Brain Matrix

By M/s Bora Associates

RG-MH-49618 · RERA P52100050187 · Last updated on MahaRERA portal: 24 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
3 of 9Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 20%
6 of 8Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

Brain Matrix is a Others project by M/s Bora Associates in Pune, Maharashtra, registered with MahaRERA as P52100050187 on 21 Mar 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 2 of the 8 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameBrain Matrix
  • TypeOthers
  • Location
    • Aundh
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411007
  • Pincode411007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050187
  • ReraGenie IDRG-MH-49618

Builder

  • NameM/s Bora Associates
  • Entity typePartnership
  • PartnerMANGALA GAUTAM BORA

Key dates

this monthRegisteredMar 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Mar 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed105 files

Current status

25%2 of 8 units booked
54.4%Work done, per cost certificate

Figures as on 24 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building BNA87088
B BuildingNA87000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 20%.

Building B36%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B BuildingNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered8
Open Space38

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,397 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Dec 2025
LandownerVillageDistrict
Ramakant Shridhar DevPune (M Corp.)Pune
Shridhar Ramakant DevPune (M Corp.)Pune
Geetanjali Sadanand KulkarniParvatiPune
Medha Uday DeshpandeParvatiPune
Dattatray Shridhar DeoParvatiPune
Sulabha Dattatray DeoParvatiPune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI2793.0
Proposed, not sanctioned2,793 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchYes Bank Ltd, Part Ground Floor, 582/D, Bazar Samiti Building, Market Yard, Pune-411037, Maharashtra
Estimated costRs 10.98 cr
Cost incurredRs 5.97 cr
Work done54.35%
BuildingWingEstimatedIncurred
Building BNARs 10.73 crRs 5.97 cr
-NARs 25.00 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISHAL ASODEKAR
EngineerVenugopal Bhimrao Gidde
Chartered AccountantUmesh Ugare
Chartered AccountantUMESH B. UGARE AND ASSOCIATES
Chartered AccountantASHISH RATHI AND CO.
PartnerRole in project
M/s Bora Associates-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31122519167Dec 2025 → Dec 2026

Reason as filed by the promoterThe extension is majorly due to significant Material shortages, which severely have impacted the construction timeline, delaying important stages of project. However, we are nearing the project completion and preparing to apply for OC. Hence, additional time is required to address the delays, requesting you to grant us the same

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4 25-26 - Brain Matrix Aundh (1).pdf24 Jun 2026
Withdrawal Update Form 2File: FORM 2 (ENGINEER CERTIFICATE).pdf24 Jun 2026
Withdrawal Update Form 3File: RERA Form - 3 - Jan 26 to March 26.pdf24 Jun 2026
Withdrawal Update Form 1File: Form 1 Q3 25-26 - Brain Matrix Aundh.pdf2 Mar 2026
Withdrawal Update Form 2File: Form 2 - Oct 25 to Dec 25 signed.pdf2 Mar 2026
Withdrawal Update Form 3File: Form-3 Q3 25-26 Signed.pdf2 Mar 2026
Form 1File: form 1 dec 2023.pdf11 Nov 2025
Form 2File: form 2 dec 2023.pdf11 Nov 2025
Form 3File: form 3 dec 2023.pdf11 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold and unsold inventory dec 2023.pdf11 Nov 2025
Form 1File: form 1 sept 2024.pdf11 Nov 2025
Form 2File: form 2 sept 2024.pdf11 Nov 2025
Form 3File: form 3 sept 2024.pdf11 Nov 2025
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory sept 2024.pdf11 Nov 2025
Form 2A (FY 2023-2024)File: Form-2A FY 2023-24 Bora Associates (1).pdf11 Nov 2025
Form 2A (FY 2024-2025)File: Form-2A FY 2024-25 Bora Associates (1).pdf11 Nov 2025
Form 5 (FY 2023-2024)File: FORM 5 FY 2023-24 BORA ASSOCIATES.pdf4 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25 BORA ASSOCIATES.pdf4 Nov 2025
Form 1File: Form 1 Q2 25-26 - Brain Matrix Aundh.pdf1 Nov 2025
Form 2File: Form 2 - July 25 to Sept 25.pdf1 Nov 2025
Form 3File: RERA Form-3 - July 25 to Sept 25.pdf1 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Sept 25.pdf1 Nov 2025
Form 1File: FORM 1 (Jan 2025 to March 2025).pdf29 Oct 2025
Form 2File: FORM-2 (Jan 25 to March 25).pdf29 Oct 2025
Form 3File: Form 3 - Jan 25 to March 25.pdf29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory March 25.pdf29 Oct 2025
Form 1File: Form 1 - April 2025 to June 2025.pdf8 Oct 2025
Form 2File: Form 2 - April 25 to June 25.pdf8 Oct 2025
Form 3File: RERA Form-3 - April 25 to June 25.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory June 25.pdf8 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (Oct 2024 to Dec 2024).pdf25 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Oct 24 to Dec 24.pdf25 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf25 Feb 2025
Layout approvalFile: New Sanction Layout 01_11zon.pdf6 Jan 2025
Building plan approvalFile: New Sanction Plan 02_11zon.pdf6 Jan 2025
Copy of Layout Approval (in case of layout)File: New Sanction Layout 01_11zon.pdf6 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: New Commercial Comencement Certificate.pdf6 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: New Sanction Plan 02_11zon.pdf6 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - July 24 to Sept 24_compressed.pdf18 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold-Booked Inventory011024.pdf18 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 sep 2024.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 sep 2024.pdf9 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf14 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 APRIL 23 TO JUNE 23.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 July to Sept 23.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct to Dec 23.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 24 to March 24.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 24 to March 24.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 APRIL 23 TO JUNE 23.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 July to Sept 23.pdf21 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 July to Sept 23.pdf21 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3 JAN 24 TO MAR 24_compressed.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECH CERTIFICATE JAN 24 TO MARCH 24.pdf13 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 24 to March 24.pdf13 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Adobe Acrobat Document.pdf13 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Adobe Acrobot Document.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: fORM 2A22-23.pdf7 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA FORM 5 ANUUAL REPORT FY22-23.pdf7 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form -2A Aundh Brain Matrix.pdf28 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold-Booked Inventory.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan 23 to March 23.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 April to March 23.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 April 23 to June 23.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 July to Sept 23.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct to Dec 23.pdf21 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 Jan 23 to March 23.pdf21 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 April 23 to June 23.pdf21 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 July to Sept 23.pdf21 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 Oct to Dec 23.pdf21 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JAN 23 TO MARCH 23_compressed.pdf21 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 APRIL 23 TO JUNE 23_compressed.pdf21 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JULY 23 TO SEPT 23.pdf21 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 OCT 23 TO DEC 23_compressed.pdf21 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: correct FORM 2 VENUGOPAL CERTIFICATEcompressedpage0001.pdf7 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECH CERTIFICATEcompressed.pdf5 Mar 2023
Details of encumbrances concerned to FinanceFile: Encumbrances legal.pdf26 Feb 2023
Details of encumbrances concerned to LegalFile: Encumbrances legal.pdf26 Feb 2023

How this compares with Pune

25%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Brain Matrix on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Aundh13,700+ in Pune

2 kmBrain MatrixCompleted 163Lapsed / revoked 119Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: M/s Bora Associates

M/s Bora Associates has 1 registration on MahaRERA, including Brain Matrix. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Brain Matrix is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Brain Matrix?

The registered promoter entity is M/s Bora Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Brain Matrix?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Brain Matrix?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Brain Matrix?

The professionals named in the filing: Architect: VISHAL ASODEKAR; Engineer: Venugopal Bhimrao Gidde; Chartered Accountant: Umesh Ugare; Chartered Accountant: UMESH B. UGARE AND ASSOCIATES; Chartered Accountant: ASHISH RATHI AND CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brain Matrix?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brain Matrix. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brain Matrix to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.