT CERTIFICATE.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate Form-3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: affidavit .pdf-
Certificate from Chartered AccountFile: FORM 1 CA CERTIFICATE.pdf-
Balance Sheet 2022 - 2023File: Balance sheet A Y 2023-24.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet A Y 2022-23.pdf-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
City DeepHaleyangadiCompleted-No date filed
City ComplexKulai, SurathkalCompleted-No date filed
City AaradhyaHosabettu, SurathkalCompleted-No date filed

How this compares with Dakshina Kannada

81%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep City AAdhya on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: City Real Estate

CITY REAL ESTATE has 5 registrations on RERA Karnataka, including CITY COMPLEX and CITY DEEP. Its filings declare 5 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if City AAdhya is delayed beyond 8 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of City AAdhya?

The registered promoter entity is City Real Estate, a partnership firm as per the filing. Its GSTIN 29AAHFC7361F1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in City AAdhya?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at City AAdhya?

The professionals named in the filing: Architect: NANDAN BHAT; Engineer: Gokul Raj; Chartered Accountant: Rajaram Shenoy Gurupura. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in City AAdhya?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About City AAdhya. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save City AAdhya to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.