ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / BOUGAIN VILLA - CLUSTER 1

Registered No litigation declared Commercial project

BOUGAIN VILLA - CLUSTER 1

By Synergy Properties

RG-MH-24000 · RERA P52100011902 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 120 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2031Possession promisedmoved 120 months from the original
0 of 440Construction stages doneacross 41 buildings; furthest along: Excavation, 0%
12 of 41Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

BOUGAIN VILLA - CLUSTER 1 is a Commercial project by Synergy Properties in Pune, Maharashtra, registered with MahaRERA as P52100011902 on 31 Aug 2017. Possession is promised by 31 Dec 2031. The completion date has moved by 120 months from the original filing. 29 of the 41 units on this registration are recorded sold or booked, and 0 of 440 construction stages are filed complete.

At a glance

Project

  • NameBOUGAIN VILLA - CLUSTER 1
  • TypeCommercial
  • Location
    • Bhor
    • Pasure
    • Pune
    • 412206
  • Pincode412206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011902
  • ReraGenie IDRG-MH-24000

Builder

  • NameSynergy Properties
  • Entity typePartnership
  • PartnersGanesh Dnyanoba Jadhav, Mandar Jayant Deogaonkar, Amruta Mandar Deogaonkar, Rajendra Dnyaneshwar Awate
  • Other registrations10 more →
  • Completed2 of 11
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredAug 2017First promiseDec 2021Revised toDec 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2031
  • Revised completionRevised to 31 Dec 2031 (originally 1 Dec 2021)
  • Buildings41 building records
  • Documents filed67 files

Current status

71%29 of 41 units booked
100.0%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA11101
A2NA11101
A3NA11101
A4NA11101
C1NA11101
C2NA11101
A5NA11101
A6NA11101
B1NA11101
B2NA11101
B3NA11101
B4NA11101
A7NA11101
A1-1NA11101
A1-2NA11101
A1-3NA11101
A1-4NA11101
A1-5NA11101
A1-6NA11101
A1-7NA11101
A1-8NA11101
A1-9NA11101
A1-10NA11101
A1-11NA11101
A1-12NA11101
B5NA11101
B6NA11101
D1NA11101
D2NA11101
D3NA11101
D4NA11101
D5NA11101
D6NA11101
D7NA11101
D8NA11101
D9NA11101
D10NA11101
D11NA11101
D12NA11202
RestaurantNA11011
Bougain Villa - Cluster 1NA11000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 41 buildings; the table lists the first 20.

0 of 440 construction stages are filed complete across 41 buildings. The stage furthest along is Excavation, at 0%.

A10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A50%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A70%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-50%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A1-70%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area19,567 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Oct 2025

Approvals and building plan

Permissible FSI1778.0
Proposed, not sanctioned1,778 sq m
Buildings approved41
Buildings sanctioned40

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKamala Nehru Bank erandwana
Estimated costRs 1.09 cr
Cost incurredRs 1.09 cr
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 1.09 crRs 1.09 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGROUP PHI ARCHITECTS & DESIGNERS
EngineerPradeep Dongarwar
Chartered AccountantChandorkar & Limaye Chartered Accountants
Chartered AccountantMaps and Company Chartered Accountants
PartnerRole in project
Gangotree Homes & Holidays-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29102518196Dec 2021 → Dec 2031

Reason as filed by the promoterThe following are the explanatory reasons setting out grounds and reasons for the delay in the completion of our said project: 1. I, Mr. Rajendra Dnyaneshwar Awate, Partner of M/s. Gangotree Homes & Holidays (previously known as Synergy Properties), having our registered office at Unit No. 801-804, 8th Floor, Siddharth Towers 1, Press Club Road, Kothrud, Pune - 411038, hereby submit this application for extension of the project completion date under the provisions of Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. 2. Our project titled “Bougain Villa - Cluster 1”, beari

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jun 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jun 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2031

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_ BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1_ BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1_ BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1_ BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1_ BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2 - BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2 - BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2 - BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2 - BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2 - BV Cluster 1.pdf22 Jul 2026
Withdrawal Update Form 3File: Cluster 1 Form 3.pdf22 Jul 2026
Withdrawal Update Form 3File: Cluster 1 Form 3.pdf22 Jul 2026
Withdrawal Update Form 3File: Cluster 1 Form 3.pdf22 Jul 2026
Withdrawal Update Form 3File: Cluster 1 Form 3.pdf22 Jul 2026
Withdrawal Update Form 3File: Cluster 1 Form 3.pdf22 Jul 2026
Form 5 (FY 2018-2019)File: Form 5_2018-19.pdf29 May 2026
Form 5 (FY 2019-2020)File: Form 5_2019-20.pdf29 May 2026
Form 5 (FY 2020-2021)File: Form 5_2020-21.pdf29 May 2026
Form 5 (FY 2021-2022)File: Form 5_2021-22.pdf29 May 2026
Form 5 (FY 2022-2023)File: Form 5_2022-23.pdf29 May 2026
Form 5 (FY 2023-2024)File: Form 5_2023-24.pdf29 May 2026
Form 5 (FY 2024-2025)File: Form 5_2024-25.pdf29 May 2026
Form 5 (FY 2025-2026)File: Form 5_2025-26.pdf29 May 2026
Form 5 (FY 2017-2018)File: Form 5_2018-19.pdf29 May 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Cer 19.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Cer 2020.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Cer 2021.pdf19 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cluster Cluster 1 - 2019.pdf19 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cluster Cluster 2 - 2019.pdf19 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 2020.pdf19 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 2021.pdf19 Apr 2023
OtherFile: Declaration BV1.pdf10 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert BV Cluster 1.pdf8 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert BV 1-compressed.pdf8 Dec 2021
Certificates of CA (Form 3)File: RERA CA Certificate BV1 -compressed.pdf8 Dec 2021
Copy of the legal title reportFile: STR 656 Pasure_compressed_compressed (1)_reduce (1).pdf23 Jun 2020
Layout approvalFile: 656 Sanction Plan.pdf13 Jun 2020
Copy of Layout Approval (in case of layout)File: 656 Sanction Plan.pdf13 Jun 2020
Commencement Certificates / NA Order for plotted developmentFile: 656 and others NA Order.pdf13 Jun 2020
Certificates of CA (Form 5)File: Synergy Properties Cluster 1.pdf1 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BV Cluster 1.pdf10 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BV Cluster 1.pdf10 Aug 2019
Certificates of CA (Form 3)File: Bougain Villa Cluster 1.pdf10 Aug 2019
OtherFile: Consent Letter1.pdf31 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Bougain Villa Cluster 1.pdf30 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Bougainvilla Cluster 1.pdf30 Sep 2018
Certificates of CA (Form 3)File: BV Cluster 1 CA Cert.pdf30 Sep 2018
Certificates of CA (Form 3)File: BV Cluster 1 CA Cert.pdf30 Sep 2018
Certificates of CA (Form 5)File: Form 5 Cluster 1.pdf30 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archt Cert BV Cluster 1.pdf29 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert BV Cluster 1.pdf29 Mar 2018
Certificates of CA (Form 3)File: CA Certificate BV Cluster 1.pdf29 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Cluster 1 NA.pdf10 Mar 2018
Status of Formation of Legal EntityFile: Scan0006.pdf10 Mar 2018
Copy of the legal title reportFile: BV Cluster 1.pdf8 Sep 2017
Layout approvalFile: Layout Sheet 1.PDF31 Jul 2017
Building plan approvalFile: Layout Sheet 2.PDF31 Jul 2017
PAN CardFile: PAN CARD - SYNERGY PROP.pdf31 Jul 2017
Copy of the legal title reportFile: Title BV Cluster 1.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrance BV 1.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Sheet 1.PDF31 Jul 2017
Building Plan Approval (IOD)File: Layout Sheet 2.PDF31 Jul 2017
Declaration in FORM BFile: Form B BV 1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert BV 1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert BV 1.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Cluster 1 certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Sample-623, 631, 637, 630 Pasure Agreement.pdf31 Jul 2017

How this compares with Pune

71%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 120 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BOUGAIN VILLA - CLUSTER 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pasure13,700+ in Pune

2 kmBOUGAIN VILLA - CLUSTER Completed 6Lapsed / revoked 2Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: Synergy Properties

Synergy Properties has 11 registrations on MahaRERA, including BOUGAIN VILLA - CLUSTER 3 and CASUARINA - CLUSTER C AND D. Its filings disclose 8 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if BOUGAIN VILLA - CLUSTER 1 is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BOUGAIN VILLA - CLUSTER 1?

The registered promoter entity is Synergy Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BOUGAIN VILLA - CLUSTER 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BOUGAIN VILLA - CLUSTER 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BOUGAIN VILLA - CLUSTER 1?

The professionals named in the filing: Architect: GROUP PHI ARCHITECTS & DESIGNERS; Engineer: Pradeep Dongarwar; Chartered Accountant: Chandorkar & Limaye Chartered Accountants; Chartered Accountant: Maps and Company Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BOUGAIN VILLA - CLUSTER 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BOUGAIN VILLA - CLUSTER 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BOUGAIN VILLA - CLUSTER 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.