Completed No litigation declared Residential / Group Housing project

BORIVALI NEELKANTH NAGAR CHS LTD

By MAHAVIR INFRASTRUCTURE

RG-MH-19728 · RERA P51800006154 · Last updated on MahaRERA portal: 3 Feb 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 49 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 208 documents Report an error

BORIVALI NEELKANTH NAGAR CHS LTD is a Residential / Group Housing project by MAHAVIR INFRASTRUCTURE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006154 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Jan 2025. The completion date has moved by 49 months from the original filing.

At a glance

Project

  • NameBORIVALI NEELKANTH NAGAR CHS LTD
  • TypeResidential / Group Housing
  • Location
    • S.V. ROAD
    • BORIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006154
  • ReraGenie IDRG-MH-19728

Builder

  • NameMAHAVIR INFRASTRUCTURE
  • Entity typePartnership
  • PartnersHEENA RAJESH RUPERA, NISHANT RAJESH RUPERA, SHIRISH BHIKHALAL RUPERA

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toJan 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion30 Jan 2025
  • Revised completionRevised to 30 Jan 2025 (originally 31 Dec 2020)
  • Buildings1 building record
  • Documents filed208 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEELKANTH NAGAR CHS LTD WING BNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

NEELKANTH NAGAR CHS LTD WING B: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed145

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots145
Closed/Covered138
Open Space7

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,238 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
BORIVALI NEELKANTH NAGAR CHS LTDBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI5403.34
Proposed, not sanctioned3,704 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVALAYA APARTMENT CHANDAVARKAR ROAD BORIVALI WEST MUMBAI 400092

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINAYAK DESHPANDE
PartnerRole in project
MAHAVIR INFRASTRUCTURE-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005082Dec 2020 → Dec 2020

Reason as filed by the promoterMCGM

EXT51800008833Dec 2020 → Jun 2021

Reason as filed by the promoterDUE TO COVID AND NON AVAILABILITY OF LABOURS AND WORKERS

EXT51800010306Dec 2020 → Jun 2022

Reason as filed by the promoterdue to COVID pandemic and non-availability of labours

EXT51800013569Dec 2020 → Dec 2023

Reason as filed by the promoterBUILDING CONSTRUCTION OF THE SOCIETY IS ALREADY COMPLETED, HOWEVER, THE TOWER PARKING WORK OF THE SOCIETY IS GOING ON WHICH IS TO BE COMPLETED IN THE NEXT 3-4 MONTHS

EXT51800027462Dec 2020 → Jan 2025

Reason as filed by the promoterThe delay in the project had been caused due to car parking system - Skyzone Parking Systems Pvt. Ltd. who have failed to meet their installation schedules and delayed the project by almost 2 years. Now we have obtained Full O.C. and also Form 4 from the architect for project completion. Hence, we request you to kindly grant us extension till our O.C. Date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Jan 2025

Documents filed208

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 208 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3.pdf3 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From 2.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: Annexure A.pdf3 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf30 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Neelkanthnagar.pdf30 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Neelkant Nagar_OC_signed.pdf30 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf11 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf11 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf11 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf11 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf11 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf11 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf11 Nov 2024
Certificates of CA (Form 3)File: Form 3.pdf11 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Annexure A.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Annexure A.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Annexure A.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Annexure A.pdf11 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf11 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf11 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf11 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf11 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf30 May 2024
Details of encumbrancesFile: RERA Encumbrance - Mahavir Infrastructure .pdf17 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf19 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Neelkanth .pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: Annexure A.pdf29 Aug 2023
Certificates of CA (Form 3)File: Form 3.pdf29 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf14 Jul 2023
Declaration in FORM BFile: Form B.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 15.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 16.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 17.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 18.pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Inventory .pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: Annexure A .pdf26 Jun 2023
Disclosure of sold/ booked inventoryFile: Annexure A.pdf26 Jun 2023
Disclosure of sold/ booked inventoryFile: Annexure A 2.pdf26 Jun 2023
Disclosure of sold/ booked inventoryFile: Annexure A 3.pdf26 Jun 2023
Certificates of CA (Form 3)File: Form 3.pdf4 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf29 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf29 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A.pdf29 Apr 2023
Certificates of CA (Form 3)File: Form 3.pdf11 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf18 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf18 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf18 Jan 2023
Certificates of CA (Form 5)File: FORM 5.pdf18 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5.pdf18 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf18 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf11 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf11 Jan 2023
Certificates of CA (Form 3)File: Form 3.pdf11 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf21 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf21 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf21 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf7 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: annexure A.pdf7 Jul 2022
Certificates of CA (Form 3)File: form 3.pdf7 Jul 2022
Proforma of Allotment letterFile: Sale Agreement Format for Neelkanth Nagar.pdf23 Feb 2022
Details of encumbrancesFile: RERA Encumbrance Letter.pdf19 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf17 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf17 Feb 2022
Disclosure of sold/ booked inventoryFile: Annexure A.pdf17 Feb 2022
Certificates of CA (Form 3)File: Form 3.pdf17 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf23 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf23 Nov 2021
Disclosure of sold/ booked inventoryFile: annexure A.pdf23 Nov 2021
Certificates of CA (Form 3)File: FORM 3.pdf23 Nov 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 49 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BORIVALI NEELKANTH NAGAR CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI WEST6,700+ in Mumbai Suburban

2 kmBORIVALI NEELKANTH NAGARCompleted 159Lapsed / revoked 94Other 219Dot size: filed unitsN

Filed coordinates, straight-line distance. 472 registered projects within 2 km.

Builder: MAHAVIR INFRASTRUCTURE

MAHAVIR INFRASTRUCTURE has 1 registration on MahaRERA, including BORIVALI NEELKANTH NAGAR CHS LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if BORIVALI NEELKANTH NAGAR CHS LTD is delayed beyond 30 Jan 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BORIVALI NEELKANTH NAGAR CHS LTD?

The registered promoter entity is MAHAVIR INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BORIVALI NEELKANTH NAGAR CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BORIVALI NEELKANTH NAGAR CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BORIVALI NEELKANTH NAGAR CHS LTD?

The professionals named in the filing: Architect: VINAYAK DESHPANDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BORIVALI NEELKANTH NAGAR CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BORIVALI NEELKANTH NAGAR CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BORIVALI NEELKANTH NAGAR CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.