Home / Browse projects / Amravati, Maharashtra / CENTRAL VISTA
CENTRAL VISTA
RG-MH-89140 · RERA P50300051971 · Last updated on MahaRERA portal: 27 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Amravati registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CENTRAL VISTA is a Commercial project by SHRI GOVINDA DEVELOPERS in Amravati, Maharashtra, registered with MahaRERA as P50300051971 on 13 Jul 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date.
At a glance
Project
- NameCENTRAL VISTA
- TypeCommercial
- Location
- NEAR G M AGRAWAL PETROL PUMP
- IRWIN SQUARE
- Amravati (M Corp.)
- Amravati
- 444601
- Pincode444601
- RERA no.P50300051971
- ReraGenie IDRG-MH-89140
Builder
- NameSHRI GOVINDA DEVELOPERS
- Entity typePartnership
- PartnersDEEPAK RAMESHLAL GODWANI, VIJAY NANAKRAM TALDA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on13 Jul 2023
- Promised completion31 Mar 2026
- Revised completionNone
- Buildings1 building record
- Documents filed104 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CENTRAL VISTA | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.
CENTRAL VISTA: 46% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 27 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed106
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | LOKESH KADU |
| Engineer | PANKAJ BAJAJ |
| Chartered Accountant | CA MANISH KHUSHLANI |
| Chartered Accountant | CA DEEPAK ZAMBANI GAD & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHRI GOVINDA DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 May 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed104
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Central Vista_Arc Cert_Form 1_Dec 25.pdf | 27 Feb 2026 |
| Form 2File: Central Vista_Eng Cert_Form 2_Dec 25.pdf | 27 Feb 2026 |
| Form 3File: Central Vista_CA Cert_Form 3_Dec 25_compressed.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Central Vista_Stock Sold Unsold Dec 25.pdf | 27 Feb 2026 |
| Form 1File: Central Vista_Arc Cert_Form 1_Sep 25.pdf | 20 Nov 2025 |
| Form 2File: Central Vista_Eng Cert_Form 2_Sep 25.pdf | 20 Nov 2025 |
| Form 3File: Central Vista_CA Cert_Form 3_Sep 25.pdf | 20 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Central Vista_Stock Sold Unsold Sep 25.pdf | 20 Nov 2025 |
| Form 1File: Central Vista_Arc Cert_Form 1_Jun 25.pdf | 23 Aug 2025 |
| Form 2File: Central Vista_Eng Cert_Form 2_Jun 25.pdf | 23 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Central Vista_Stock Sold Unsold Jun 25.pdf | 23 Aug 2025 |
| Form 3File: Central Vista_CA Cert_Form 3_Jun 25_compressed.pdf | 23 Aug 2025 |
| Form 1File: Arc Cert_Form 1_CV.pdf | 5 Aug 2025 |
| Form 2File: Engineer Cert Form 2_CV.pdf | 5 Aug 2025 |
| Form 3File: Form 3_Central Vista_Q2_FY 23-24.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: CV_Sold Unsold.pdf | 5 Aug 2025 |
| Form 1File: Central Vista_Form 1 ARC_Q3.pdf | 5 Aug 2025 |
| Form 2File: Central Vista_Form 2 ENG_Q3.pdf | 5 Aug 2025 |
| Form 3File: Central Vista_Form 3 CA_Q3.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Central Vista_Inventory Sold Unsold_Q3.pdf | 5 Aug 2025 |
| Form 1File: CENTRAL VISTA ARC CERTIFICATE_Form 1 Q4 23-24.pdf | 5 Aug 2025 |
| Form 2File: CENTRAL VISTA ENGINEER CERTIFICATEForm 2 Q4 23-24.pdf | 5 Aug 2025 |
| Form 3File: CENTRAL VISTA CA CERTFICATE_Form 3 Q4 23-24.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q4_23-24.pdf | 5 Aug 2025 |
| Form 1File: Central_Form 1_300624.pdf | 5 Aug 2025 |
| Form 2File: Central_Form 2_300624.pdf | 5 Aug 2025 |
| Form 3File: Central_Form 3_300624.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Central_Sold_300624.pdf | 5 Aug 2025 |
| Form 1File: CENTRAL VISTA_FORM 1_ Q2 24-25.pdf | 5 Aug 2025 |
| Form 2File: CENTRAL VISTA_FORM 2_ Q2 24-25.pdf | 5 Aug 2025 |
| Form 3File: CENTRAL VISTA_FORM 3_ Q2 24-25.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: CENTRAL VISTA_SOLD_ Q2 24-25.pdf | 5 Aug 2025 |
| Form 1File: GOVINDA DEVLOPERS ARC CERTIFICATEForm 1 Q3 24-25.pdf | 5 Aug 2025 |
| Form 2File: GOVINDA DEVLOPERS ENG CERTIFICATEForm 1 Q3 24-25.pdf | 5 Aug 2025 |
| Form 3File: GOVINDA DEVLOPERS CA CERTFICATE_Form 3 Q3 24-25.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q3_24-25.pdf | 5 Aug 2025 |
| Form 1File: CENTRAL VISTA ARC CERTIFICATEForm 1 Q4 24-25.pdf | 5 Aug 2025 |
| Form 2File: CENTRAL VISTA ENG CERTIFICATEForm 1 Q4 24-25.pdf | 5 Aug 2025 |
| Form 3File: CENTRAL VISTA CA CERTFICATE_Form 3 Q4 24-25.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q4_24-25.pdf | 5 Aug 2025 |
| OthersFile: CENTRAL VISTA Quality Assurance.pdf | 5 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CENTRAL VISTA ARC CERTIFICATEForm 1 Q4 24-25.pdf | 26 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CENTRAL VISTA CA CERTFICATE_Form 3 Q4 24-25.pdf | 26 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CENTRAL VISTA ENG CERTIFICATEForm 1 Q4 24-25.pdf | 26 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q4_24-25.pdf | 26 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: CENTRAL VISTA Quality Assurance.pdf | 26 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GOVINDA DEVLOPERS ARC CERTIFICATEForm 1 Q3 24-25.pdf | 18 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GOVINDA DEVLOPERS CA CERTFICATE_Form 3 Q3 24-25.pdf | 18 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GOVINDA DEVLOPERS ENG CERTIFICATEForm 1 Q3 24-25.pdf | 18 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q3_24-25.pdf | 18 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Central Vista 310324.pdf | 14 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CENTRAL VISTA_FORM 1_ Q2 24-25.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CENTRAL VISTA_FORM 3_ Q2 24-25.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CENTRAL VISTA_FORM 2_ Q2 24-25.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: CENTRAL VISTA_SOLD_ Q2 24-25.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Central_Form 1_300624.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Central_Form 3_300624.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GOVINDA DEVLOPERS ARC CERTIFICATEForm 1 Q1 24-25.pdf | 14 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GOVINDA DEVLOPERS ENGINEER CERTIFICATEForm 2 Q1 24-25.pdf | 14 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q1_24-25.pdf | 14 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GOVINDA DEVLOPERS CA CERTFICATE_Form 3 Q1 24-25.pdf | 14 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CENTRAL VISTA ARC CERTIFICATE_Form 1 Q4 23-24.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CENTRAL VISTA ENGINEER CERTIFICATEForm 2 Q4 23-24.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: CENTRAL VISTA SOLD UNSOLD INVENTORY _Q4_23-24.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CENTRAL VISTA CA CERTFICATE_Form 3 Q4 23-24.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Central Vista_Form 1 ARC_Q3.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Central Vista_Form 2 ENG_Q3.pdf | 17 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Central Vista_Inventory Sold Unsold_Q3.pdf | 17 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Central Vista_Form 3 CA_Q3.pdf | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Form 1_CV.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Form 2_CV.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: CV_Sold Unsold.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Central Vista_Q2_FY 23-24.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA Certificate_130723.pdf | 6 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Kharidi_compressed_merged.pdf | 22 Jun 2023 |
| Other - LegalFile: Kharidi_compressed_merged.pdf | 22 Jun 2023 |
| Other - FinanceFile: Kharidi_compressed_merged.pdf | 22 Jun 2023 |
| Other - TechnicalFile: Kharidi_compressed_merged.pdf | 22 Jun 2023 |
| CERSAI detailsFile: Undertaking of No Cersai with Cersai.pdf | 15 Jun 2023 |
| Proforma of Agreement for saleFile: ATS.pdf | 15 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Amravati
Computed across the 450+ Amravati projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 104 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CENTRAL VISTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near IRWIN SQUARE450+ in Amravati
GOVINDA NAGARI
SHRI GOVINDA PROPERTIES
DCC Dreamz City Chambers
DREAMZ-CITY REAL ESTATE PVT LTD
DUBAI CITY
SKYLINE URBANSPACE LLP
Radha City
Ravi sahu, Rupesh sahu And Deepak sahu
Green Heights
Aksha Builder and Developers
UDAY NAGAR LAYOUT D
DEVENDRA RAMACHANDRA CHANDAK
See every Amravati project, with the district possession charts
Builder: SHRI GOVINDA DEVELOPERS
SHRI GOVINDA DEVELOPERS has 1 registration on MahaRERA, including CENTRAL VISTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Amravati district page.
Frequently asked questions
What does it mean that CENTRAL VISTA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if CENTRAL VISTA is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CENTRAL VISTA?
The registered promoter entity is SHRI GOVINDA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CENTRAL VISTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CENTRAL VISTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CENTRAL VISTA?
The professionals named in the filing: Architect: LOKESH KADU; Engineer: PANKAJ BAJAJ; Chartered Accountant: CA MANISH KHUSHLANI; Chartered Accountant: CA DEEPAK ZAMBANI GAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CENTRAL VISTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback