Home / Browse projects / Mumbai Suburban, Maharashtra / CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED
CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED
By CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED
RG-MH-29873 · RERA P51800029344 · Last updated on MahaRERA portal: 7 Feb 2025
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED is a Residential / Group Housing project by CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029344 on 18 May 2021. The registration is recorded completed; possession was promised by 31 Dec 2025. 1 complaint is on record with the regulator.
At a glance
Project
- NameCHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED
- TypeResidential / Group Housing
- Location
- RSC 11
- CHARKOP KANDIVALI WEST
- Borivali
- Mumbai Suburban
- 400067
- Pincode400067
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800029344
- ReraGenie IDRG-MH-29873
Builder
- NameCHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED
- Entity typeSociety
- GSTIN27AAAAC3813G1Z5
- SecretoryANIL WAMAN SAWANT
- ChairpersonJITENDRA R DANDEKAR
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on18 May 2021
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed82 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CHARKOP SHWETAMBARA CO-OPERATIVE HOUSING SOCIETY LIMITED | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
CHARKOP SHWETAMBARA CO-OPERATIVE HOUSING SOCIETY LIMITED: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 15% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed63
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HARSHAD MAANOHAAR MORE |
| Engineer | HARSHAD MAANOHAAR MORE |
| Chartered Accountant | D E BHANAGE AND COMPANY |
| Chartered Accountant | NILESH G PALANDE AND ASSOCIATES |
| Chartered Accountant | R V B & Associates Proprietor CA Rahul Vishnu Bombale |
| Chartered Accountant | DEEPAK S PAMECHA AND ASSOCIATES PROPRIETOR DEEPAK S PAMECHA |
| Partner | Role in project |
|---|---|
| CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12602957 | DEVENDRA PANDURANG DAHIBAWKAR | CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED | 19/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 May 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 May 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Sep 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Feb 2025
Documents filed82
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULL OC.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Charkop Shwetambara From 3 (10-01-2025) SIGNED_compressed.pdf | 28 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM - 5 - SIGNED - F.pdf | 22 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shwetambara_FORM 1_ARCHITECT CERTIFICATE_Q-3_JULY TO SEPT 2024.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2024-09-30_Form 2 Engineers certificate.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CHARKOP SHWETAMBARA CHSL SIGNED FORM-3.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shwetambara_FORM 1_ARCHITECT CERTIFICATE_Q-2_APRIL TO JUNE 2024.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2024-06-30_Shwetambara_Form 2 Engineers certificate.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 - CHARKOP SHWETAMBARA CHSL - 30062024 - SIGNED - UPLOADED.pdf | 25 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_Charkop Shwetambara_Q1_2024.pdf | 1 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1 - SIGNED.pdf | 30 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 -SINGED.pdf | 30 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 SIGNED.pdf | 17 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-12-31_Form 2 Engineers certificate.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1 - OCT TO DEC 23.pdf | 24 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - SINGED.pdf | 24 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC_signed.pdf | 14 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - FINAL SINGED FY 2022-23_compressed.pdf | 14 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q-1 APRIL TO JUNE 2023.pdf | 2 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q-2 JULY TO SEPT 2023.pdf | 2 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-06-30_Form 2 Engineers certificate.pdf | 2 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-09-30_Form 2 Engineers certificate.pdf | 2 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q1 - SINGED.pdf | 28 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Q2 SINGED.pdf | 28 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A - FY 2022-23 - SINGED.pdf | 8 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Charkop Shwetambara CHSL FORM 5.pdf | 19 Oct 2023 |
| Building plan approvalFile: Approved Plan - 21-08-2023 - 1-4.pdf | 26 Sep 2023 |
| Building plan approvalFile: Approved Plan - 21-08-2023 - 5-7.pdf | 26 Sep 2023 |
| Building plan approvalFile: Approved Plan - 21-08-2023 - 8-11.pdf | 26 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan - 21-08-2023 - 1-4.pdf | 26 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan - 21-08-2023 - 5-7.pdf | 26 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Approved Plan - 21-08-2023 - 8-11.pdf | 26 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 01 FORM 2A_Charkop Shwetambara_Q1_2021.pdf | 23 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 02 FORM 2A_Charkop Shwetambara_Q2_2021.pdf | 23 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 03 FORM 2A_Charkop Shwetambara_Q3_2021 .pdf | 23 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 04 FORM 2A_Charkop Shwetambara_Q4_2022.pdf | 23 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q-3 ARCHITECTS CERTIFICATE - FORM 1- sign.pdf | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 - FORM - 2.pdf | 8 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 - Shwetambara chsl Compressed.pdf | 30 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - SHWETAMBARA CHSL.pdf | 23 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q-1 Architect Certificate Form- 300922.pdf | 2 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q-1 ENGINEERS CERTIFICATE as on 30-09-2022.pdf | 2 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 SHWETAMBARA CHSL AS ON 30092022.pdf | 1 Nov 2022 |
| OtherFile: FORM 5 - SHWETAMBARA CHSL.pdf | 26 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q-1 Architect Certificate Form-1 APRIL TO JUNE 2022.pdf | 18 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q-1 ENGINEERS CERTIFICATE as on 30-06-2022.pdf | 18 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 SHWETAMBARA CHSL AS ON 30062022 -compressed.pdf | 31 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q-4 Architect Certificate Form-1 JAN TO MARCH 2022.pdf | 10 Jun 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 2022.pdf | 10 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SHWETAMBARA 1102021 - 31122021_compressed.pdf | 10 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (2).pdf | 15 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3_compressed.pdf | 16 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shwetambara Form 3_ QTR 1 FY 21-22.pdf | 16 Aug 2021 |
| Building plan approvalFile: 05_BUILDING_APPROVAL_PLAN_05.pdf | 7 May 2021 |
| Layout approvalFile: 04_BUILDING_IOA_01.pdf | 7 May 2021 |
| Layout approvalFile: 04_BUILDING_IOA_02.pdf | 7 May 2021 |
| Layout approvalFile: 04_BUILDING_IOA_03.pdf | 7 May 2021 |
| Layout approvalFile: 04_BUILDING_IOA_PLAN_compressed.pdf | 7 May 2021 |
| Building plan approvalFile: 05_BUILDING_APPROVAL_PLAN_01.pdf | 7 May 2021 |
| Building plan approvalFile: 05_BUILDING_APPROVAL_PLAN_02.pdf | 7 May 2021 |
| Building plan approvalFile: 05_BUILDING_APPROVAL_PLAN_03.pdf | 7 May 2021 |
| Building plan approvalFile: 05_BUILDING_APPROVAL_PLAN_04.pdf | 7 May 2021 |
| PAN CardFile: 01_PAN_CHARKOP_SHWETAMBARA_CHS.pdf | 7 May 2021 |
| Copy of the legal title reportFile: 02_LEGAL_TITILE_CERTIFICATE_compressed.pdf | 7 May 2021 |
| Details of encumbrancesFile: 03_ENCUMBERANCE_compressed.pdf | 7 May 2021 |
| Copy of Layout Approval (in case of layout)File: 04_BUILDING_IOA_01.pdf | 7 May 2021 |
| Copy of Layout Approval (in case of layout)File: 04_BUILDING_IOA_02.pdf | 7 May 2021 |
| Copy of Layout Approval (in case of layout)File: 04_BUILDING_IOA_03.pdf | 7 May 2021 |
| Copy of Layout Approval (in case of layout)File: 04_BUILDING_IOA_PLAN_compressed.pdf | 7 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 05_BUILDING_APPROVAL_PLAN_01.pdf | 7 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 05_BUILDING_APPROVAL_PLAN_02.pdf | 7 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 05_BUILDING_APPROVAL_PLAN_03.pdf | 7 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 05_BUILDING_APPROVAL_PLAN_04.pdf | 7 May 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 05_BUILDING_APPROVAL_PLAN_05.pdf | 7 May 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: 06_CC_CHARKOP_SHWETAMBARA_CHS_compressed.pdf | 7 May 2021 |
| Declaration in FORM BFile: 10_FORM_B_AFFIDAVIT_CUM_DECLERATION_compressed.pdf | 7 May 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11_FORM_1_ARCHITECH_CERTIFICATE.pdf | 7 May 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12_FORM_2_ENGINEER_CERTIFICATE.pdf | 7 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13_FORM_3_CA_CERTIFICATE.pdf | 7 May 2021 |
| Proforma of Allotment letterFile: 11_DRAFT_AGREEMENT_FOR_SALE.pdf | 7 May 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 82 filed documents as one ZIP, foldered, with a manifest
Keep CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHARKOP KANDIVALI WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 195 registered projects within 2 km.
Ruparel Optima Ph I
Ruparel Infra & Realty Pvt Ltd
"SALE BLDG NO. 6 (A & B) WING KNOWN AS NORTHER
N.ROSE DEVELOPERS PVT LTD
JP Commerz
Metallica Industries Limited
Ruparel Skygreens I
Shree Siddhivinayak Infrastructure & Realt
ShreejiAikyam
Rushabh Developers
Shiv Vardaan
NAVKARMIK HOMES LLP, URVI CONSTRUCTION
See every Mumbai Suburban project, with the district possession charts
Builder: CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED
CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED has 1 registration on MahaRERA, including CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED?
The registered promoter entity is CHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED, a society as per the filing. Its GSTIN 27AAAAC3813G1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED?
The professionals named in the filing: Architect: HARSHAD MAANOHAAR MORE; Engineer: HARSHAD MAANOHAAR MORE; Chartered Accountant: D E BHANAGE AND COMPANY; Chartered Accountant: NILESH G PALANDE AND ASSOCIATES; Chartered Accountant: R V B & Associates Proprietor CA Rahul Vishnu Bombale; Chartered Accountant: DEEPAK S PAMECHA AND ASSOCIATES PROPRIETOR DEEPAK S PAMECHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback