Home / Browse projects / Palghar, Maharashtra / BROOKLYN PARK PHASE IV
BROOKLYN PARK PHASE IV
By EKTA HOUSING PRIVATE LIMITED
RG-MH-09097 · RERA P99000000417 · Last updated on MahaRERA portal: 20 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 36 complaints at MahaRERA
- Completion date moved by 71 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BROOKLYN PARK PHASE IV is a Residential / Group Housing project by EKTA HOUSING PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000000417 on 15 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 71 months from the original filing. 115 of the 189 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete. 36 complaints are on record with the regulator.
At a glance
Project
- NameBROOKLYN PARK PHASE IV
- TypeResidential / Group Housing
- Location
- Narangi Bypass Rd
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401303
- Pincode401303
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000000417
- ReraGenie IDRG-MH-09097
Builder
- NameEKTA HOUSING PRIVATE LIMITED
- Entity typeCompany
- CINU45200MH1990PTC058279
- GSTIN27AAACE2460K1ZP
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsVIVEK ASHOK MOHANANI, ASHOK GOBINDRAM MOHANANI
- Other registrations8 more →
- Completed5 of 9
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jul 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Jan 2021)
- Buildings2 building records
- Documents filed100 files
Current status
Figures as on 20 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B WING | NA | 14 | 14 | 94 | 0 | 94 |
| C WING | NA | 14 | 14 | 83 | 12 | 95 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
B WING65%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C WING71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 60% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | Yes | 80% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| B WING | 1 | 1 |
| C WING | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B WING | NA | Rs 12.63 cr | Rs 7.44 cr |
| C WING | NA | Rs 11.38 cr | Rs 8.09 cr |
| - | NA | Rs 1.99 cr | Rs 1.71 cr |
Certifying professionals and partners11
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Samir Desai |
| Architect | SAMEER DESAI |
| Architect | AJAY WADE & ASSOCIATES |
| Engineer | SACHIN S KARAWADE |
| Engineer | Amit Parshuram Kamble |
| Chartered Accountant | MANOJ CHATURVEDI & CO |
| Chartered Accountant | BABULAL GUPTA & CO |
| Chartered Accountant | V MANGAL AND COMPANY |
| Chartered Accountant | Vikas Mangal |
| Chartered Accountant | Manoj Chaturvedi |
| Chartered Accountant | Shivanandan N Katdare |
| Partner | Role in project |
|---|---|
| EKTA HOUSING PRIVATE LIMITED | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO SCARCITY OF AVAILABILITY OF THE RESOURCES.
Reason as filed by the promoterReply attached herewith.
Reason as filed by the promoterWe hereby apply for extension u/s 7(3) of the RERA for the registered project BROOKLYN PARK Phase IV bearing MahaRERA registration No.P99000000417 The structure is already complete however on account of defaults by the project proponent [ B & C ], the occupation certificate shall be applied for on [ B & C ]. The possession date as per RERA has already expired on 30.07.2022, and we are hereby applying u/s 7(3) for extension till 31.07.2023. As prescribed under circular No. 07/2019 dated 8th Feb, 2019 for the consent letters, we are giving details of consents as under. Total Units 2 wings B and
Reason as filed by the promoterNon Compliance on the part of HDIL
Complaints filed with MahaRERA36
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001053 | Santosh Vallury | Ekta Housing Pvt Ltd/Ekta Parksville Homes Pvt Ltd | 04/10/2017 |
| CC006000000044071 | Meghna Rohit Khandelwal & Rohit Brijmohan Khandelwal | Ekta Housing Private Limited | 10/04/2018 |
| CC006000000479888 | deepak upadhyay | EKTA HOUSING PRIVATE LTD | 01/04/2024 |
| CC006000000171927 | Surajkumar Rajendra Rai & Another | Ekta Housing Private Limited | 24/12/2019 |
| CC006000000141195 | Ponneth Somashekharan Nair | Ekta Housing Private Limited | 09/10/2019 |
| CC006000000196407 | Prashant Karkera / Archana Karkera | Ekta World | 20/03/2021 |
| CC006000000198633 | Madhura Devendra Ranade | EKTA HOUSING PVT LTD | 18/12/2021 |
| CC006000000364642 | Madhura Devendra Ranade | EKTA HOUSING PVT LTD | 11/03/2023 |
| CC006000000199183 | SWAPNIL GOLAPKAR | EKTA HOUSING PRIVATE LIMITED THROUGH DIRECTOR VIVEK A.MOHNANI | 21/12/2021 |
| CC006000000220911 | ASHWANI KUMAR PRAHLAD PATWA | Ekta Housing Pvt. Ltd. | 15/05/2022 |
| CC006000000251848 | Kausalkumar Pralhad Patwa | Ekta Housing Private Limited | 11/07/2022 |
| CC006000000303693 | Prathamesh Girish Waidande | Ekta Housing Private Limited | 16/12/2022 |
| CC006000000251619 | Santosh Rammohan Vallury | Ekta Housing Private Limited | 22/07/2022 |
| CC006000000354390 | Vinay Shobhnath Shukla | Ekta Housing Private Limited | 23/02/2023 |
| CC006000000396994 | Yogesh Vijay Shinde | EKTA WORLD | 20/07/2024 |
| CC006000000364594 | Ramu Chellakan Nadar | Vivek A. Hohanani | 03/03/2023 |
| CC006000000395915 | KANCHAN JHA | M/s. EKTA HOUSING PVT. LTD. | 26/05/2023 |
| CC006000000397547 | Pushkar Pradepkumar Lele | Ekta Housing Private Limited | 29/09/2023 |
| CC006000000397765 | SUHAIL FARUQUE SHAIKH | EKTA HOUSING PRIVATE LIMITED | 22/10/2023 |
| CC006000000398058 | RAJA MITRA | EKTA HOUSING PVT LTD | 21/12/2023 |
| CC12401138 | Krunal Umesh Parikh | EKTA HOUSING PRIVATE LIMITED | 16/12/2024 |
| CC12401115 | MAITHILI VINAYAK CHAVAN | EKTA HOUSING PRIVATE LIMITED | 13/12/2024 |
| CC12500022 | Abhishek Sharma | EKTA HOUSING PRIVATE LIMITED | 03/01/2025 |
| CC12401258 | GEETA MANOHAR INGLESHWAR | BALAJI ENTERPRISES | 28/12/2024 |
| CC12500137 | ROHINI SATISH KOTIAN | EKTA HOUSING PRIVATE LIMITED | 15/01/2025 |
| CC12500396 | Yunus Munaf Patel | EKTA HOUSING PRIVATE LIMITED | 06/02/2025 |
| CC12500362 | SUSHANT SURESHBHAI RATHOR | EKTA HOUSING PRIVATE LIMITED | 03/02/2025 |
| CC12500370 | PANKAJ DINESH SHARMA | EKTA HOUSING PRIVATE LIMITED | 03/02/2025 |
| CC12501361 | manish ramesh almal | EKTA HOUSING PRIVATE LIMITED | 24/04/2025 |
| CC12502214 | VIJAY KUMAR RAMKUMAR MISHRA | EKTA HOUSING PRIVATE LIMITED | 03/07/2025 |
| CC12502221 | VIJAY KUMAR RAMKUMAR MISHRA | EKTA HOUSING PRIVATE LIMITED | 04/07/2025 |
| CC12502416 | PINTU TEJBAHADUR SINGH | EKTA HOUSING PRIVATE LIMITED | 16/07/2025 |
| CC12502434 | PINTU TEJBAHADUR SINGH | EKTA HOUSING PRIVATE LIMITED | 17/07/2025 |
| CC12602541 | Tejas Girish Dedhia | EKTA HOUSING PRIVATE LIMITED | 01/05/2026 |
| CC12600858 | TASNIM TAJUDDIN KHAN | EKTA HOUSING PRIVATE LIMITED | 16/02/2026 |
| CC12603339 | ARUN BADRIPRASAD UPADHYAY | EKTA HOUSING PRIVATE LIMITED | 01/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jun 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed100
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: SIGNED FORM 1 BP P IV MARCH 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: SIGNED FORM 2 BP P IV MARCH 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: SIGNED FORM 3 BP P IV MARCH 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 30-09-2025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 1File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31-12-2025 NEW FORMAT.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Sep 2025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 BROOKLYN PARK PHASE IV.pdf | 21 Jan 2026 |
| Withdrawal Update Form 3File: Signed FORM 3 BP P IV HOUSING.pdf | 21 Jan 2026 |
| Withdrawal Update Form 3File: Signed FORM 3 BP P IV HOUSING.pdf | 21 Jan 2026 |
| Form 1File: EKTA BROOKLYN PHASE IV FORM 1 30-06-2025.pdf | 17 Jul 2025 |
| Form 2File: FORM 2 EKTA BROOKLYN PARK PHASE 4.pdf | 17 Jul 2025 |
| Form 3File: Signed FORM 3 BP P IV HOUSING 30_06_2025.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold & unsold BP phase 4.pdf | 17 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31_03_2025.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: brooklyn park phase 4 sold unsold march 2025.pdf | 18 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31_12_2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: BP P IV_compressed.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EH PHASE IV (1).pdf | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 30-09-2024 .pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: BP P IV.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ekta brooklyn phase IV.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: JUNE 2024_ FORM 3 BP P IV HOUSING.pdf | 8 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: BP P IV REDUCE SIZE.pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SIGNED EW BP PHASE IV WING BC FORM 1 ARCH CERT 31-04-2024.pdf | 3 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SIGNED EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31012024.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PARKSVILLE PHASE IV WING ABCD FORM 2A Quality Assurance 31-3-2024.pdf | 3 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BP PHASE IV WING BC QUALITY CERT 31-03-2024.pdf | 3 May 2024 |
| Certificates of CA (Form 3)File: SIGNED Final Form 3 BP P IV 31-03-2024.pdf | 3 May 2024 |
| Disclosure of sold/ booked inventoryFile: BP BB8 (EHPL) Inventory.pdf | 16 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV WING BC FORM 1 ARCH CERT 31-12-2023.pdf | 26 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31012024.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: BP-EHPL-B,C BP P IV.pdf | 18 Jan 2024 |
| OtherFile: Construction Schedule BP phase 4.pdf | 3 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BP P IV.pdf | 15 Dec 2023 |
| Proforma of Agreement for saleFile: AFS Brooklyn Park Phase IV.pdf | 8 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 30112023.pdf | 4 Dec 2023 |
| Certificates of CA (Form 3)File: EKTA FORM 3 BP P IV 30112023.pdf | 4 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 bp 4.pdf | 18 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: BP Phase 4.pdf | 17 Oct 2023 |
| Certificates of CA (Form 3)File: Signed Form 3 BP P IV 31072023.pdf | 12 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31-07-2023.pdf | 11 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE IV FORM 1 ARCH CERT 28-7-2023.pdf | 1 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A QUALITY ASSURANCE BP PHASE IV 28-7-2023.pdf | 1 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: BP phase4, Form5.pdf | 27 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: BROOKLYN PARK-PH-4.pdf | 20 Jul 2023 |
| OtherFile: Brooklyn Park phase4.pdf | 2 May 2023 |
| Disclosure of sold/ booked inventoryFile: BP P IV.pdf | 6 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH BROOKLYN PARK PHASE IV.pdf | 4 Mar 2023 |
| Certificates of CA (Form 3)File: FORM 3 BROOKLYN PARK PHASE IV.pdf | 10 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 BROOKLYN PARK PHASE IV.pdf | 10 Feb 2023 |
| OtherFile: BP Phase IV.pdf | 10 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EW BP PHASE IV Form 2 ENGINEER CERTIFICATE 31-12-22.pdf | 8 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: BP Phase IV.pdf | 4 Feb 2023 |
| Details of encumbrances concerned to LegalFile: BP Phase IV.pdf | 4 Feb 2023 |
| Declaration about Commencement CertificateFile: EKTA BP PHASE IV CC DECLARATION 31-01-2023.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A QUALITY ASSURANCE BP PHASE IV 1-01-2022.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A QUALITY ASSURANCE BP PHASE IV 1-01-2022.pdf | 4 Feb 2023 |
| CERSAI detailsFile: Housing.pdf | 4 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Housing.pdf | 4 Feb 2023 |
| Proforma of Agreement for saleFile: Allottment Letter and Agreement for Sale - BP Ph IV.pdf | 4 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: BP PHASE IV.pdf | 15 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: brooklyn park phase IV.pdf | 1 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Parksville Phase IV.pdf | 9 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: BROOKLYN PHASE IV.pdf | 14 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: brooklyn IV.pdf | 5 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: brooklyn park IV.pdf | 7 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: BROOKLYN PHASE IV.pdf | 30 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: brooklyn park phase IV.pdf | 19 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21 brooklyn park phase IV.pdf | 6 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold InventoryBrookline park Phase 4.pdf | 3 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ekta Brooklyn Phase IV.pdf | 10 Feb 2021 |
| Details of encumbrancesFile: Index-2 Jm 20 Crs.pdf | 3 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Brooklyn park IV.pdf | 16 Nov 2019 |
| Certificates of CA (Form 5)File: Brooklyn park IV.pdf | 11 Oct 2019 |
| Certificates of CA (Form 5)File: Brooklyan Park Phase IV 04102018110357.pdf | 9 Oct 2018 |
| OtherFile: MOEF-Pollution Dept Permission-1-5.pdf | 16 Aug 2018 |
| OtherFile: MOEF-Pollution Dept Permission-6-10.pdf | 16 Aug 2018 |
| OtherFile: Virar tree NOC 18-07-18.pdf | 7 Aug 2018 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| EKTA GREENVILLE WING F,G,H,L,M,N | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 192 | Completed | Mar 2017 | Late, Jul 2017 |
| EKTA CALIFORNIA WING A,B,C,D,E | Survey No 9 Hissa No 1 Part Undri Pune | 120 | Completed | Mar 2015 | Late, Jul 2015 |
| EKTA GREENVILLE ROW HOUSES AND VILLAS | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 20 | Completed | May 2014 | Late, Jul 2017 |
| EKTA GREENVILLE ROW HOUSE NO 29 AND 30 | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 2 | Completed | Jul 2012 | Jul 2012 |
| EKTA GREENVILLE WING A, B, C, D, E, K | SURVEY NO 231 AT PATHARDI NASHIK - 422 010 | 192 | Completed | Apr 2012 | Late, Jul 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 100 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep BROOKLYN PARK PHASE IV on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar
Filed coordinates, straight-line distance. 63 registered projects within 2 km.
Mayfair Virar Gardens Cluster-VI
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS CLUSTER IV
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19,
MAYFAIR HOUSING
Agarwal Infinity
Laxminarayan Prabhudayal Agarwal
GOKUL HARI ANANTA
Mehta Ventures
GOKUL NAKSHATRA II
JSB HOMEMAKERS PRIVATE LIMITED
See every Palghar project, with the district possession charts
Builder: EKTA HOUSING PRIVATE LIMITED
EKTA HOUSING PRIVATE LIMITED has 9 registrations on MahaRERA, including EKTA GREENVILLE PHASE 1 WING I AND J and EKTA GREENVILLE PHASE 2 WING O , P , Q AND R. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if BROOKLYN PARK PHASE IV is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BROOKLYN PARK PHASE IV?
The registered promoter entity is EKTA HOUSING PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH1990PTC058279 and GSTIN 27AAACE2460K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BROOKLYN PARK PHASE IV?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against BROOKLYN PARK PHASE IV?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for BROOKLYN PARK PHASE IV?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BROOKLYN PARK PHASE IV?
The professionals named in the filing: Architect: Samir Desai; Architect: SAMEER DESAI; Architect: AJAY WADE & ASSOCIATES; Engineer: SACHIN S KARAWADE; Engineer: Amit Parshuram Kamble; Chartered Accountant: MANOJ CHATURVEDI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BROOKLYN PARK PHASE IV?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback