Registered Litigation declared Others project

CALISTA

By BLUESCAPE INFRA

RG-MH-04519 · RERA P52000022210 · Last updated on MahaRERA portal: 17 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 11 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 11 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
40 of 129Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 128 documents Report an error

CALISTA is a Others project by BLUESCAPE INFRA in Raigarh, Maharashtra, registered with MahaRERA as P52000022210 on 5 Sep 2019. Possession is promised by 15 Nov 2026. The completion date has moved by 11 months from the original filing. 89 of the 129 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCALISTA
  • TypeOthers
  • Location
    • PUSHPAK NEW
    • SECTOR 3
    • Navi Mumbai Panvel Rigardh (CT)
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000022210
  • ReraGenie IDRG-MH-04519

Builder

  • NameBLUESCAPE INFRA
  • Entity typePartnership
  • PartnersCHANDRAKANT DEVJI CHEDDA, KHETSHI GANGJI CHAMARIYA, DEVJI BECHARA CHOUDHARY, VIJAY GANESH PATEL
  • Authorized SignatoryVIPUL DHIRAJ VERAT
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2019First promiseDec 2025Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Sep 2019
  • Promised completion15 Nov 2026
  • Revised completionRevised to 15 Nov 2026 (originally 30 Dec 2025)
  • Buildings1 building record
  • Documents filed128 files

Current status

69%89 of 129 units booked
88.6%Work done, per cost certificate

Figures as on 17 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CALISTANA15141236129

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

CALISTA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed143

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots143
Closed/Covered143

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,159 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Oct 2024

Approvals and building plan

Sanctioning authorityCIDCO LTD
Permissible FSI8747.36
Proposed, not sanctioned8,715 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVAIBHAV CHSL, PLOT NO 28, SECTOR 11, KHARGHAR, NAVI MUMBAI- 410210
Estimated costRs 40.75 cr
Cost incurredRs 36.11 cr
Work done88.61%
BuildingWingEstimatedIncurred
CALISTANARs 40.75 crRs 36.11 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL
EngineerPUSHPENDRA VISHWAKARMA
EngineerDHANAJI BHIMARAV CHAVAN
Chartered AccountantCA JYOTI GAJRA
Chartered AccountantH. M. SHAH & ASSOCIATES
Chartered AccountantP. R. VORA & ASSOCIATES
PartnerRole in project
BLUESCAPE INFRA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19122518767Dec 2025 → Jun 2026

Reason as filed by the promoterThe construction of the aforesaid project has been carried out in accordance with the sanctioned plans. However, the promoter has applied for issuance of further amended Commencement Certificate (CC) and approval of amended building plans from the concerned Planning Authority. Despite submission of all requisite applications, documents, and compliances, the issuance of the further amended Commencement Certificate and sanctioned amended plans has been delayed due to administrative and procedural reasons at the level of the Planning Authority, which are beyond the control of the promoter. In vie

EA09072621710Dec 2025 → Nov 2026

Reason as filed by the promoterWe, Bluescape Infra, hereby declare the following with respect to the project Calista bearing registration number P52000022210 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 07/04/2026 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, Permissible Built-up Area,

Litigation declared2

CaseCourtStatus
96/2017/2017PANVEL DISTRICT COURTNO LITIGATION
WP/9293/2021/2019High Court of BombayOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501219Pradeep AgarwalKrishan Builders and Developers12/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Nov 2026

Documents filed128

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - March 2026.pdf17 Aug 2026
Withdrawal Update Form 2File: Form 2 - March 2026.pdf17 Aug 2026
Withdrawal Update Form 3File: Form 3 - May 2026.pdf17 Aug 2026
Building plan approvalFile: OC Plan 1_highlighted.pdf24 Jul 2026
Building plan approvalFile: OC Plan 2_highlighted.pdf24 Jul 2026
Building plan approvalFile: OC Plan 3_highlighted.pdf24 Jul 2026
Building plan approvalFile: OC Plan 4.pdf24 Jul 2026
Withdrawal Update Form 1File: Form 1 - March 2026.pdf9 Jul 2026
Withdrawal Update Form 1File: Form 1 - March 2026.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2 - March 2026.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2 - March 2026.pdf9 Jul 2026
Withdrawal Update Form 3File: Form 3 - May 2026.pdf9 Jul 2026
Withdrawal Update Form 3File: Form 3 - May 2026.pdf9 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A - 2025-26.pdf9 Jul 2026
Form 5 (FY 2023-2024)File: Bluescape infra FY 23-24.pdf19 Dec 2025
Form 5 (FY 2024-2025)File: Bluescape infra FY 24-25.pdf19 Dec 2025
Form 1File: FORM 1.pdf12 Dec 2025
Form 2File: Form-2.pdf12 Dec 2025
Form 3File: Form 3 with sign.pdf12 Dec 2025
Disclosure of Sold and Booked InventoryFile: inventory sold details.pdf12 Dec 2025
Form 1File: FORM 1.pdf12 Dec 2025
Form 2File: Form-2.pdf12 Dec 2025
Form 3File: Form 3 final.pdf12 Dec 2025
Disclosure of Sold and Booked InventoryFile: inventory sold details.pdf12 Dec 2025
Withdrawal Update Form 1File: FORM1 Q2 25-26.pdf3 Dec 2025
Withdrawal Update Form 2File: FORM2 Q2 25-26.pdf3 Dec 2025
Withdrawal Update Form 3File: FORM3 25-26.pdf3 Dec 2025
Withdrawal Update Form 1File: Final FORM 1.pdf19 Aug 2025
Withdrawal Update Form 2File: Final FORM 2.pdf19 Aug 2025
Withdrawal Update Form 3File: final FORM 3.pdf19 Aug 2025
Withdrawal Update Form 1File: Final FORM 1.pdf28 Jul 2025
Withdrawal Update Form 2File: Final FORM 2.pdf28 Jul 2025
Withdrawal Update Form 3File: final FORM 3.pdf28 Jul 2025
Withdrawal Update Form 1File: Final FORM 1.pdf25 Jul 2025
Withdrawal Update Form 2File: Final FORM 2.pdf25 Jul 2025
Withdrawal Update Form 3File: final FORM 3.pdf25 Jul 2025
Form 2A (FY 2020-2021)File: FORM 2A (20-21).pdf24 Jun 2025
Form 2A (FY 2019-2020)File: FORM 2A (19-20).pdf24 Jun 2025
Form 2A (FY 2021-2022)File: FORM 2A (21-22).pdf24 Jun 2025
Form 2A (FY 2022-2023)File: FORM 2A (22-23).pdf24 Jun 2025
Form 2A (FY 2023-2024)File: FORM 2A (23-24).pdf24 Jun 2025
Form 2A (FY 2024-2025)File: FORM 2A (24-25).pdf24 Jun 2025
Form 1File: Form 1.pdf18 Jun 2025
Form 2File: Form 2.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: invenotry sold june 24.pdf18 Jun 2025
Form 3File: FORM 3 with sign.pdf18 Jun 2025
Form 1File: FORM 1_.pdf18 Jun 2025
Form 2File: FORM 2.pdf18 Jun 2025
Form 3File: FORM 3.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: invenotry sold sep 24.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: invenotry sold dec 24.pdf18 Jun 2025
Form 1File: Final FORM 1.pdf18 Jun 2025
Form 2File: FORM 2.pdf18 Jun 2025
Form 3File: Final FORM 3.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: invenotry sold march 25.pdf18 Jun 2025
Form 2File: FORM 2.pdf18 Jun 2025
Form 1File: Final FORM 1.pdf18 Jun 2025
Form 3File: Final FORM 3.pdf18 Jun 2025
Form 5 (FY 2021-2022)File: Form 5 New.pdf24 May 2025
Form 5 (FY 2022-2023)File: Form 5 with Sign.pdf24 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final FORM 1.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final FORM 3.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final FORM 1.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final FORM 3.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_.pdf26 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf26 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 with sign.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: Inventory Sold Letter-March 24.pdf1 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_signed_11zon.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: final form 2.pdf10 Apr 2024
Disclosure of sold/ booked inventoryFile: inventory sold details.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with sign.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf19 Jan 2024

How this compares with Raigarh

69%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 11 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CALISTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SECTOR 35,900+ in Raigarh

Builder: BLUESCAPE INFRA

BLUESCAPE INFRA has 1 registration on MahaRERA, including CALISTA. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if CALISTA is delayed beyond 15 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CALISTA?

The registered promoter entity is BLUESCAPE INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CALISTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CALISTA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CALISTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CALISTA?

The professionals named in the filing: Architect: ATUL PATEL; Engineer: PUSHPENDRA VISHWAKARMA; Engineer: DHANAJI BHIMARAV CHAVAN; Chartered Accountant: CA JYOTI GAJRA; Chartered Accountant: H. M. SHAH & ASSOCIATES; Chartered Accountant: P. R. VORA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CALISTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CALISTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CALISTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.