Home / Browse projects / Mumbai Suburban, Maharashtra / LOTUS

Completed No litigation declared Residential / Group Housing project

LOTUS

By RAJESHWAR LAND DEVELOPERS PRIVATE LIMITED

RG-MH-20890 · RERA P51800011190 · Last updated on MahaRERA portal: 21 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 96 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Installation of Lifts, 90%
21 of 60Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 109 documents Report an error

LOTUS is a Residential / Group Housing project by RAJESHWAR LAND DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011190 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 96 months from the original filing. 39 of the 60 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameLOTUS
  • TypeResidential / Group Housing
  • Location
    • jari mari road
    • malad malvani village
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011190
  • ReraGenie IDRG-MH-20890

Builder

  • NameRAJESHWAR LAND DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • GSTIN27AAECR0492A1ZP
  • Managing DirectorsSUNIL KRISHNARAO KARVIR, SHIVRAM GOPAL DALVI, BHAVESH RATILAL RAMBHIA

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed109 files

Current status

65%39 of 60 units booked
89.1%Work done, per cost certificate

Figures as on 21 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LOTUSNA232160060

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

LOTUS: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes0%

Parking filed91

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots91
Closed/Covered31
Open Space60

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,373 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 May 2026

Approvals and building plan

Sanctioning authoritybmc
Permissible FSI5788.73
Proposed, not sanctioned5,687 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 SHREE SAGVAN CHS LTD RTO LANE FOUR BUNGALOWS ANDHERI WEST MUMBAI 400053
Estimated costRs 26.00 cr
Cost incurredRs 23.16 cr
Work done89.08%
BuildingWingEstimatedIncurred
LOTUSNARs 21.00 crRs 19.71 cr
-NARs 5.00 crRs 3.45 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANDDEP PANDURANG VICHARE
EngineerKIRITKUMAR H SHAH
EngineerSushant Sawant & Associates
Chartered AccountantS R Mulye & Co.
PartnerRole in project
RAJESHWAR LAND DEVELOPERS PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001447Dec 2018 → Apr 2020

Reason as filed by the promoterThere is an encroachment on the access road to the building. The Hon’ble High Court has directed to the Mumbai Municipal Corporation office to remove encroachments on the access road to the building.

EA16052620993Dec 2018 → Dec 2026

Reason as filed by the promoterDear Sir/Ma’am, We, Rajeshwar Land Developers Private Limited, hereby declare the following with respect to the project “Lotus” bearing registration number P51800011190 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the all the buildings. Currently, we are undertaking the Pending finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance wo

Litigation declared2

CaseCourtStatus
576/2016HIGH COURTPENDING
2407/2016HIGH COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed109

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf21 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf21 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf21 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Engineer s Certificate.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Engineer s Certificate.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Engineer s Certificate.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Engineer s Certificate.pdf21 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf21 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf21 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf21 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf21 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2017.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2017.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2018.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2018.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2020.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2018.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2018.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2019.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2019.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2019.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2019.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2020.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2020.pdf16 May 2026
Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Form 3File: Form 3 CA Certificate.pdf16 May 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2020.pdf16 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf16 May 2026
Withdrawal Update Form 2File: Form 2 Engineer s Certificate.pdf16 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf16 May 2026
Form 2A (FY 2017-2018)File: FORM 2A 17-18.pdf16 May 2026
Form 2A (FY 2018-2019)File: FORM 2A 18-19.pdf16 May 2026
Form 2A (FY 2019-2020)File: FORM 2A 19-20.pdf16 May 2026
Form 2A (FY 2020-2021)File: FORM 2A 20-21.pdf16 May 2026
Form 5 (FY 2017-2018)File: Form 5 17-18.pdf16 May 2026
Form 5 (FY 2018-2019)File: Form 5 18-19.pdf16 May 2026
Form 5 (FY 2019-2020)File: Form 5 19-20.pdf16 May 2026
Form 5 (FY 2020-2021)File: Form 5 20-21.pdf16 May 2026
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf15 Feb 2021

How this compares with Mumbai Suburban

65%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 96 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LOTUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near malad malvani village6,700+ in Mumbai Suburban

2 kmLOTUSCompleted 31Lapsed / revoked 19Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: RAJESHWAR LAND DEVELOPERS PRIVATE LIMITED

RAJESHWAR LAND DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including LOTUS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if LOTUS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LOTUS?

The registered promoter entity is RAJESHWAR LAND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its GSTIN 27AAECR0492A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LOTUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LOTUS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LOTUS?

The professionals named in the filing: Architect: SANDDEP PANDURANG VICHARE; Engineer: KIRITKUMAR H SHAH; Engineer: Sushant Sawant & Associates; Chartered Accountant: S R Mulye & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LOTUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LOTUS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LOTUS to a free account