Home / Browse projects / Palghar, Maharashtra / BROOKLYN PARK PHASE III

Completed No litigation declared Residential / Group Housing project

BROOKLYN PARK PHASE III

By EKTA PARKSVILLE HOMES PVT. LTD.

RG-MH-08471 · RERA P99000000148 · Last updated on MahaRERA portal: 7 Feb 2025

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA
  • Completion date moved by 41 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jul 2023Possession promisedregistration recorded completed
27 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 81%
12Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

BROOKLYN PARK PHASE III is a Residential / Group Housing project by EKTA PARKSVILLE HOMES PVT. LTD. in Palghar, Maharashtra, registered with MahaRERA as P99000000148 on 5 Jul 2017. The registration is recorded completed; possession was promised by 27 Jul 2023. The completion date has moved by 41 months from the original filing. 12 complaints are on record with the regulator.

At a glance

Project

  • NameBROOKLYN PARK PHASE III
  • TypeResidential / Group Housing
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000000148
  • ReraGenie IDRG-MH-08471

Builder

  • NameEKTA PARKSVILLE HOMES PVT. LTD.
  • Entity typeCompany
  • CINU70102MH1988PTC050060
  • GSTIN27AAACW4316N1Z2
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsDILIP LAXMAN BORHADE, PRAKASH TRIBHUVANDAS TANNA, DILIP LAXMAN BORHADE, PRAKASH TRIBHUVANDAS TANNA
  • Other registrations6 more →
  • Completed5 of 7

Key dates

this monthRegisteredJul 2017First promiseFeb 2020Revised toJul 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Jul 2017
  • Promised completion27 Jul 2023
  • Revised completionRevised to 27 Jul 2023 (originally 28 Feb 2020)
  • Buildings3 building records
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SEC III BUILDING NO 9 WING ANA140000
SEC III BUILDING NO 9 WING BNA140000
SEC III BUILDING NO 9 WING CNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 81%.

SEC III BUILDING NO 9 WING A89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises74%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SEC III BUILDING NO 9 WING B89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises81%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SEC III BUILDING NO 9 WING C88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises68%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 7 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
LAWNYes100%
GazeboYes100%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
SEC III BUILDING NO 9 WING A11
SEC III BUILDING NO 9 WING B11
SEC III BUILDING NO 9 WING C11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area919 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7981.91
Proposed, not sanctioned7,982 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR UNIT NO 001A HALLMARK BUSINESS PLAZA NEAR COLLECTORS OFFICE BANDRA EAST MUMBAI 400051

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJAY WADE AND ASSOCIATES
PartnerRole in project
EKTA PARKSVILLE HOMES PVT. LTD.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000012337Feb 2020 → Apr 2023

Reason as filed by the promoterwe have almost completed the project but are pending for the environment Clearance Certificate, Once will get applied for the OC.

EXT99000005765Feb 2020 → Feb 2021

Reason as filed by the promoterdue to scarcity of the resources & also some technical reasons.

EXT99000016883Feb 2020 → Jul 2023

Reason as filed by the promoterReply attached herewith.

Litigation declared3

CaseCourtStatus
887/2016BOMBAY CIVIL COURTWithdrawal
889/2016BOMBAY CIVIL COURTWithdrawal
890/2016BOMBAY CIVIL COURTWithdrawal

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000141021Archana Pradeep PandeyEkta Housing Private Limited24/09/2019
CC006000000194189AJINKYA PRAKASH PALANDEEKTA PARKSVILLE HOMES PRIVATE LTD29/09/2020
CC006000000001076VIJAY JAISINGHEkta Parksville homes Pvt Ltd09/10/2017
CC006000000012698Somya ChawanEKTA WORLD PVT LTD04/03/2018
CC006000000193345prasanth bamblasseryAshok mohnani24/05/2021
CC006000000231261apurva PEDNEKAREKTA PARKSVILLE HOMES PVT LTD06/06/2022
CC006000000196205Akshay B. SaveVivek Mohnani16/03/2021
CC006000000397562Akshay SaveEkta Housing (P) Ltd.29/09/2023
CC006000000196425Amit ShahEkta Parksville Homes Pvt Ltd.23/03/2021
CC006000000251623Rajesh KananiM/s Ekta Parksville Homes Pvt. Ltd.25/06/2022
CC006000000282216Heena Sanjay SharmaM/s Ekta Parksville Homes Private Limited05/08/2022
CC006000000302901Ms Manisha BandekarEkta Parksville Homes Pvt Ltd30/09/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jun 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Feb 2025

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 BP PHASE III 1-8-2023.pdf7 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 27-07-2023.pdf7 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 BP PHASE III 1-8-2023.pdf8 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 BP PHASE III 1-8-2023.pdf19 Dec 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: society formation.pdf16 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: brooklyn park phase III.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: BP P III.pdf9 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VIRAR 1ST OC 15052019 B9 G AND I.pdf22 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: BP P III.pdf3 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: virar OC 28072023.pdf30 Jul 2023
Disclosure of sold/ booked inventoryFile: BROOKLYN PARK-PH-3.pdf20 Jul 2023
Certificates of CA (Form 3)File: FINAL Form 3 BPPIII 31 may 2023.pdf29 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SIGNED EW BP PHASE III WING ABC Form 2 ENG CERT 31 MAY 23 1.pdf27 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW BP PHASE III FORM1 ARCH CERT 31-3-23.pdf22 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance (Form 2A FY 2022-23).pdf22 Jun 2023
Disclosure of sold/ booked inventoryFile: BP P III.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 BP Phase 3.pdf10 Mar 2023
Certificates of CA (Form 3)File: FORM 3 BP Phase 3.pdf10 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Virar C P GOYAL.pdf4 Mar 2023
Details of encumbrances concerned to FinanceFile: BP Phase III.pdf27 Feb 2023
Details of encumbrances concerned to LegalFile: BP Phase III.pdf27 Feb 2023
Declaration about Commencement CertificateFile: EKTA BP PHASE III CC DECLARATION 20-02-2023.pdf27 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BP PHASE III WING ABC FORM 1 ARCH CERT 20-02-2023.pdf27 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: EW BP WING ABC PHASE III QUALITY ASSURANCE 31-12-2020.pdf27 Feb 2023
CERSAI detailsFile: Parksville.pdf20 Feb 2023
Proforma of Agreement for saleFile: Allottment Letter and Agreement for Sale Brooklyn Park Phase III.pdf15 Feb 2023
Disclosure of sold/ booked inventoryFile: BP PHASE III.pdf16 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EW form 1BP WING ABC FORM 2 ARCH CERT 20-10-2022_11zon.pdf20 Oct 2022
Certificates of CA (Form 3)File: Form-3 brooklyn park PHASE III.pdf20 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: EW BP WING ABC PHASE III QUALITY CERT 17-10-2022.pdf19 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: BROOKLYN PARK PHASE III.pdf19 Oct 2022
Disclosure of sold/ booked inventoryFile: BROOKLYN PARK III.pdf9 Oct 2022
Disclosure of sold/ booked inventoryFile: BROOKLYN PHASE III.pdf14 Jul 2022
Disclosure of sold/ booked inventoryFile: brooklyn III.pdf5 Apr 2022
Disclosure of sold/ booked inventoryFile: brooklyn park III.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: BROOKLYN PARK PHASE III.pdf30 Dec 2021
Disclosure of sold/ booked inventoryFile: Brooklyn Park Phase III.pdf19 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21 brooklyn park phase III.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: sold inventory Brookline Phase 3.pdf3 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Brooklyn Park Phase III.pdf10 Feb 2021
Details of encumbrancesFile: Index-2 Jm 20 Crs.pdf3 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Brooklyn park III.pdf16 Nov 2019
Certificates of CA (Form 5)File: Brooklyn park III.pdf11 Oct 2019
Certificates of CA (Form 5)File: Brooklyan Park Phase III 04102018110255.pdf9 Oct 2018
OtherFile: MOEF-Pollution Dept Permission-1-5.pdf16 Aug 2018
OtherFile: MOEF-Pollution Dept Permission-6-10.pdf16 Aug 2018
OtherFile: Virar tree NOC 18-07-18.pdf7 Aug 2018
Details of encumbrancesFile: Parksville.pdf7 Apr 2018
Details of encumbrancesFile: JMF-Indenture of Mortgage-2423-2018-303-303.pdf7 Apr 2018
Details of encumbrancesFile: Index II TATA Capital.pdf30 Nov 2017
Copy of the legal title reportFile: WG Title Report DT 09-01-2012.pdf1 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part I_1.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part I_2.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part I_3.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part I_4.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part I_5.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part I_6.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part II_1.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part II_2.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part II_3.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part II_4.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: EPHPL - Virar - Bldg No 9 - DA Part II_5.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Bldg No 9 POA Part I.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Bldg No 9 POA Part II.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental Agreement Bldg No 9 Part I.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 Part II.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 Part III.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 Part IV.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 Part V.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 Part VI.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 Part VII.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 VIII.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 IX.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 X.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Supplemental DA Bldg No 9 XI.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: POA for Supplemental DA Bldg No 9 Part I.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: POA for Supplemental DA Bldg No 9 Part II.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Bldg No 9 CC Part I.pdf30 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Bldg No 9 CC Part II.pdf30 Jun 2017
Building plan approvalFile: covering letter for virar layout 1.pdf24 Jun 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 41 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BROOKLYN PARK PHASE III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmBROOKLYN PARK PHASE IIICompleted 62Lapsed / revoked 39Other 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 154 registered projects within 2 km.

Builder: EKTA PARKSVILLE HOMES PVT. LTD.

EKTA PARKSVILLE HOMES PVT. LTD. has 7 registrations on MahaRERA, including EKTA PARKSVILLE PHASE I and EKTA PARKSVILLE PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if BROOKLYN PARK PHASE III is delayed beyond 27 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BROOKLYN PARK PHASE III?

The registered promoter entity is EKTA PARKSVILLE HOMES PVT. LTD., a company as per the filing. Its CIN U70102MH1988PTC050060 and GSTIN 27AAACW4316N1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BROOKLYN PARK PHASE III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BROOKLYN PARK PHASE III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BROOKLYN PARK PHASE III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BROOKLYN PARK PHASE III?

The professionals named in the filing: Architect: AJAY WADE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BROOKLYN PARK PHASE III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BROOKLYN PARK PHASE III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BROOKLYN PARK PHASE III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.