Home / Browse projects / Mumbai Suburban, Maharashtra / BRINDAVAN CHSL

Registered No litigation declared Residential / Group Housing project

BRINDAVAN CHSL

By MITESH BHIKHUBHAI SHAH

RG-MH-18526 · RERA P51800076772 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2028Possession promisedmoved 28 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 90%
1Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

BRINDAVAN CHSL is a Residential / Group Housing project by MITESH BHIKHUBHAI SHAH in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800076772 on 28 Jun 2024. Possession is promised by 30 Oct 2028. The completion date has moved by 28 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBRINDAVAN CHSL
  • TypeResidential / Group Housing
  • Location
    • YASHWANTRAO TAWADE MARG
    • OPP DAHISAR RAILWAY STATION DAHISAR WEST
    • Dahisar
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • RERA no.P51800076772
  • ReraGenie IDRG-MH-18526

Builder

  • NameMITESH BHIKHUBHAI SHAH
  • Entity typeIndividual
  • Other registrations3 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredJun 2024First promiseJun 2026Revised toOct 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Jun 2024
  • Promised completion30 Oct 2028
  • Revised completionRevised to 30 Oct 2028 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed62 files

Current status

34.2%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PROP RED OF EXIST BLDG KNOWN AS BRINDAVAN CHSL SITUATED AT Y R TAWADE MARG DAHISAR W MUMBAI 400068NA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

PROP RED OF EXIST BLDG KNOWN AS BRINDAVAN CHSL SITUATED AT Y R TAWADE MARG DAHISAR W MUMBAI 400068: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered1
Open Space26

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,439 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jun 2025
LandownerVillageDistrict
BRINDAVAN CHSLDahisarMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3884.94
Proposed, not sanctioned1,817 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHAVIR NAGAR KANDIVALI WEST MUMBAI 400067
Estimated costRs 9.25 cr
Cost incurredRs 3.16 cr
Work done34.16%
BuildingWingEstimatedIncurred
PROP RED OF EXIST BLDG KNOWN AS BRINDAVAN CHSL SITUATED AT Y R TAWADE MARG DAHISAR W MUMBAI 400068NARs 9.25 crRs 3.16 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJEEGAR TANNA
ArchitectMEHUL KANAKIA
EngineerUNISTEPS CONSULTING
EngineerUniSteps Consulting Pvt. Ltd.
Chartered AccountantANPM & CO LLP
Chartered AccountantSukhwal & Associates
Chartered AccountantGEETA NARANG
Chartered AccountantANKUR JAIN
PartnerRole in project
MITESH BHIKHUBHAI SHAH-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA22072621836Jun 2026 → Jun 2028

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow. 3) Due to changes and alterations in the sale units/layout, revised concessions and approvals are required from the Municipal Commissioner. Additionally, certain finishing works remain pending because of the limited plot area, which creates challenges in storing and handling construction materials, thereby affecting the progress of the remaining work.

P51800076772/WarJun 2026 → Oct 2028

Reason as filed by the promoterNA

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500150Bhakti AchrekarMITESH BHIKHUBHAI SHAH25/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2028

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf22 Jul 2026
Withdrawal Update Form 2File: FORM 2.pdf22 Jul 2026
Withdrawal Update Form 3File: Signed Brindavan Q4 25-26_0001.pdf22 Jul 2026
Form 2A (FY 2024-2025)File: Form- 2A April 2024 to March 2025.pdf22 Jul 2026
Form 2A (FY 2025-2026)File: Form- 2A April 2025 to March 2026.pdf22 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf11 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf11 Jun 2026
Withdrawal Update Form 3File: Signed Brindavan Q4 25-26_0001.pdf11 Jun 2026
Withdrawal Update Form 1File: RERA CERTIFICATE (1).pdf18 Feb 2026
Withdrawal Update Form 2File: FORM 2.pdf18 Feb 2026
Withdrawal Update Form 3File: Q3_CA certificate Brindavan.pdf18 Feb 2026
Withdrawal Update Form 1File: RERA CERTIFICATE (1).pdf13 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf13 Jan 2026
Withdrawal Update Form 3File: Q2 CA certificate Brindavan Project.pdf13 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5 BRD.pdf25 Nov 2025
Withdrawal Update Form 1File: Architect Certifucate Form 1.pdf19 Sep 2025
Withdrawal Update Form 1File: Architect Certifucate Form 1.pdf19 Sep 2025
Withdrawal Update Form 2File: BRD Signed Form 2 Q3 MITESH SIR SIGH.pdf19 Sep 2025
Withdrawal Update Form 2File: BRD Signed Form 2 Q3 MITESH SIR SIGH.pdf19 Sep 2025
Withdrawal Update Form 3File: FORM 3 FINAL.pdf19 Sep 2025
Withdrawal Update Form 3File: FORM 3 FINAL.pdf19 Sep 2025
Withdrawal Update Form 1File: Architect Certifucate Form 1.pdf18 Sep 2025
Withdrawal Update Form 2File: BRD Signed Form 2 Q3 MITESH SIR SIGH.pdf18 Sep 2025
Withdrawal Update Form 3File: FORM 3 FINAL.pdf18 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8TH SLAB CERTIFICATE.pdf25 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BRD Signed Form 3 Q3 MITESH SIR SIGH.pdf11 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BRD Signed Form 2 Q3 MITESH SIR SIGH.pdf11 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1 FORM - 1 (Architect Certificate) NEW FORMAT WEF.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 FORM - 1 (Architect Certificate) NEW FORMAT WEF.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1 FORM - 1 (Architect Certificate) NEW FORMAT WEF.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1 FORM - 1 (Architect Certificate) NEW FORMAT WEF.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BRD_FORM 1 Q1 FY 24-25.pdf20 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BRD_FORM 1 Q2 FY 24-25.pdf20 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BRD Form 3 Q1 FY 24-25 Signed.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BRD Form 3 Q2 FY 24-25 Signed.pdf18 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BRD Form 2 Q1 FY 24-25 Signed.pdf18 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BRD Form 2 Q2 FY 24-25 Signed.pdf18 Dec 2024
Proforma of Agreement for saleFile: BRD Agreement for Sales AFS.pdf20 Jun 2024
Proforma of Allotment letterFile: Model Form of Allotment Letter Ann A-compressed.pdf20 Jun 2024
Deviation Report with respect to Allotment letterFile: No Deviation Allottment Letter.pdf20 Jun 2024
Deviation Report with respect to model copy of AgreementFile: No Deviation Agreement for Sales.pdf20 Jun 2024
Declaration about Commencement CertificateFile: BRD DECLARATION ABOUT CC.pdf19 Jun 2024
Details of encumbrances concerned to FinanceFile: BRD No Encurmbance Legal.pdf18 Jun 2024
Details of encumbrances concerned to LegalFile: BRD No Encurmbance Legal.pdf18 Jun 2024
Declaration in FORM BFile: BRD Form B Mitesh B Shah.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL 1.pdf18 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: BRD Disclosure of Interest in other Real Estate.pdf18 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BRD Seprate Bank Format 'A'.pdf18 Jun 2024
Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf13 Jun 2024
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf13 Jun 2024
PAN CardFile: 2 PAN Card.pdf13 Jun 2024
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf13 Jun 2024
Details of encumbrances concerned to FinanceFile: BRD Legal.pdf13 Jun 2024
Details of encumbrances concerned to LegalFile: BRD Legal.pdf13 Jun 2024
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf13 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf13 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certifucate Form 1.pdf13 Jun 2024
CERSAI detailsFile: 2 CERSAI details.pdf13 Jun 2024
CERSAI detailsFile: CERSAI_Search_Report_200310201389_For_Asset_Based_Search_13_06_2024_19_31_49_852 (1).pdf13 Jun 2024
Other - LegalFile: 1 Other - Legal.pdf13 Jun 2024
Other - FinanceFile: Details of encumbrances concerned to Finance.pdf13 Jun 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SAPNA CHSLKOTHARIWADI RAMCHANDRALANE MALAD W24CompletedJun 2017May 2017
MATRUPRIYACHICKUWADI BORIVALI WEST24CompletedNov 2007Late, Dec 2016
TRI HANS CHSLTPS 3FP NO 505 CHICKUWADI BORIVALI WEST MUMBAI 40009216CompletedDec 2006Jul 2006

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 28 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BRINDAVAN CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP DAHISAR RAILWAY STATION DAHISAR WEST6,700+ in Mumbai Suburban

Builder: MITESH BHIKHUBHAI SHAH

MITESH BHIKHUBHAI SHAH has 4 registrations on MahaRERA, including BRINDAVAN CHSL and RIJIN CITYSHORE. Its filings disclose 7 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if BRINDAVAN CHSL is delayed beyond 30 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BRINDAVAN CHSL?

The registered promoter entity is MITESH BHIKHUBHAI SHAH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BRINDAVAN CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BRINDAVAN CHSL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BRINDAVAN CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BRINDAVAN CHSL?

The professionals named in the filing: Architect: JEEGAR TANNA; Architect: MEHUL KANAKIA; Engineer: UNISTEPS CONSULTING; Engineer: UniSteps Consulting Pvt. Ltd.; Chartered Accountant: ANPM & CO LLP; Chartered Accountant: Sukhwal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BRINDAVAN CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BRINDAVAN CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BRINDAVAN CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.