CHAITRABAN RESIDENCY
RG-MH-86069 · RERA P52100016643 · Last updated on MahaRERA portal: 23 Nov 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- Completion date moved by 25 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CHAITRABAN RESIDENCY is a Residential / Group Housing project by RELIVE CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100016643 on 5 Jun 2018. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 25 months from the original filing.
At a glance
Project
- NameCHAITRABAN RESIDENCY
- TypeResidential / Group Housing
- Location
- PUNE - POUD ROAD
- BHAIRAVNATH NAGAR
- Pirangut
- Mulshi
- Pune
- 412115
- Pincode412115
- RERA no.P52100016643
- ReraGenie IDRG-MH-86069
Builder
- NameRELIVE CONSTRUCTION
- Entity typePartnership
- PartnersDEEPAK POPATRAO MARNE, DHONDIBA TUKARAM KEDARI, GAURI MOHAN GOLE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on5 Jun 2018
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 30 May 2022)
- Buildings2 building records
- Documents filed63 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CHAITRABAN A | NA | 2 | 0 | 0 | 0 | 0 |
| CHAITRABAN B | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.
CHAITRABAN A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CHAITRABAN B68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities15
As on 23 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 30% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 30% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership9
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SANGITA ASHOK GOLE | Pirangut | Pune |
| RAJESH ASHOK GOLE | Pirangut | Pune |
| YOGESH ASHOK GOLE | Pirangut | Pune |
| DEEPAK POPATRAO MARNE | Pirangut | Pune |
| ANIL DAMODAR GOLE | Pirangut | Pune |
| SANJAY GANAPATI PATIL | Pirangut | Pune |
| DHONDIBA TUKARAM KEDARI | Pirangut | Pune |
| GAURI MOHAN GOLE | Pirangut | Pune |
| SANDHYA PANDURANG TAWARE | charholi kh | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JAIDEEP SUNIL DESHPANDE |
| Engineer | SATISH GHANEKAR |
| Partner | Role in project |
|---|---|
| RELIVE CONSTRUCTION | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReason for delay is due to Change in Contractor as earlier construction pace was pretty slow hence changed the contractor in month of dec, 22 & now we are aiming to close the project by end of this year hence we are looking for an extension of 12 months.
Reason as filed by the promoterSir Building is almost completed we are awaiting Lift NOC and Fire NOC before getting final completion Certificate for Wing B from competent authority, as these NOC are depend on third party their might be delay in getting those NOC's hence we are requesting you for extension of project completion date to 30 June 2024. I have also uploaded additional documents as asked for by your office in document upload tab and same are attached here also for your easy access.
Reason as filed by the promoterDue to covid 19 pandemic since 2020 we face lot of difficulties in getting required material and labour on time. Now all is working well booking also flowing contentiously and we are very much sure about the completion of the project in extended time. Please kindly look into it and allow us some time relief to complete the project.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 May 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 May 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 May 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 May 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed63
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Affidavit cum Decelaration.pdf | 23 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 23 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 23 Nov 2023 |
| Certificates of CA (Form 3)File: CA Certificate 13 march 23.pdf | 2 Nov 2023 |
| Certificates of CA (Form 3)File: CA Certificate 02nd Aug 2023.pdf | 2 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5 FY 2022 23.pdf | 2 Nov 2023 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 30 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account Declaration.pdf | 30 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation Declaration.pdf | 30 Oct 2023 |
| Details of encumbrancesFile: 1 Form B Encumberance Letter.pdf | 25 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: 1 Form B Encumberance Letter.pdf | 25 Oct 2023 |
| Details of encumbrances concerned to LegalFile: 1 Form B Encumberance Letter.pdf | 25 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Quality Assurance Certificate from Engineer.pdf | 25 Oct 2023 |
| Proforma of Agreement for saleFile: Draft of Agreement.pdf | 25 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: LETTER FOR CHAITRABAN RESIDENCY REGARDING RERA UPDACTION.pdf | 25 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1) (1).pdf | 8 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (2) (1).pdf | 8 Jun 2023 |
| Declaration in FORM BFile: New Document(73)_compressed.pdf | 23 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form-2 'chitraban.pdf | 23 May 2023 |
| Disclosure of sold/ booked inventoryFile: 2 Disclosure of sold_ booked inventory (1).pdf | 23 May 2023 |
| Certificates of CA (Form 3)File: New Document(4) (1).pdf | 23 May 2023 |
| Certificates of CA (Form 3)File: New Document(5).pdf | 23 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance Chitarban.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: New Document(41)_compressed (1).pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: CA Certificate compressed (1).pdf | 19 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: CA Certificate compressed (1).pdf | 19 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf | 13 May 2023 |
| Declaration about Commencement CertificateFile: Declaration of Commencements.pdf | 29 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PIRANGUT RERA 1.pdf | 29 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold and sold inventari rera letter (2).pdf | 29 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5_compressed.pdf | 29 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 23 Feb 2023 |
| CERSAI detailsFile: Cersai Declaration.pdf | 1 Jul 2022 |
| CERSAI detailsFile: Marathi Bandhkam Vyavsaik Association Reg Certificate.pdf | 22 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 FY 2017-18.pdf | 19 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 2018 19.pdf | 19 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019 20.pdf | 19 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020 21.pdf | 19 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2 A 2019 20.pdf | 17 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2 A 2020 21.pdf | 17 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory B Wing.pdf | 17 Jun 2022 |
| Declaration about Commencement CertificateFile: Commencemnt Certificate.pdf | 10 Jun 2022 |
| Details of encumbrancesFile: Encumbrance.pdf | 1 Jun 2018 |
| Declaration in FORM BFile: From B pdf New.pdf | 1 Jun 2018 |
| Layout approvalFile: Blue Print 1.pdf | 26 May 2018 |
| Building plan approvalFile: Blue Print 2.pdf | 26 May 2018 |
| Building plan approvalFile: Blue Print 3.pdf | 26 May 2018 |
| PAN CardFile: chitraban pan card pdf.pdf | 26 May 2018 |
| Copy of the legal title reportFile: chaitraban sarch pdf.pdf | 26 May 2018 |
| Details of encumbrancesFile: ENCUMBRANCE PDF.pdf | 26 May 2018 |
| Copy of Layout Approval (in case of layout)File: Blue Print 1.pdf | 26 May 2018 |
| Building Plan Approval (IOD)File: Blue Print 2.pdf | 26 May 2018 |
| Building Plan Approval (IOD)File: Blue Print 3.pdf | 26 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: PMRDA PARAVANGI PATRA.pdf | 26 May 2018 |
| Declaration in FORM BFile: Form B2 New Pdf.pdf | 26 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: chatraban architects pdf.pdf | 26 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: chaitraban engineers pdf 1.pdf | 26 May 2018 |
| Certificates of CA (Form 3)File: chaitraban CA pdf.pdf | 26 May 2018 |
| Proforma of Allotment letterFile: Chaitraban_Sample Draft.pdf | 26 May 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Partnarship Deed Part 1.pdf | 26 May 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Partnarship Deed Part 2.pdf | 26 May 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Partnarsheep Deed.pdf | 26 May 2018 |
| OtherFile: NA Order Pdf.pdf | 26 May 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 63 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep CHAITRABAN RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHAIRAVNATH NAGAR13,700+ in Pune
Avian Valley - Solaire
KAKADE ESTATE DEVELOPERS PVT. LTD.
Park Pebbles Phase I
M/s Rainbow Purple Construction LLP
Mahindra Rivenza Phase 2
Mahindra Lifespace Developers limited
Mahindra Rivenza Phase 1
Mahindra Lifespace Developers limited
FOREST TRAILS ATHASHRI B3
LAVIM DEVELOPERS PVT LTD
KOHINOOR WOODSHIRE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: RELIVE CONSTRUCTION
RELIVE CONSTRUCTION has 1 registration on MahaRERA, including CHAITRABAN RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that CHAITRABAN RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if CHAITRABAN RESIDENCY is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CHAITRABAN RESIDENCY?
The registered promoter entity is RELIVE CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CHAITRABAN RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CHAITRABAN RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CHAITRABAN RESIDENCY?
The professionals named in the filing: Architect: JAIDEEP SUNIL DESHPANDE; Engineer: SATISH GHANEKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CHAITRABAN RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback