Home / Browse projects / Palghar, Maharashtra / BROOKLYN PARK PHASE IV

Registered No litigation declared Residential / Group Housing project

BROOKLYN PARK PHASE IV

By EKTA HOUSING PRIVATE LIMITED

RG-MH-09097 · RERA P99000000417 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • 36 complaints at MahaRERA
  • Completion date moved by 71 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 71 months from the original
10 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 95%
74 of 189Units unsoldnot recorded sold or booked
36Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

BROOKLYN PARK PHASE IV is a Residential / Group Housing project by EKTA HOUSING PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000000417 on 15 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 71 months from the original filing. 115 of the 189 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete. 36 complaints are on record with the regulator.

At a glance

Project

  • NameBROOKLYN PARK PHASE IV
  • TypeResidential / Group Housing
  • Location
    • Narangi Bypass Rd
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000000417
  • ReraGenie IDRG-MH-09097

Builder

  • NameEKTA HOUSING PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200MH1990PTC058279
  • GSTIN27AAACE2460K1ZP
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsVIVEK ASHOK MOHANANI, ASHOK GOBINDRAM MOHANANI
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredJul 2017First promiseJan 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Jan 2021)
  • Buildings2 building records
  • Documents filed100 files

Current status

61%115 of 189 units booked
66.3%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WINGNA141494094
C WINGNA1414831295

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

B WING65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C WING71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
B WING11
C WING11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area887 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Jun 2026

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNICIPAL CORPORATION
Permissible FSI8055.73
Proposed, not sanctioned8,056 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Unit No 001a, Hallmark Business Plaza , New Collector Office, Bandra East Mumbai Mahar
Estimated costRs 26.00 cr
Cost incurredRs 17.23 cr
Work done66.27%
BuildingWingEstimatedIncurred
B WINGNARs 12.63 crRs 7.44 cr
C WINGNARs 11.38 crRs 8.09 cr
-NARs 1.99 crRs 1.71 cr

Certifying professionals and partners11

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSamir Desai
ArchitectSAMEER DESAI
ArchitectAJAY WADE & ASSOCIATES
EngineerSACHIN S KARAWADE
EngineerAmit Parshuram Kamble
Chartered AccountantMANOJ CHATURVEDI & CO
Chartered AccountantBABULAL GUPTA & CO
Chartered AccountantV MANGAL AND COMPANY
Chartered AccountantVikas Mangal
Chartered AccountantManoj Chaturvedi
Chartered AccountantShivanandan N Katdare
PartnerRole in project
EKTA HOUSING PRIVATE LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000006168Jan 2021 → Jan 2022

Reason as filed by the promoterDUE TO SCARCITY OF AVAILABILITY OF THE RESOURCES.

EXT99000017569Jan 2021 → Dec 2024

Reason as filed by the promoterReply attached herewith.

EXT99000012699Jan 2021 → Jul 2023

Reason as filed by the promoterWe hereby apply for extension u/s 7(3) of the RERA for the registered project BROOKLYN PARK Phase IV bearing MahaRERA registration No.P99000000417 The structure is already complete however on account of defaults by the project proponent [ B & C ], the occupation certificate shall be applied for on [ B & C ]. The possession date as per RERA has already expired on 30.07.2022, and we are hereby applying u/s 7(3) for extension till 31.07.2023. As prescribed under circular No. 07/2019 dated 8th Feb, 2019 for the consent letters, we are giving details of consents as under. Total Units 2 wings B and

EA12092401796Jan 2021 → Dec 2026

Reason as filed by the promoterNon Compliance on the part of HDIL

Complaints filed with MahaRERA36

Case no.ComplainantRespondentFiled
CC006000000001053Santosh ValluryEkta Housing Pvt Ltd/Ekta Parksville Homes Pvt Ltd04/10/2017
CC006000000044071Meghna Rohit Khandelwal & Rohit Brijmohan KhandelwalEkta Housing Private Limited10/04/2018
CC006000000479888deepak upadhyayEKTA HOUSING PRIVATE LTD01/04/2024
CC006000000171927Surajkumar Rajendra Rai & AnotherEkta Housing Private Limited24/12/2019
CC006000000141195Ponneth Somashekharan NairEkta Housing Private Limited09/10/2019
CC006000000196407Prashant Karkera / Archana KarkeraEkta World20/03/2021
CC006000000198633Madhura Devendra RanadeEKTA HOUSING PVT LTD18/12/2021
CC006000000364642Madhura Devendra RanadeEKTA HOUSING PVT LTD11/03/2023
CC006000000199183SWAPNIL GOLAPKAREKTA HOUSING PRIVATE LIMITED THROUGH DIRECTOR VIVEK A.MOHNANI21/12/2021
CC006000000220911ASHWANI KUMAR PRAHLAD PATWAEkta Housing Pvt. Ltd.15/05/2022
CC006000000251848Kausalkumar Pralhad PatwaEkta Housing Private Limited11/07/2022
CC006000000303693Prathamesh Girish WaidandeEkta Housing Private Limited16/12/2022
CC006000000251619Santosh Rammohan ValluryEkta Housing Private Limited22/07/2022
CC006000000354390Vinay Shobhnath ShuklaEkta Housing Private Limited23/02/2023
CC006000000396994Yogesh Vijay ShindeEKTA WORLD20/07/2024
CC006000000364594Ramu Chellakan NadarVivek A. Hohanani03/03/2023
CC006000000395915KANCHAN JHAM/s. EKTA HOUSING PVT. LTD.26/05/2023
CC006000000397547Pushkar Pradepkumar LeleEkta Housing Private Limited29/09/2023
CC006000000397765SUHAIL FARUQUE SHAIKHEKTA HOUSING PRIVATE LIMITED22/10/2023
CC006000000398058RAJA MITRAEKTA HOUSING PVT LTD21/12/2023
CC12401138Krunal Umesh ParikhEKTA HOUSING PRIVATE LIMITED16/12/2024
CC12401115MAITHILI VINAYAK CHAVANEKTA HOUSING PRIVATE LIMITED13/12/2024
CC12500022Abhishek SharmaEKTA HOUSING PRIVATE LIMITED03/01/2025
CC12401258GEETA MANOHAR INGLESHWARBALAJI ENTERPRISES28/12/2024
CC12500137ROHINI SATISH KOTIANEKTA HOUSING PRIVATE LIMITED15/01/2025
CC12500396Yunus Munaf PatelEKTA HOUSING PRIVATE LIMITED06/02/2025
CC12500362SUSHANT SURESHBHAI RATHOREKTA HOUSING PRIVATE LIMITED03/02/2025
CC12500370PANKAJ DINESH SHARMAEKTA HOUSING PRIVATE LIMITED03/02/2025
CC12501361manish ramesh almalEKTA HOUSING PRIVATE LIMITED24/04/2025
CC12502214VIJAY KUMAR RAMKUMAR MISHRAEKTA HOUSING PRIVATE LIMITED03/07/2025
CC12502221VIJAY KUMAR RAMKUMAR MISHRAEKTA HOUSING PRIVATE LIMITED04/07/2025
CC12502416PINTU TEJBAHADUR SINGHEKTA HOUSING PRIVATE LIMITED16/07/2025
CC12502434PINTU TEJBAHADUR SINGHEKTA HOUSING PRIVATE LIMITED17/07/2025
CC12602541Tejas Girish DedhiaEKTA HOUSING PRIVATE LIMITED01/05/2026
CC12600858TASNIM TAJUDDIN KHANEKTA HOUSING PRIVATE LIMITED16/02/2026
CC12603339ARUN BADRIPRASAD UPADHYAYEKTA HOUSING PRIVATE LIMITED01/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: SIGNED FORM 1 BP P IV MARCH 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: SIGNED FORM 2 BP P IV MARCH 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: SIGNED FORM 3 BP P IV MARCH 2026.pdf20 Apr 2026
Withdrawal Update Form 1File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 30-09-2025.pdf21 Jan 2026
Withdrawal Update Form 1File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31-12-2025 NEW FORMAT.pdf21 Jan 2026
Withdrawal Update Form 2File: Form 2 Sep 2025.pdf21 Jan 2026
Withdrawal Update Form 2File: FORM 2 BROOKLYN PARK PHASE IV.pdf21 Jan 2026
Withdrawal Update Form 3File: Signed FORM 3 BP P IV HOUSING.pdf21 Jan 2026
Withdrawal Update Form 3File: Signed FORM 3 BP P IV HOUSING.pdf21 Jan 2026
Form 1File: EKTA BROOKLYN PHASE IV FORM 1 30-06-2025.pdf17 Jul 2025
Form 2File: FORM 2 EKTA BROOKLYN PARK PHASE 4.pdf17 Jul 2025
Form 3File: Signed FORM 3 BP P IV HOUSING 30_06_2025.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold & unsold BP phase 4.pdf17 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31_03_2025.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: brooklyn park phase 4 sold unsold march 2025.pdf18 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31_12_2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: BP P IV_compressed.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EH PHASE IV (1).pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 30-09-2024 .pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: BP P IV.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta brooklyn phase IV.pdf18 Oct 2024
Certificates of CA (Form 3)File: JUNE 2024_ FORM 3 BP P IV HOUSING.pdf8 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: BP P IV REDUCE SIZE.pdf17 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SIGNED EW BP PHASE IV WING BC FORM 1 ARCH CERT 31-04-2024.pdf3 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SIGNED EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31012024.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PARKSVILLE PHASE IV WING ABCD FORM 2A Quality Assurance 31-3-2024.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BP PHASE IV WING BC QUALITY CERT 31-03-2024.pdf3 May 2024
Certificates of CA (Form 3)File: SIGNED Final Form 3 BP P IV 31-03-2024.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: BP BB8 (EHPL) Inventory.pdf16 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31-12-2023.pdf26 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31012024.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: BP-EHPL-B,C BP P IV.pdf18 Jan 2024
OtherFile: Construction Schedule BP phase 4.pdf3 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BP P IV.pdf15 Dec 2023
Proforma of Agreement for saleFile: AFS Brooklyn Park Phase IV.pdf8 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 30112023.pdf4 Dec 2023
Certificates of CA (Form 3)File: EKTA FORM 3 BP P IV 30112023.pdf4 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 bp 4.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: BP Phase 4.pdf17 Oct 2023
Certificates of CA (Form 3)File: Signed Form 3 BP P IV 31072023.pdf12 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31-07-2023.pdf11 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV FORM 1 ARCH CERT 28-7-2023.pdf1 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A QUALITY ASSURANCE BP PHASE IV 28-7-2023.pdf1 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: BP phase4, Form5.pdf27 Jul 2023
Disclosure of sold/ booked inventoryFile: BROOKLYN PARK-PH-4.pdf20 Jul 2023
OtherFile: Brooklyn Park phase4.pdf2 May 2023
Disclosure of sold/ booked inventoryFile: BP P IV.pdf6 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH BROOKLYN PARK PHASE IV.pdf4 Mar 2023
Certificates of CA (Form 3)File: FORM 3 BROOKLYN PARK PHASE IV.pdf10 Feb 2023
Certificates of CA (Form 3)File: FORM 3 BROOKLYN PARK PHASE IV.pdf10 Feb 2023
OtherFile: BP Phase IV.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31-12-22.pdf8 Feb 2023
Details of encumbrances concerned to FinanceFile: BP Phase IV.pdf4 Feb 2023
Details of encumbrances concerned to LegalFile: BP Phase IV.pdf4 Feb 2023
Declaration about Commencement CertificateFile: EKTA BP PHASE IV CC DECLARATION 31-01-2023.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A QUALITY ASSURANCE BP PHASE IV 1-01-2022.pdf4 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A QUALITY ASSURANCE BP PHASE IV 1-01-2022.pdf4 Feb 2023
CERSAI detailsFile: Housing.pdf4 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Housing.pdf4 Feb 2023
Proforma of Agreement for saleFile: Allottment Letter and Agreement for Sale - BP Ph IV.pdf4 Feb 2023
Disclosure of sold/ booked inventoryFile: BP PHASE IV.pdf15 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: brooklyn park phase IV.pdf1 Nov 2022
Disclosure of sold/ booked inventoryFile: Parksville Phase IV.pdf9 Oct 2022
Disclosure of sold/ booked inventoryFile: BROOKLYN PHASE IV.pdf14 Jul 2022
Disclosure of sold/ booked inventoryFile: brooklyn IV.pdf5 Apr 2022
Disclosure of sold/ booked inventoryFile: brooklyn park IV.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: BROOKLYN PHASE IV.pdf30 Dec 2021
Disclosure of sold/ booked inventoryFile: brooklyn park phase IV.pdf19 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21 brooklyn park phase IV.pdf6 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold InventoryBrookline park Phase 4.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Brooklyn Phase IV.pdf10 Feb 2021
Details of encumbrancesFile: Index-2 Jm 20 Crs.pdf3 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Brooklyn park IV.pdf16 Nov 2019
Certificates of CA (Form 5)File: Brooklyn park IV.pdf11 Oct 2019
Certificates of CA (Form 5)File: Brooklyan Park Phase IV 04102018110357.pdf9 Oct 2018
OtherFile: MOEF-Pollution Dept Permission-1-5.pdf16 Aug 2018
OtherFile: MOEF-Pollution Dept Permission-6-10.pdf16 Aug 2018
OtherFile: Virar tree NOC 18-07-18.pdf7 Aug 2018

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
EKTA GREENVILLE WING F,G,H,L,M,NSURVEY NO 231 AT PATHARDI NASHIK - 422 010192CompletedMar 2017Late, Jul 2017
EKTA CALIFORNIA WING A,B,C,D,ESurvey No 9 Hissa No 1 Part Undri Pune120CompletedMar 2015Late, Jul 2015
EKTA GREENVILLE ROW HOUSES AND VILLASSURVEY NO 231 AT PATHARDI NASHIK - 422 01020CompletedMay 2014Late, Jul 2017
EKTA GREENVILLE ROW HOUSE NO 29 AND 30SURVEY NO 231 AT PATHARDI NASHIK - 422 0102CompletedJul 2012Jul 2012
EKTA GREENVILLE WING A, B, C, D, E, KSURVEY NO 231 AT PATHARDI NASHIK - 422 010192CompletedApr 2012Late, Jul 2012

How this compares with Palghar

61%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 71 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BROOKLYN PARK PHASE IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmBROOKLYN PARK PHASE IVCompleted 37Lapsed / revoked 21Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: EKTA HOUSING PRIVATE LIMITED

EKTA HOUSING PRIVATE LIMITED has 9 registrations on MahaRERA, including EKTA GREENVILLE PHASE 1 WING I AND J and EKTA GREENVILLE PHASE 2 WING O , P , Q AND R. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if BROOKLYN PARK PHASE IV is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BROOKLYN PARK PHASE IV?

The registered promoter entity is EKTA HOUSING PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH1990PTC058279 and GSTIN 27AAACE2460K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BROOKLYN PARK PHASE IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BROOKLYN PARK PHASE IV?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BROOKLYN PARK PHASE IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BROOKLYN PARK PHASE IV?

The professionals named in the filing: Architect: Samir Desai; Architect: SAMEER DESAI; Architect: AJAY WADE & ASSOCIATES; Engineer: SACHIN S KARAWADE; Engineer: Amit Parshuram Kamble; Chartered Accountant: MANOJ CHATURVEDI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BROOKLYN PARK PHASE IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BROOKLYN PARK PHASE IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BROOKLYN PARK PHASE IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.