Home / Browse projects / Dakshina Kannada, Karnataka / Cherry Enclaves
Cherry Enclaves
RG-KA-46910 · RERA PRM/KA/RERA/1257/333/PR/300626/008777 · Last updated on RERA Karnataka portal: 13 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Cherry Enclaves is a Residential/Group Housing project by Das Builders & Developers in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/333/PR/300626/008777 on 30 Jun 2026. Possession is promised by 27 Feb 2028. 13 of the 20 units on this registration are recorded sold or booked, and 3 of 14 construction stages are filed complete.
At a glance
Project
- NameCherry Enclaves
- TypeResidential/Group Housing
- Location
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/333/PR/300626/008777
- ReraGenie IDRG-KA-46910
Builder
- NameDas Builders & Developers
- Entity typePartnership Firm
- GSTIN29AAYFD4627N1ZH
- Authorized SignatoryMohandas Shetty
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Jun 2026
- Promised completion27 Feb 2028
- Revised completionNone
- Buildings1 building record
- Documents filed103 files
Current status
Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CHERRY ENCLAVES | - | - | - | 20 | 0 | 20 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 14 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 80%.
Building: 45% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 80% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 70% |
| Masonry Construction | 70% |
| Plastering inside , outside & Ceiling | 70% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 45% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 50% |
| Sewage and Drainage System | Yes | 10% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 50% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 25% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 10% |
| Storm water drains | Yes | 10% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 35% |
| Lifts | Yes | 10% |
| Corridor/Lobbies | Yes | 35% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 10% |
| Basement | Yes | 100% |
| Terrace | Yes | 0% |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Bharathi M Shetty | - | - |
| M/S DAS BUILDERS AND DEVELOPERS | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 2.41 cr | Rs 96.76 lakh |
| On-site expenditure-Salaries of workers | - | Rs 4.56 lakh |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | - | Rs 48.04 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJEEV . S |
| Engineer | Bhavish R Salian |
| Chartered Accountant | Shiva Kumar K |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed103
As listed on the registration, under the names the promoter filed them with; the newest 80 of 103 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/333/PR/300626/008777 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Cherry.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 cherry.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: form 6 Cherry.pdf | 13 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 13 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 13 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM - 4 CA Certificate.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: 09-07 FORM - 5.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 09-07 FORM - 6.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| BANK LETTERFile: bank letter.pdf | 10 Jun 2026 |
| AFFIDAVITFile: Affidavit Bank.pdf | 10 Jun 2026 |
| LOAN SANCTION LETTERFile: loan sanction letter.pdf | 10 Jun 2026 |
| FORM 1File: FORM 1.pdf | 10 Jun 2026 |
| CONTRIBUTION DEEDFile: Contribution Deed.pdf | 10 Jun 2026 |
| ENCUMBRANCE CERTIFICATEFile: EC.pdf | 10 Jun 2026 |
| ENGINEER CERTIFICATEFile: Form 6.pdf | 10 Jun 2026 |
| AGREEMENT FOR SALEFile: AFS.pdf | 10 Jun 2026 |
| ALLOTMENT LETTERFile: ALLOTMENT letter.pdf | 10 Jun 2026 |
| CLARIFICATIONFile: Clarification - Cherry Enclave.pdf | 10 Jun 2026 |
| RERA DESIGNATED ACCOUNT STATEMENTFile: Das Builders & Developers RERA Current Account.pdf | 10 Jun 2026 |
| PROFIT AND LOSS A/C & BS 23-24 MOHANDASFile: MOHANDAS 23-24 P&L AND BS.pdf | 21 Apr 2026 |
| PROFIT AND LOSS A/C & BS 24-25 MOHANDASFile: MOHANDAS 24-25 P &L AND BS.pdf | 21 Apr 2026 |
| SOURCES OF FUNDSFile: loan sanction letter.pdf | 21 Apr 2026 |
| CA CERTIFICATE- FORM 1File: FORM 1.pdf | 21 Apr 2026 |
| ECFile: EC.pdf | 21 Apr 2026 |
| JDAFile: JDA.pdf | 21 Apr 2026 |
| SINGLE PLOT LAYOUT PLANFile: PROPOSED SITE.jpeg | 21 Apr 2026 |
| BUILDING LICENSEFile: Building Licence.pdf | 21 Apr 2026 |
| ADLR CERTIFIED SKETCHFile: ADLR Certified Survey Sketch.pdf | 21 Apr 2026 |
| PROPOSED SITEFile: PROPOSED SITE.jpeg | 21 Apr 2026 |
| APPROVED PLANFile: Sketch (1).pdf | 21 Apr 2026 |
| CDP 1File: Dist No 12B.pdf | 21 Apr 2026 |
| CDP 2File: Dist No 13A.pdf | 21 Apr 2026 |
| CDP 3File: Dist No 14A.pdf | 21 Apr 2026 |
| VILLAGE MAPFile: PROPOSED SITE.jpeg | 21 Apr 2026 |
| WATER NOCFile: WATER NOC.pdf | 21 Apr 2026 |
| SPECIFICATIONSFile: SPECIFICATION.pdf | 21 Apr 2026 |
| FORM 6File: Form 6.pdf | 21 Apr 2026 |
| STPFile: S T P Drawing.pdf | 21 Apr 2026 |
| GUIDANACE VALUEFile: Guidance Value (1).pdf | 21 Apr 2026 |
| ALLOTMENT LETTERFile: ALLOTMENT letter.pdf | 21 Apr 2026 |
| PROFIT AND LOSS A/C & BS 25-26 MOHANDASFile: MOHANDAS 25-26 P &L AND BS.pdf | 21 Apr 2026 |
| PROFIT AND LOSS A/C & BS 23-24 BHARATHIFile: Bharathi 23-24 P&L AND BS.pdf | 21 Apr 2026 |
| PROFIT AND LOSS A/C & BS 24-25 BHARATHIFile: Bharathi 24-25P&L AND BS.pdf | 21 Apr 2026 |
| PROFIT AND LOSS A/C & BS 25-26 BHARATHIFile: Bharathi 25-26 P&L AND BS.pdf | 21 Apr 2026 |
| AFSFile: AOS _merged.pdf | 21 Apr 2026 |
| CLARIFICATIONSFile: Clarifications.pdf | 21 Apr 2026 |
| CLARIFICATION RELATING TO JDAFile: CLARIFICATION RELATING TO JDA.pdf | 21 Apr 2026 |
| CASE LAW RELATING TO CLARIFICATIONFile: CASE LAW.pdf | 21 Apr 2026 |
| RTC, survey 2/1(P4) | - |
| Mutation, survey 2/1(P4) | - |
| Encumbrance Certificate, survey 2/1(P4) | - |
| Conversion/Alienation Order, survey 2/1(P4) | - |
| Sale/Title/Gift Deed, survey 2/1(P4) | - |
| Khatha, survey 2/1(P4) | - |
| Registration CertificateFile: Partnership Registration Certificate.pdf | - |
| GST CertificateFile: DAS BUILDERS GSTIN.pdf | - |
| Partnership DeedFile: PARTNERSHIP DEED.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: FORM 1.pdf | - |
| Certificate issued by Architect Form 2File: FORM -2.pdf | - |
| Certificate issued by Engineer Form 3File: FORM - 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit No claim & No Litigation.pdf | - |
| Balance Sheet 2024 - 2025File: NA 1.pdf | - |
| Balance Sheet 2023 - 2024File: NA 1.pdf | - |
| Balance Sheet 2022 - 2023File: NA 1.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: NA 1.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: NA 1.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: NA 1.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: NA 1.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: NA 1.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: NA 1.pdf | - |
| Building Licence | - |
| Plan | - |
| Plan | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep Cherry Enclaves on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: Das Builders & Developers
Das Builders & Developers has 1 registration on RERA Karnataka, including Cherry Enclaves. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if Cherry Enclaves is delayed beyond 27 Feb 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Cherry Enclaves?
The registered promoter entity is Das Builders & Developers, a partnership firm as per the filing. Its GSTIN 29AAYFD4627N1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Cherry Enclaves?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Cherry Enclaves?
The professionals named in the filing: Architect: RAJEEV . S; Engineer: Bhavish R Salian; Chartered Accountant: Shiva Kumar K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Cherry Enclaves?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.