Home / Browse projects / Raigarh, Maharashtra / BRAHMARAJ ENCLAVE

Registration lapsed No litigation declared Residential / Group Housing project

BRAHMARAJ ENCLAVE

By SUSHILKUMAR BRAMHADIN MISHRA

RG-MH-22898 · RERA P52000029079 · Last updated on MahaRERA portal: 7 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 96%
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

BRAHMARAJ ENCLAVE is a Residential / Group Housing project by SUSHILKUMAR BRAMHADIN MISHRA in Raigarh, Maharashtra, registered with MahaRERA as P52000029079 on 26 Apr 2021. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameBRAHMARAJ ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • SECTOR 23
    • PLOT NO 37
    • ULWE
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000029079
  • ReraGenie IDRG-MH-22898

Builder

  • NameSUSHILKUMAR BRAMHADIN MISHRA
  • Entity typeIndividual

Key dates

19 months past promisethis monthRegisteredApr 2021First promiseMar 2022Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Apr 2021
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 25 Mar 2022)
  • Buildings1 building record
  • Documents filed46 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BRAHMARAJ ENCLAVENA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 96%.

BRAHMARAJ ENCLAVE: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%

Progress on shared amenities15

As on 7 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered8

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area499 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Pandrinath Namdev BhagatUlaweRaigarh
Pandharinath Namdev BhagatNavi Mumbai (M Corp.)Thane

Approvals and building plan

Permissible FSI748.28
Proposed, not sanctioned748 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIDTOWN CO-OP HSG SOCIETY, PLOT NO A-005, SECTOR-9, MULUND AIROLI HIGHWAY, AIROLI, NAVI MUMBAI 40070

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMANT P DHAVALE
EngineerVIKRAM VINOD MISHRA
EngineerVilas Agharkar
Chartered AccountantBHAVNA AMIT PATIL
PartnerRole in project
SUSHILKUMAR BRAMHADIN MISHRA-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000011851Mar 2022 → Aug 2023

Reason as filed by the promoterDue to no sales of the unit constructed we are unable to fund the project . Due to which the project has faced the delay for more than six months .

EXT52000017770Mar 2022 → Mar 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 100% allottees for purpose of extension of RERA registration period of the said project.

EXT52000025053Mar 2022 → Mar 2025

Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by Delay in OC. By implementing the outlined action plan, we aim to mitigate these delays and move forward efficiently. However, we assure you that our utmost priority is to safeguard the interests of the allottees and ensure the successful completion of the project In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. We have consent of 100% allottees for purpose of extension of RERA registration period of the said project.we kindly request an extension u/s until 31

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 updated for ulwe September 2024_11zon.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24 updated ulwe.pdf7 Nov 2024
Declaration in FORM BFile: Form B 31-03-2025.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate for ulwe oct 2024.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ulwe rera extension engineer certificate _11zon.pdf30 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality certificate form 2A for ulwe rera.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 rera ulwe extension .pdf30 Oct 2024
CERSAI detailsFile: Cersai letter Rera ulwe.pdf25 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Sushil mishra for Rera ulwe.pdf25 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Rera ulwe.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Brahmaraj.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer certificate ulwe.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Circular 29 Brahmaraj.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate ulwe_11zon.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Circular 29 latest.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2223.pdf19 Dec 2023
Declaration about Commencement CertificateFile: Format D.pdf21 Nov 2023
Declaration in FORM BFile: Affidavit Cum Declaration.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form -2A 2019-20 Brahmaraj Developers.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form -2A 2020-2021 Brahmaraj Developers.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form -2A 2021-2022 Brahmaraj Developers.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form -2A 2022-2023 Brahmaraj Developers.pdf21 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 26-04_11zon.pdf31 Oct 2023
Layout approvalFile: cc plan approved COMP.pdf20 Apr 2021
Copy of Layout Approval (in case of layout)File: cc plan approved COMP.pdf20 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: cc plan approved COMP.pdf20 Apr 2021
Proforma of Allotment letterFile: Allotment Letter.pdf20 Apr 2021
Copy of the legal title reportFile: 11 Title Clearance Certificate.pdf30 Mar 2021
Details of encumbrancesFile: 8 Encumbrance Certificate.pdf30 Mar 2021
Declaration in FORM BFile: 7 Affidavit Cum Declaration.pdf30 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE- 37,23-ULWE.pdf30 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE FOR RERA_compressed.pdf30 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_compressed.pdf30 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5.pdf30 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf30 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf30 Mar 2021
Proforma of Allotment letterFile: 11 Agreement for Sale_compressed_compressed (1).pdf30 Mar 2021
Details of Restarting of Construction work post lockdownFile: post lockdown.pdf30 Mar 2021
Details of Restarting of Construction work post lockdownFile: post lockdown.pdf30 Mar 2021
Building plan approvalFile: Building Plan Approval.pdf25 Jan 2020
PAN CardFile: PAN CARD SUSHILKUMAR MISHRA.pdf25 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf25 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf25 Jan 2020

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 36 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BRAHMARAJ ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PLOT NO 37, ULWE5,900+ in Raigarh

Builder: SUSHILKUMAR BRAMHADIN MISHRA

SUSHILKUMAR BRAMHADIN MISHRA has 1 registration on MahaRERA, including BRAHMARAJ ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that BRAHMARAJ ENCLAVE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BRAHMARAJ ENCLAVE is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BRAHMARAJ ENCLAVE?

The registered promoter entity is SUSHILKUMAR BRAMHADIN MISHRA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BRAHMARAJ ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BRAHMARAJ ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BRAHMARAJ ENCLAVE?

The professionals named in the filing: Architect: HEMANT P DHAVALE; Engineer: VIKRAM VINOD MISHRA; Engineer: Vilas Agharkar; Chartered Accountant: BHAVNA AMIT PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BRAHMARAJ ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BRAHMARAJ ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BRAHMARAJ ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.