Home / Browse projects / Mumbai Suburban, Maharashtra / CALLISSA

Registered Litigation declared Residential / Group Housing project

CALLISSA

By KARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED

RG-MH-25615 · RERA P51800008237 · Last updated on MahaRERA portal: 5 Mar 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 4 complaints at MahaRERA
  • Completion date moved by 72 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 72 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 50%
81 of 101Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

CALLISSA is a Residential / Group Housing project by KARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008237 on 18 Aug 2017. Possession is promised by 31 Dec 2029. The completion date has moved by 72 months from the original filing. 20 of the 101 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameCALLISSA
  • TypeResidential / Group Housing
  • Location
    • Jari Mari Road
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008237
  • ReraGenie IDRG-MH-25615

Builder

  • NameKARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorsHASMUKH DEVJI RAMBHIA, SUNIL KRISHNARAO KARVIR, VAIBHAV SUNIL KARVIR, MEGHA SUNIL KARVIR, BHAVESH RATILAL RAMBHIA
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed51 files

Current status

20%20 of 101 units booked
13.8%Work done, per cost certificate

Figures as on 5 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CALLISSANA27211010101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.

CALLISSA: 32% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed116

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots116
Closed/Covered95
Open Space21

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,198 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Nov 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI6103.79
Proposed, not sanctioned1,733 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDATTANI CHAMBERS S V ROAD MALAD WEST MUMBAI 400064
Estimated costRs 32.40 cr
Cost incurredRs 4.48 cr
Work done13.83%
BuildingWingEstimatedIncurred
CALLISSANARs 28.51 crRs 4.48 cr
-NARs 3.89 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANDEEP PANDURANG VICHARE
EngineerKIRITKUMAR H SHAH
EngineerParas Consultants
EngineerRavindra V Tannir
Chartered AccountantVaishali Jain & Co
Chartered AccountantS R Mulye & Co
PartnerRole in project
RAMBHIA PROPERTIES PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA12112518313Dec 2023 → Dec 2029

Reason as filed by the promoterWe, Karvir & Rambhia Properties Private Limited, Promoters of the above-mentioned project, hereby submit this explanatory note in support of our request for extension of the project completion timeline, and humbly request your kind consideration. 1. Grounds and Reasons for Delay The project progress has been impacted due to reasons beyond the control of the Promoter, as detailed below: • Construction Challenges: Initial phases of construction witnessed slower progress due to manpower shortages, logistical constraints, and material supply coordination challenges. • Prevailing Market Conditions:

Litigation declared1

CaseCourtStatus
85/2015HIGH COURTPENDING

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000194039Bela ValiaKarvir & Rambhia Properties Private Limited29/09/2020
CC006000000194054Messrs Valia Infracon Pvt LtdKarvir & Rambhia Properties Private Limited28/09/2020
CC006000000194088Hema ValiaKarvir & Rambhia Properties Pvt Ltd28/09/2020
CC12401112VENSTER DLIMAKARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED12/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 June 2025.pdf5 Mar 2026
Withdrawal Update Form 1File: Form 1 September 2025.pdf5 Mar 2026
Withdrawal Update Form 1File: Form 1 December 2025.pdf5 Mar 2026
Withdrawal Update Form 2File: Form 2 June 2025.pdf5 Mar 2026
Withdrawal Update Form 2File: Form 2 September 2025.pdf5 Mar 2026
Withdrawal Update Form 2File: Form 2 December 2025.pdf5 Mar 2026
Withdrawal Update Form 3File: Form 3 June 2025.pdf5 Mar 2026
Withdrawal Update Form 3File: Form 3 September 2025.pdf5 Mar 2026
Withdrawal Update Form 3File: Form 3 December 2025.pdf5 Mar 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 as on September 2025.pdf17 Dec 2025
Withdrawal Update Form 2File: Withdrawal Application Form2 as on September 2025.pdf17 Dec 2025
Withdrawal Update Form 3File: Withdrawal Application Form3 as on September 2025.pdf17 Dec 2025
Form 2A (FY 2017-2018)File: Form 2A for 17-18.pdf17 Dec 2025
Form 2A (FY 2018-2019)File: Form 2A for 18-19.pdf17 Dec 2025
Form 2A (FY 2019-2020)File: Form 2A for 19-20.pdf17 Dec 2025
Form 2A (FY 2020-2021)File: Form 2A for 20-21.pdf17 Dec 2025
Form 2A (FY 2021-2022)File: Form 2A for 21-22.pdf17 Dec 2025
Form 2A (FY 2022-2023)File: Form 2A for 22-23.pdf17 Dec 2025
Form 5 (FY 2017-2018)File: FORM 5 (CA Certificate) CALLISSA FY 2017-18.pdf5 Nov 2025
Form 5 (FY 2018-2019)File: FORM 5 (CA Certificate) CALLISSA FY 2018-19.pdf5 Nov 2025
Form 5 (FY 2019-2020)File: FORM 5 (CA Certificate) CALLISSA FY 2019-20.pdf5 Nov 2025
Form 5 (FY 2020-2021)File: FORM 5 (CA Certificate) CALLISSA FY 2020-21.pdf5 Nov 2025
Form 5 (FY 2021-2022)File: FORM 5 (CA Certificate) CALLISSA FY 2021-22.pdf5 Nov 2025
Form 5 (FY 2022-2023)File: FORM 5 (CA Certificate) CALLISSA FY 2022-23.pdf5 Nov 2025
Form 5 (FY 2023-2024)File: FORM 5 (CA Certificate) CALLISSA FY 2023-24.pdf5 Nov 2025
Form 2A (FY 2023-2024)File: Form-2A_23-24.pdf4 Nov 2025
Layout approvalFile: Layout Plan.pdf31 Jul 2017
Building plan approvalFile: IOD (1).pdf31 Jul 2017
Building plan approvalFile: IOD (2).pdf31 Jul 2017
PAN CardFile: PAN Card.pdf31 Jul 2017
Copy of the legal title reportFile: 1493.pdf31 Jul 2017
Copy of the legal title reportFile: 1494.pdf31 Jul 2017
Copy of the legal title reportFile: 1495.pdf31 Jul 2017
Copy of the legal title reportFile: 1501.pdf31 Jul 2017
Copy of the legal title reportFile: 1504.pdf31 Jul 2017
Copy of the legal title reportFile: 1505.pdf31 Jul 2017
Copy of the legal title reportFile: 1507.pdf31 Jul 2017
Copy of the legal title reportFile: 1508.pdf31 Jul 2017
Copy of the legal title reportFile: 1509.pdf31 Jul 2017
Copy of the legal title reportFile: 1515.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD (1).pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD (2).pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf31 Jul 2017
Declaration in FORM BFile: Form B Callissa.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Callissa.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Callissa.pdf31 Jul 2017
Certificates of CA (Form 3)File: Architects Certificate Callissa.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Annexure Callissa.pdf31 Jul 2017
Proforma of Allotment letterFile: Proforma Allotment Letter.pdf31 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
LOTUSP51800011190malad malvani village, Mumbai Suburban60Aug 2017OngoingOct 2020Registered original: Dec 2018Not delivered

How this compares with Mumbai Suburban

20%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CALLISSA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmCALLISSACompleted 32Lapsed / revoked 19Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: KARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED

KARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED has 1 registration on MahaRERA, including CALLISSA. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if CALLISSA is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CALLISSA?

The registered promoter entity is KARVIR & RAMBHIA PROPERTIES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CALLISSA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CALLISSA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CALLISSA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CALLISSA?

The professionals named in the filing: Architect: SANDEEP PANDURANG VICHARE; Engineer: KIRITKUMAR H SHAH; Engineer: Paras Consultants; Engineer: Ravindra V Tannir; Chartered Accountant: Vaishali Jain & Co; Chartered Accountant: S R Mulye & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CALLISSA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CALLISSA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CALLISSA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.