Home / Browse projects / Dakshina Kannada, Karnataka / Chirag's Panchajanya Residency
Chirag's Panchajanya Residency
By CHIRAG PAANCHAJANYA DEVELOPERS
RG-KA-43600 · RERA PRM/KA/RERA/1257/334/PR/220817/005161 · Last updated on RERA Karnataka portal: 9 Aug 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Chirag's Panchajanya Residency is a Residential/Group Housing project by CHIRAG PAANCHAJANYA DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/220817/005161 on 17 Aug 2022. Possession is promised by 30 Mar 2025. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameChirag's Panchajanya Residency
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/220817/005161
- ReraGenie IDRG-KA-43600
Builder
- NameCHIRAG PAANCHAJANYA DEVELOPERS
- Entity typeCompany
- CINU45201KA2007PTC043793
- Authorized SignatoryB Hemanth Kumar
- DirectorMRS. MANISHA H KUMAR
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on17 Aug 2022
- Promised completion30 Mar 2025
- Revised completionRevised to 30 Mar 2025 (originally 30 Mar 2024)
- Buildings1 building record
- Documents filed124 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CHIRAG'S PANCHAJANYA RESIDENCY | - | - | - | 21 | 0 | 21 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 9 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
As on 9 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Narasimha Boloor | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Dhan Prakash |
| Engineer | Anand S.M |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Labour
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed124
As listed on the registration, under the names the promoter filed them with; the newest 80 of 124 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/220817/005161 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Rera reply letterFile: Rera reply letter 9 Aug 2022 .pdf | 9 Aug 2022 |
| corrected agreement copy SCHEDULE 'C' (SCHEDULE I)File: corrected agreement copy.pdf | 9 Aug 2022 |
| Rera letterFile: Rera letter 27 jul 2022.pdf | 27 Jul 2022 |
| Registered joint development agreementFile: registered JDA panchajanya residency.pdf | 27 Jul 2022 |
| Registered general power of attorneyFile: GPA Panchajanya residency.pdf | 27 Jul 2022 |
| Reply letter for your letter dated 08.02.2022File: Rera reply letter 14 Feb 2022.pdf | 14 Feb 2022 |
| STP Demarcation DrawingFile: MYSCAN_0196.PDF | 14 Feb 2022 |
| Reply letter for your mail dated 28.12.2021File: RERA Reply Letter 01 jan 2021.pdf | 4 Jan 2022 |
| Form-BFile: notarized form-B.pdf | 23 Dec 2021 |
| Deed of PartitionFile: Deed of Partition panchajanya.pdf | 16 Dec 2021 |
| Deed of DeclarationFile: Deed of Declaration panchajanya.pdf | 16 Dec 2021 |
| Registration certificate of Partnership deedFile: certificate of registration of firm.pdf | 20 Sep 2021 |
| Partnership deed between landownersFile: deed of partnership.pdf | 20 Sep 2021 |
| Indian partnership actFile: indian partnership act.pdf | 20 Sep 2021 |
| Memorandum of UnderstandingFile: memorandum of understanding.pdf | 20 Sep 2021 |
| CA UDIN NUMBER MENTIONED IN THE BALANCE SHEETFile: balance sheet 2019-20 latest.pdf | 17 Apr 2021 |
| CASH FLOW STATEMENTFile: cash flow statement 2019-20 latest.pdf | 17 Apr 2021 |
| PROFIT AND LOSS STATEMENTFile: profit and loss account 2019-20 latest.pdf | 17 Apr 2021 |
| Affidavit towards projectFile: affidavit (1).pdf | 17 Apr 2021 |
| Joint affidavit cum declarationFile: JD Affidavit cum declaration.pdf | 17 Apr 2021 |
| APPLICABLE EC FROM THE DATE OF PURCHASE 16-11-17File: EC.pdf | 17 Apr 2021 |
| Bank Account as per RERA NotificationFile: Bank Pass book.jpg | 1 Apr 2021 |
| Balance sheet of 2019-20File: balance sheet new 2019-20.pdf | 1 Apr 2021 |
| Profit and loss account 2019-20File: profit and loss statement 2019-20.pdf | 1 Apr 2021 |
| Csh flow statement 2019-20File: cash flow statement new 2019-20.pdf | 1 Apr 2021 |
| Auditor's report 2019-20File: auditor report 2019-20.pdf | 1 Apr 2021 |
| Director's reportFile: Directors Report 2019-20.pdf | 1 Apr 2021 |
| Registered agreementFile: registered joint development agreement.pdf | 1 Apr 2021 |
| Updated ECFile: EC.pdf | 1 Apr 2021 |
| Notarised form BFile: notarized form-B.pdf | 1 Apr 2021 |
| Project specificationsFile: Chirag Panchajanya Brochure.pdf | 1 Apr 2021 |
| Sanctioned floor plan, Approved Elevation plan, Cross section planFile: MYSCAN_0195.PDF | 1 Apr 2021 |
| Sanctioned floor plan, Approved elevation plan, Cross section planFile: MYSCAN_0196.PDF | 1 Apr 2021 |
| NOC;S - FIREFile: NOC fire force.pdf | 1 Apr 2021 |
| NOC - CRZFile: CRZ NOC.pdf | 1 Apr 2021 |
| NOC - Pollution Control BoardFile: pollution NOC.pdf | 1 Apr 2021 |
| CertificateFile: company registration certificate.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: EX 1 Arc certificate - work completed.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: EX 5 Engg certificate - work completed.pdf | - |
| CA Certificate for Funds UtilizationFile: EX 3 Chartered Accountant extension 1.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: EX 2 Arc certificate - work pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: EX 6 Engg certificate - work pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: EX 4 Chartered Accountant extension 2.pdf | - |
| AffidavitFile: EX 7 Affidavit for seeking extention of registered projec.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: Rera form B.pdf | - |
| Document 2File: panchajanya mescom NOC.pdf | - |
| Document 3File: NOC water supply.pdf | - |
| Document 4File: NOC fire force.pdf | - |
| Document 5File: building licence.pdf | - |
| Document 6File: sanction plan.pdf | - |
| Document 7File: Notarized Affidavit for 3(1) Voliation.pdf | - |
| Document 8File: litigation affidavit.pdf | - |
| Document 9File: CRZ NOC.pdf | - |
| Document 10File: Affidavit paying componsation.pdf | - |
| Document 11File: EC panchajanya.pdf | - |
| Document 12File: typical floor site plan.PDF | - |
| Document 13File: section first ground floor plan.PDF | - |
| Document 14File: Change Request Conirmation.pdf | - |
| Document 15File: proforma AOS.pdf | - |
| Document 16File: Proforma allotment letter.pdf | - |
| Building License | - |
| MYSCAN_0196 | - |
| Office order | - |
| Proforma of sale deed | - |
| Proforma of agreement for sale | - |
| sale deed-merged | - |
| MYSCAN_0196 | - |
| NA-min | - |
| Chirag Panchajanya Brochure | - |
| NA-min | - |
| Encumbrance certificate | - |
| Notarized Affidavit for 3(1) Voliation | - |
| JD Affidavit cum declaration | - |
| joint khatha | - |
| Agreement | - |
| Deed of Indenture | - |
| Conversion certificate | - |
| Unnamed document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep Chirag's Panchajanya Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 84 registered projects within 2 km.
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: CHIRAG PAANCHAJANYA DEVELOPERS
CHIRAG PAANCHAJANYA DEVELOPERS has 1 registration on RERA Karnataka, including Chirag's Panchajanya Residency. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if Chirag's Panchajanya Residency is delayed beyond 30 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Chirag's Panchajanya Residency?
The registered promoter entity is CHIRAG PAANCHAJANYA DEVELOPERS, a company as per the filing. Its CIN U45201KA2007PTC043793 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Chirag's Panchajanya Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Chirag's Panchajanya Residency?
The professionals named in the filing: Architect: Dhan Prakash; Engineer: Anand S.M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Chirag's Panchajanya Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback