ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / BORIVALI KESAR KRIPA CHS LTD

Registered No litigation declared Residential / Group Housing project

BORIVALI KESAR KRIPA CHS LTD

By BORIVALI KESAR KRIPA CHS LTD

RG-MH-06860 · RERA P51800053824 · Last updated on MahaRERA portal: 15 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Basement (if any), 75%
26 of 39Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

BORIVALI KESAR KRIPA CHS LTD is a Residential / Group Housing project by BORIVALI KESAR KRIPA CHS LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053824 on 1 Dec 2023. Possession is promised by 31 Dec 2027. 13 of the 39 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameBORIVALI KESAR KRIPA CHS LTD
  • TypeResidential / Group Housing
  • Location
    • CHANDAVARKAR ROAD
    • BORIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800053824
  • ReraGenie IDRG-MH-06860

Builder

  • NameBORIVALI KESAR KRIPA CHS LTD
  • Entity typeSociety
  • SecretoryRAJENDRA KUMAR N DAMANI

Key dates

this monthRegisteredDec 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Dec 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed71 files

Current status

33%13 of 39 units booked
57.2%Work done, per cost certificate

Figures as on 15 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BORIVALI KESAR KRIPA CHSLNA22162339

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 75%.

BORIVALI KESAR KRIPA CHSL: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth100%
Stilt Floor20%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 15 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes35%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area914 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3081.45
Proposed, not sanctioned968 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBORIVALI WEST MUMBAI
Estimated costRs 19.17 cr
Cost incurredRs 10.96 cr
Work done57.16%
BuildingWingEstimatedIncurred
BORIVALI KESAR KRIPA CHSLNARs 17.73 crRs 10.96 cr
-NARs 1.44 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARSHAD MAANOHAAR MORE
EngineerABHIJIT PHATARPEKAR
EngineerHARSHAD MAANOHAAR MORE
Chartered AccountantR V B & Associates
Chartered AccountantA K O R D & CO Partner CA Dattatray Bhanage
Chartered AccountantDEEPAK S PAMECHA AND ASSOCIATES PROPRIETOR DEEPAK S PAMECHA
PartnerRole in project
BORIVALI KESAR KRIPA CHS LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 - RERA Format Q4.pdf15 May 2026
Withdrawal Update Form 1File: FORM 1 - RERA Format Q4.pdf15 May 2026
Withdrawal Update Form 2File: FORM 2 - RERA Format Q2.pdf15 May 2026
Withdrawal Update Form 2File: FORM 2 - RERA Format Q2.pdf15 May 2026
Withdrawal Update Form 3File: SCAN COPY FORM 3.pdf15 May 2026
Withdrawal Update Form 3File: SCAN COPY FORM 3.pdf15 May 2026
Withdrawal Update Form 1File: RERA FORM 1 FINAL.pdf10 Feb 2026
Withdrawal Update Form 2File: RERA FROM 2 FINAL.pdf10 Feb 2026
Withdrawal Update Form 3File: Borivali Kesar Kripa Form 3_11zon.pdf10 Feb 2026
Withdrawal Update Form 1File: FORM 1 Architechts certificate F.pdf27 Oct 2025
Withdrawal Update Form 2File: Form 2 Engineers certificate_Q2 2025 F.pdf27 Oct 2025
Withdrawal Update Form 3File: SCANNED Borivali Kesar Kripa Form_11zon.pdf27 Oct 2025
Form 5 (FY 2024-2025)File: Borivali Kesar kripa form 5 S.pdf30 Sep 2025
Withdrawal Update Form 1File: FORM 1_Q1-FY25-26_BORIVALI KESARKRIPA CHSL.pdf11 Aug 2025
Withdrawal Update Form 2File: FORM 2_Q1_FY25-26_BORIVALI KESARKRIPA CHSL.pdf11 Aug 2025
Withdrawal Update Form 3File: FORM 3_Q1_FY 25-26_BORIVALI KESARKRIPA CHSL.pdf11 Aug 2025
Withdrawal Update Form 1File: FORM 1_Q1-FY25-26_BORIVALI KESARKRIPA CHSL.pdf4 Aug 2025
Withdrawal Update Form 1File: FORM 1_Q1-FY25-26_BORIVALI KESARKRIPA CHSL.pdf4 Aug 2025
Withdrawal Update Form 2File: FORM 2_Q1_FY25-26_BORIVALI KESARKRIPA CHSL.pdf4 Aug 2025
Withdrawal Update Form 2File: FORM 2_Q1_FY25-26_BORIVALI KESARKRIPA CHSL.pdf4 Aug 2025
Withdrawal Update Form 3File: FORM 3_Q1_FY 25-26_BORIVALI KESARKRIPA CHSL.pdf4 Aug 2025
Withdrawal Update Form 3File: FORM 3_Q1_FY 25-26_BORIVALI KESARKRIPA CHSL.pdf4 Aug 2025
FORM 1 Architechts certificate Q1 2025_KESAR KRIPA29 Apr 2025
Form 2 Engineers certificate_Q1 202529 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Borivali Kesar Kripa Form 3 (10-04-2025).pdf25 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 2025-04-04_BKK_FurtherCC Upto 15TH Floor_signed.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architechts certificate Q4 2024_KESAR KRIPA.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate_Q4 2024.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Borivali Kesar Kripa Form 3 (10-01-2025 signed.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architechts certificate Q3 2024_KESAR KRIPA.pdf28 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 signed Borivali Kesar kripa_1_11zon.pdf28 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate_Q3 2024.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architechts certificate Q2 2024_KESAR KRUPA.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate_Q2 2024.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Borivali kesar karipa chsl.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 - BORIVALI KESAR KRIPA CHS LTD - SINGED - F.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architechts certificate 2024_KESAR KRUPA.pdf12 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate_ 2024.pdf12 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Borivali Kesarkripa_FORM 2A 2024.pdf12 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_11zon.pdf30 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Q4_2023_Borivali Kesarkripa.pdf1 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q4_2023_Borivali Kesarkripa.pdf1 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 SIGN.pdf31 Jan 2024
Declaration about Commencement CertificateFile: Delcration about CC.pdf23 Nov 2023
CERSAI detailsFile: Borivalli Kesar Kripa_ANNEXURE G-ASSET BASED DECLARATION - P - 1.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 1.pdf23 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Borivalli Kesar Kripa_Disclosure of Interest in Other Real Estate Organizations.pdf23 Oct 2023
Layout approvalFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_1.pdf9 Oct 2023
Building plan approvalFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_1.pdf9 Oct 2023
Building plan approvalFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_2.pdf9 Oct 2023
Building plan approvalFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_3.pdf9 Oct 2023
Building plan approvalFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_4.pdf9 Oct 2023
Building plan approvalFile: Borivali Kesar Kripa CHSL_IOD_signed.pdf9 Oct 2023
PAN CardFile: Society PAN Card.pdf9 Oct 2023
Copy of the legal title reportFile: Legal Title Report.pdf9 Oct 2023
Details of encumbrances concerned to FinanceFile: Declaration of Encumbrance.pdf9 Oct 2023
Details of encumbrances concerned to LegalFile: Declaration of Encumbrance.pdf9 Oct 2023
Copy of Layout Approval (in case of layout)File: Borivali Kesar Kripa CHSL_IOD Drawing_Page_1.pdf9 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_1.pdf9 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_2.pdf9 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_3.pdf9 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Borivali Kesar Kripa CHSL_IOD Drawing_Page_4.pdf9 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Borivali Kesar Kripa CHSL_IOD_signed.pdf9 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: 2023-09-29_Borivali Kesar Kripa CHSL_First CC.pdf9 Oct 2023
Declaration in FORM BFile: Borivali Kesar Kripa FORM B.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architechts certificate New Registration_KESAR KRUPA.pdf9 Oct 2023
Proforma of Agreement for saleFile: Agreement for Sale_RERA - BKK.pdf9 Oct 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER_ANNEXURE 1 - RERA.pdf9 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account Declaration_Format - A - 1.pdf9 Oct 2023
Deviation Report with respect to Allotment letterFile: No Deviation report_Allotment.pdf9 Oct 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation report_AFS.pdf9 Oct 2023

How this compares with Mumbai Suburban

33%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BORIVALI KESAR KRIPA CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI WEST6,700+ in Mumbai Suburban

2 kmBORIVALI KESAR KRIPA CHSCompleted 173Lapsed / revoked 100Other 235Dot size: filed unitsN

Filed coordinates, straight-line distance. 508 registered projects within 2 km.

Builder: BORIVALI KESAR KRIPA CHS LTD

BORIVALI KESAR KRIPA CHS LTD has 1 registration on MahaRERA, including BORIVALI KESAR KRIPA CHS LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if BORIVALI KESAR KRIPA CHS LTD is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BORIVALI KESAR KRIPA CHS LTD?

The registered promoter entity is BORIVALI KESAR KRIPA CHS LTD, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BORIVALI KESAR KRIPA CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BORIVALI KESAR KRIPA CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BORIVALI KESAR KRIPA CHS LTD?

The professionals named in the filing: Architect: HARSHAD MAANOHAAR MORE; Engineer: ABHIJIT PHATARPEKAR; Engineer: HARSHAD MAANOHAAR MORE; Chartered Accountant: R V B & Associates; Chartered Accountant: A K O R D & CO Partner CA Dattatray Bhanage; Chartered Accountant: DEEPAK S PAMECHA AND ASSOCIATES PROPRIETOR DEEPAK S PAMECHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BORIVALI KESAR KRIPA CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BORIVALI KESAR KRIPA CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BORIVALI KESAR KRIPA CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.