Home / Browse projects / Pune, Maharashtra / CHAITRABAN RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

CHAITRABAN RESIDENCY

By RELIVE CONSTRUCTION

RG-MH-86069 · RERA P52100016643 · Last updated on MahaRERA portal: 23 Nov 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 25 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
4 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

CHAITRABAN RESIDENCY is a Residential / Group Housing project by RELIVE CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100016643 on 5 Jun 2018. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 25 months from the original filing.

At a glance

Project

  • NameCHAITRABAN RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • PUNE - POUD ROAD
    • BHAIRAVNATH NAGAR
    • Pirangut
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • RERA no.P52100016643
  • ReraGenie IDRG-MH-86069

Builder

  • NameRELIVE CONSTRUCTION
  • Entity typePartnership
  • PartnersDEEPAK POPATRAO MARNE, DHONDIBA TUKARAM KEDARI, GAURI MOHAN GOLE

Key dates

28 months past promisethis monthRegisteredJun 2018First promiseMay 2022Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Jun 2018
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 May 2022)
  • Buildings2 building records
  • Documents filed63 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CHAITRABAN ANA20000
CHAITRABAN BNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

CHAITRABAN A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
CHAITRABAN B68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 23 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes30%
Street LightingNoNot applicable
Community BuildingsYes30%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
SANGITA ASHOK GOLEPirangutPune
RAJESH ASHOK GOLEPirangutPune
YOGESH ASHOK GOLEPirangutPune
DEEPAK POPATRAO MARNEPirangutPune
ANIL DAMODAR GOLEPirangutPune
SANJAY GANAPATI PATILPirangutPune
DHONDIBA TUKARAM KEDARIPirangutPune
GAURI MOHAN GOLEPirangutPune
SANDHYA PANDURANG TAWAREcharholi khPune

Approvals and building plan

Permissible FSI3459.68
Proposed, not sanctioned3,460 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAHADHU NANA COMPLEX GHOTAWADE PHATA AT KASARAMBOLI AMBHARVET PIRANGUT MULSHI PUNE 412108

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAIDEEP SUNIL DESHPANDE
EngineerSATISH GHANEKAR
PartnerRole in project
RELIVE CONSTRUCTION-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016502May 2022 → Dec 2023

Reason as filed by the promoterReason for delay is due to Change in Contractor as earlier construction pace was pretty slow hence changed the contractor in month of dec, 22 & now we are aiming to close the project by end of this year hence we are looking for an extension of 12 months.

EXT52100017963May 2022 → Jun 2024

Reason as filed by the promoterSir Building is almost completed we are awaiting Lift NOC and Fire NOC before getting final completion Certificate for Wing B from competent authority, as these NOC are depend on third party their might be delay in getting those NOC's hence we are requesting you for extension of project completion date to 30 June 2024. I have also uploaded additional documents as asked for by your office in document upload tab and same are attached here also for your easy access.

EXT52100011957May 2022 → May 2023

Reason as filed by the promoterDue to covid 19 pandemic since 2020 we face lot of difficulties in getting required material and labour on time. Now all is working well booking also flowing contentiously and we are very much sure about the completion of the project in extended time. Please kindly look into it and allow us some time relief to complete the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Affidavit cum Decelaration.pdf23 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf23 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Nov 2023
Certificates of CA (Form 3)File: CA Certificate 13 march 23.pdf2 Nov 2023
Certificates of CA (Form 3)File: CA Certificate 02nd Aug 2023.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5 FY 2022 23.pdf2 Nov 2023
Proforma of Allotment letterFile: Allotment letter.pdf30 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account Declaration.pdf30 Oct 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation Declaration.pdf30 Oct 2023
Details of encumbrancesFile: 1 Form B Encumberance Letter.pdf25 Oct 2023
Details of encumbrances concerned to FinanceFile: 1 Form B Encumberance Letter.pdf25 Oct 2023
Details of encumbrances concerned to LegalFile: 1 Form B Encumberance Letter.pdf25 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Quality Assurance Certificate from Engineer.pdf25 Oct 2023
Proforma of Agreement for saleFile: Draft of Agreement.pdf25 Oct 2023
Deviation Report with respect to model copy of AgreementFile: LETTER FOR CHAITRABAN RESIDENCY REGARDING RERA UPDACTION.pdf25 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1) (1).pdf8 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (2) (1).pdf8 Jun 2023
Declaration in FORM BFile: New Document(73)_compressed.pdf23 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form-2 'chitraban.pdf23 May 2023
Disclosure of sold/ booked inventoryFile: 2 Disclosure of sold_ booked inventory (1).pdf23 May 2023
Certificates of CA (Form 3)File: New Document(4) (1).pdf23 May 2023
Certificates of CA (Form 3)File: New Document(5).pdf23 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance Chitarban.pdf19 May 2023
Certificates of CA (Form 3)File: New Document(41)_compressed (1).pdf19 May 2023
Certificates of CA (Form 3)File: CA Certificate compressed (1).pdf19 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: CA Certificate compressed (1).pdf19 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf13 May 2023
Declaration about Commencement CertificateFile: Declaration of Commencements.pdf29 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PIRANGUT RERA 1.pdf29 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold and sold inventari rera letter (2).pdf29 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5_compressed.pdf29 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf23 Feb 2023
CERSAI detailsFile: Cersai Declaration.pdf1 Jul 2022
CERSAI detailsFile: Marathi Bandhkam Vyavsaik Association Reg Certificate.pdf22 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 FY 2017-18.pdf19 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 2018 19.pdf19 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019 20.pdf19 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020 21.pdf19 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2 A 2019 20.pdf17 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2 A 2020 21.pdf17 Jun 2022
Disclosure of sold/ booked inventoryFile: Sold Inventory B Wing.pdf17 Jun 2022
Declaration about Commencement CertificateFile: Commencemnt Certificate.pdf10 Jun 2022
Details of encumbrancesFile: Encumbrance.pdf1 Jun 2018
Declaration in FORM BFile: From B pdf New.pdf1 Jun 2018
Layout approvalFile: Blue Print 1.pdf26 May 2018
Building plan approvalFile: Blue Print 2.pdf26 May 2018
Building plan approvalFile: Blue Print 3.pdf26 May 2018
PAN CardFile: chitraban pan card pdf.pdf26 May 2018
Copy of the legal title reportFile: chaitraban sarch pdf.pdf26 May 2018
Details of encumbrancesFile: ENCUMBRANCE PDF.pdf26 May 2018
Copy of Layout Approval (in case of layout)File: Blue Print 1.pdf26 May 2018
Building Plan Approval (IOD)File: Blue Print 2.pdf26 May 2018
Building Plan Approval (IOD)File: Blue Print 3.pdf26 May 2018
Commencement Certificates / NA Order for plotted developmentFile: PMRDA PARAVANGI PATRA.pdf26 May 2018
Declaration in FORM BFile: Form B2 New Pdf.pdf26 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: chatraban architects pdf.pdf26 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: chaitraban engineers pdf 1.pdf26 May 2018
Certificates of CA (Form 3)File: chaitraban CA pdf.pdf26 May 2018
Proforma of Allotment letterFile: Chaitraban_Sample Draft.pdf26 May 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Partnarship Deed Part 1.pdf26 May 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Partnarship Deed Part 2.pdf26 May 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Partnarsheep Deed.pdf26 May 2018
OtherFile: NA Order Pdf.pdf26 May 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 25 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CHAITRABAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHAIRAVNATH NAGAR13,700+ in Pune

Builder: RELIVE CONSTRUCTION

RELIVE CONSTRUCTION has 1 registration on MahaRERA, including CHAITRABAN RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that CHAITRABAN RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CHAITRABAN RESIDENCY is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHAITRABAN RESIDENCY?

The registered promoter entity is RELIVE CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHAITRABAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHAITRABAN RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHAITRABAN RESIDENCY?

The professionals named in the filing: Architect: JAIDEEP SUNIL DESHPANDE; Engineer: SATISH GHANEKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHAITRABAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHAITRABAN RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHAITRABAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.