Registration lapsed No litigation declared Residential / Group Housing project

CASAROYALE

By FAIRMONT CONSTRUCTIONS PRIVATE LIMITED

RG-MH-29311 · RERA P51800031988 · Last updated on MahaRERA portal: 11 Oct 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

CASAROYALE is a Residential / Group Housing project by FAIRMONT CONSTRUCTIONS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031988 on 3 Dec 2021. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameCASAROYALE
  • TypeResidential / Group Housing
  • Location
    • J V P D SCHEME
    • JUHU
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800031988
  • ReraGenie IDRG-MH-29311

Builder

  • NameFAIRMONT CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorsABDUL RAZAK AHMED CHUNAWALA, AARIF ABDUL RAZAK CHUNAWALA, FAROOK ABDUL RAZAK CHUNAWALA, SAMEER ABDUL RAZAK CHUNAWALA
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredDec 2021First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Dec 2021
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CASAROYALENA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

CASAROYALE: 9% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area409 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1660.0
Proposed, not sanctioned1,230 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMORYA ESTATE ANDHERI LINK ROAD ANDHERI WEST MUMBAI 400053

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectELLORA PROJECT CONSULTANTS PRIVATE LIMITED
EngineerSAYED ZAKIR HUSSAIN
Chartered AccountantA R SODHA & CO
PartnerRole in project
FAIRMONT CONSTRUCTIONS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017733Dec 2023 → Dec 2024

Reason as filed by the promoterwe would like to bring to the kind attention of this Hon’ble authority, that the development work of said Project Casaroyale have been stalled/halted/ delayed due to mischievous slum dwellers and further SRA authority not granting approvals due to complaint of Earth (an NGO). Upon receipt of the SRA approvals, the construction work has again started and further we state that we have not even sold a single apartment in the project Casaroyale. Hence, we humbly place before this Hon’ble authority our request to grant us an extension of the RERA possession by a period of 1 (One) year. And we under

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Amended IOA CTS 10 17 04 2023.pdf11 Oct 2023
Building plan approvalFile: Amended plan CTS 10 1 17 04 2023.pdf11 Oct 2023
PAN CardFile: Faime Maker Pvt Ltd Pan Card.pdf11 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Amended IOA CTS 10 17 04 2023.pdf11 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Amended plan CTS 10 1 17 04 2023.pdf11 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: casaroyale CC upto 3rd floor.pdf11 Oct 2023
Declaration in FORM BFile: Form B casaroyale 29 09 2023.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casaroyale FY 2021 22.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casaroyale FY 2022 23.pdf11 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Casaroyale dt 23 08 2023.pdf11 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate FY 2021-22.pdf11 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate FY 2022-23.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 Engineer Certificate FY 2021-22.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate FY 2021-22.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate FY 2022-23.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory 29 09 2023.pdf11 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2023 casaroyale.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 casaroyale 2021 22.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Casaroyale 2022 23.pdf11 Oct 2023
Declaration about Commencement CertificateFile: Form D CTS 10A2.pdf23 Nov 2021
Building plan approvalFile: Casaroyal Plan 1.pdf1 Oct 2021
Building plan approvalFile: Casaroyal Plan 2.pdf1 Oct 2021
Building plan approvalFile: Casaroyal Plan 3.pdf1 Oct 2021
Copy of the legal title reportFile: Rera Title certificate Form A.pdf1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Casaroyal Plan 1.pdf1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Casaroyal Plan 2.pdf1 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Casaroyal Plan 3.pdf1 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: CC Juhu new.pdf1 Oct 2021
Layout approvalFile: Declaration for Layout.pdf29 Jan 2021
Details of encumbrancesFile: Index II DHFL.pdf29 Jan 2021
Copy of Layout Approval (in case of layout)File: Declaration for Layout.pdf29 Jan 2021
PAN CardFile: 2 PAN FCP Upload.pdf28 Jan 2021
Declaration in FORM BFile: Form B.pdf28 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Form 1 Casaroyale.pdf28 Jan 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form 2 Casaroyale.pdf28 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Juhu - Form 3.pdf28 Jan 2021
Proforma of Allotment letterFile: RERA Allotment Letter.pdf28 Jan 2021
Proforma of Allotment letterFile: RERA Agreement for Sale.pdf28 Jan 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
REYHAAN TOWERSAHAKAR BANDIVALI HILL ROAD OFF. S.V. ROAD JOGESHWARI WEST MUMBAI 400102100CompletedNov 2010Nov 2010

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CASAROYALE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JUHU6,700+ in Mumbai Suburban

2 kmCASAROYALECompleted 43Lapsed / revoked 13Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: FAIRMONT CONSTRUCTIONS PRIVATE LIMITED

FAIRMONT CONSTRUCTIONS PRIVATE LIMITED has 3 registrations on MahaRERA, including FAIRMONT MOKSH and CASAROYALE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that CASAROYALE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CASAROYALE is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CASAROYALE?

The registered promoter entity is FAIRMONT CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CASAROYALE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CASAROYALE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CASAROYALE?

The professionals named in the filing: Architect: ELLORA PROJECT CONSULTANTS PRIVATE LIMITED; Engineer: SAYED ZAKIR HUSSAIN; Chartered Accountant: A R SODHA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASAROYALE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASAROYALE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASAROYALE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.