ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West

Registration lapsed No litigation declared Residential / Group Housing project

Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West

By SKYLINE CONSTRUCTION CO.

RG-MH-11867 · RERA P51800008028 · Last updated on MahaRERA portal: 11 Jun 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date
  • 11 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
4 of 11Construction stages donefurthest along: Podiums (if any), 75%
11Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West is a Residential / Group Housing project by SKYLINE CONSTRUCTION CO. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008028 on 18 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. 11 complaints are on record with the regulator.

At a glance

Project

  • NameBuilding on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West
  • TypeResidential / Group Housing
  • Location
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008028
  • ReraGenie IDRG-MH-11867

Builder

  • NameSKYLINE CONSTRUCTION CO.
  • Entity typeOthers
  • Named personAnubhav Anilkumar Aggarwal
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

82 months past promisethis monthRegisteredAug 2017PromisedDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RNA ImperialNA430000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Jun 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 75%.

RNA Imperial: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)75%
Plinth100%
Stilt Floor100%
Slabs of Super Structure54%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises13%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 11 Jun 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Covered Parking only RCCYes75%

Parking filed615

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots615
Closed/Covered582
Open Space33

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,228 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI32000.0
Proposed, not sanctioned15,483 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBandra West Mumbai 400050

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB S Barot L S
EngineerHM Raje Structural Consultants Pvt. Ltd
PartnerRole in project
SKYLINE CONSTRUCTION CO.-

Litigation declared25

CaseCourtStatus
COMSL/201/2016/2016High Court at BombayFor Ad interim relief
COMSL/202/2016/2016High Court at BombayFor Ad interim relief
COMSL/124/2016/2016High Court at Bombayfor ad interim relief
COMSL/152/2016/2016High Court at BombayFor Ad interim relief
COMSL/151/2016/2016High Court at BombayFor Ad interim relief
COMSL/126/2016/2016High Court at BombayFor Ad interim relief
COMSL/142/2016/2016High Court at BombayFor Ad interim relief
COMSL/125/2016/2016High Court at BombayFor Ad interim relief
COMSL/123/2016/2016High Court at BombayFor Ad interim relief
COMSL/134/2016/2016High Court at BombayFor Ad interim relief
COMSL/132/2016/2016High Court at BombayFor Ad interim relief
COMSL/140/2016/2016High Court at BombayFor Ad interim relief
COMSL/321/2017/2017High Court at BombayFor Ad interim relief
COMSL/80/2017/2017High Court at BombayFor Ad interim relief
CC006000000012179 of 2017 Tejas Shah Vs Skyline/2017MahaRERA AuthorityDisposed off
CC006000000001808 of 2017 Usha Ramnani Vs Skyline/2017MahaRERA AuthorityDisposed Off
CC006000000001490 of 2017 of Darshan Shah Vs Skyline Construction Co/2017MahaRERA AuthorityDisposed Off
CC006000000001934 of 2017 Uday Ghare Vs Skyline Construction Co/2017MahaRERA authorityDisposed Off
CC no3245 of 2017 Prachi Ameya Bhobe and Anrs v/s M/s Skyline Construction/2017NCDRCsine Die
CC NO 006000000023949 OF 2018 Manish Goel v/s Skyline Construction Co/2018MahaRERA AuthorityNew Matter
COMSL/122/2016 Anusuya Purohit and Anrs Vs Skyline Construction Co /2016High Court at BombayWe filed Consent Terms on Four May Eighteen
Securitization Case No 244/2017 Bank of Baroda V/s Ms Skyline Construction Co and Anr/2017CMM BombayDisposed off allowing the Applicant bank to take Physical possession of the Secured Assets
Notice of Motion L No 2295 of 2018 in COMSL/206/2016 and others/2016High Court of BombayPre Admission
Rekha Jain NOML 2295/2018 in COMSL/206/2016/2016High Court of BombayPre Admission
Jignesh Manhar Rathod and Anr in NOML 85/2016 in COMSL 126/2016/2016High Court of BombayPending

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC006000000023949Manish GoelAnubhav Agarrwal09/04/2018
CC006000000001490DARSHAN SHAH & ANR.SKYLINE CONSTRUCTION CO.26/10/2017
CC006000000089693ACG ASSOCIATED CAPSULES PVT LTDRNA Corporation11/06/2019
CC006000000089698ACG ASSOCIATED CAPSULES PVT. LTD.RNA Corporation11/06/2019
CC006000000089700PAM PHARMACEUTICAL AND ALLIED MACHINERY CO. PVT. LTD.RNA Corporation11/06/2019
CC006000000089701ACG PHARMAPACK PVT. LTD.RNA Corporation11/06/2019
CC006000000001934UDAY GHARE & ANRSKYLINE CONSTRUCTION CO.16/11/2017
CC006000000001808Usha Ramnani & AnrSKYLINE CONSTRUCTION COMPANY15/11/2017
CC006000000012179TEJAS SHAH AND ANR.SKYLINE CONSTRUCTION COMPANY28/11/2017
CC006000000089623ARVIND RAO & OTHERSSKYLINE CONSTRUCTION CO10/06/2019
CC006000000100301RNA IMPERIAL RESIDENTS WELFARE ASSOCIATIONSKYLINE CONSTRUCTION CO.31/07/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Imperial.pdf11 Jun 2019
Proforma of Allotment letterFile: AFS-Imperial-1-8-2018 version A0.pdf1 Aug 2018
Copy of the legal title reportFile: Project Imperial - One Page Title Report.pdf26 Apr 2018
Declaration in FORM BFile: Form B Imperial 22 Sept 2017.pdf22 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Imperial A Certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate for Imperial.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3 Imperial.pdf31 Jul 2017
OtherFile: Imperial note.pdf31 Jul 2017
Details of encumbrancesFile: Imperial.pdf30 Jul 2017
Details of encumbrancesFile: Imperial Index 2.pdf30 Jul 2017
Declaration in FORM BFile: Form B and DA of Imperial.pdf30 Jul 2017
Proforma of Allotment letterFile: Imperial.pdf30 Jul 2017
Layout approvalFile: Kandivali Layout Plan Document 29 Mar 2007 pg 11 to 20.pdf26 Jul 2017
Layout approvalFile: Kandivali Layout Plan Document 29 Mar 2007 pg 21 to 34.pdf26 Jul 2017
Layout approvalFile: kandivali layout approval plan 29 march 2007.pdf26 Jul 2017
Layout approvalFile: kandivali layout approval plan 29032007.pdf26 Jul 2017
Layout approvalFile: Kandivali Layout Plan Document 29 Mar 2007 Pg 1 to 10.pdf26 Jul 2017
Building plan approvalFile: 3 Lower Gr Fl Plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 5 1st Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 6 2nd Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 7 3rd Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 8 4th Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 10 Refuge Fl Plan for Wing G and F 3 and 10 Fl dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 11 Wing G 17th Fl Plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 12 Terrace Fl Plan Wing G and F dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 9 Typical Fl plan for Wing G and F1 to 2 4 to 9 11 to 16 Fl dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 2 Plot Area Calculation dt 08 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 4 Ground Fl Plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: 1 Block Plan dt 8 Oct 2014.pdf26 Jul 2017
Building plan approvalFile: Imperial Amended IOA dt 8 Oct 2014.pdf26 Jul 2017
PAN CardFile: PAN Anubhav Aggarwal.pdf26 Jul 2017
Copy of the legal title reportFile: Imperial Title Report pg 1 to 9.pdf26 Jul 2017
Copy of the legal title reportFile: Imperial Title Report 10 to 17.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Kandivali Layout Plan Document 29 Mar 2007 Pg 1 to 10.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Kandivali Layout Plan Document 29 Mar 2007 pg 11 to 20.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Kandivali Layout Plan Document 29 Mar 2007 pg 21 to 34.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: kandivali layout approval plan 29 march 2007.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: kandivali layout approval plan 29032007.pdf26 Jul 2017
Building Plan Approval (IOD)File: Imperial Amended IOA dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 1 Block Plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 2 Plot Area Calculation dt 08 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 3 Lower Gr Fl Plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 4 Ground Fl Plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 5 1st Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 6 2nd Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 7 3rd Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 8 4th Podium Fl plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 9 Typical Fl plan for Wing G and F1 to 2 4 to 9 11 to 16 Fl dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 10 Refuge Fl Plan for Wing G and F 3 and 10 Fl dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 11 Wing G 17th Fl Plan dt 8 Oct 2014.pdf26 Jul 2017
Building Plan Approval (IOD)File: 12 Terrace Fl Plan Wing G and F dt 8 Oct 2014.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Imeprial CC dt 31 Oct 2014.pdf26 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Building on Sub Plot A CTS No 283 D pt 287 A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmBuilding on Sub Plot A CCompleted 112Lapsed / revoked 69Other 150Dot size: filed unitsN

Filed coordinates, straight-line distance. 331 registered projects within 2 km.

Builder: SKYLINE CONSTRUCTION CO.

SKYLINE CONSTRUCTION CO. has 2 registrations on MahaRERA, including Building on Sub plot - D, CTS No 101/B of village Goregaon and Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West?

The registered promoter entity is SKYLINE CONSTRUCTION CO., an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West?

The professionals named in the filing: Architect: B S Barot L S; Engineer: HM Raje Structural Consultants Pvt. Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Building on Sub Plot A CTS No 283 D pt 287 A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.