ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Blue Star CHSL

Completed No litigation declared Others project

Blue Star CHSL

By Thomas Joseph Vazhaparampil

RG-MH-99564 · RERA P51800045882 · Last updated on MahaRERA portal: 9 Apr 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2024Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Blue Star CHSL is a Others project by Thomas Joseph Vazhaparampil in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800045882 on 15 Jun 2022. The registration is recorded completed; possession was promised by 31 Mar 2024.

At a glance

Project

  • NameBlue Star CHSL
  • TypeOthers
  • Location
    • I C Colony Borivali West
    • Mumbai
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • RERA no.P51800045882
  • ReraGenie IDRG-MH-99564

Builder

  • NameThomas Joseph Vazhaparampil
  • Entity typeIndividual

Key dates

this monthRegisteredJun 2022PromisedMar 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jun 2022
  • Promised completion31 Mar 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Blue Star CHSLNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

Blue Star CHSL: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 9 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes80%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area667 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Blue Star CHSLBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1786.63
Proposed, not sanctioned1,787 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround and First Floor Esperanca Poly CHS Holy Cross Road I C Colony Borivali WEst

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRIKANT VICHARE & ASSOCIATES
EngineerG M PANDHI
Chartered AccountantHimani R Patel & Associates
PartnerRole in project
Thomas Joseph Vazhaparampil-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Apr 2024

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2023.pdf9 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2023.pdf9 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2023.pdf9 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 2023.pdf9 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2023.pdf9 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold of flats June 2023.pdf9 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold of flats Sept 2023.pdf9 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold of flats Dec 2023.pdf9 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2023.pdf9 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 2023.pdf9 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2023.pdf9 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate Blue Star.pdf9 Apr 2024
Architect’s Certificate on Completion of Project (Form 4)File: Fom 4 Architect Completion.pdf9 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance March 2023.pdf6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 for 22-23.pdf6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 for 21-22.pdf24 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure of Intersest.pdf6 Apr 2023
Deviation Report with respect to Allotment letterFile: No deviation letter for AL and AFS.pdf6 Apr 2023
Deviation Report with respect to model copy of AgreementFile: No deviation letter for AL and AFS.pdf6 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC 9th Floor.pdf5 Apr 2023
Declaration about Commencement CertificateFile: Declaration about CC Letter head.pdf5 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate Maha RERA upto Dec 2022.pdf5 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate March 2023.pdf5 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance March 2023.pdf5 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate March 2023.pdf5 Apr 2023
Proforma of Agreement for saleFile: Draft Agreement.pdf5 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf9 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2 A.pdf9 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf6 Oct 2022
Declaration about Commencement CertificateFile: Declaration about CC.pdf6 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Cost Incurred.pdf6 Oct 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Booked and Sold Flats.pdf6 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate account details.pdf6 Oct 2022
Copy of the legal title reportFile: Title Report Format A.pdf9 Jun 2022
Proforma of Allotment letterFile: Allotment Letter (Divine LH).pdf7 Jun 2022
Proforma of Allotment letterFile: RERA Agreement Draft .pdf7 Jun 2022
Layout approvalFile: Building Plan 1.pdf6 Jun 2022
Building plan approvalFile: Building Plan 1.pdf6 Jun 2022
Building plan approvalFile: Building Plan 2.pdf6 Jun 2022
Building plan approvalFile: Building Plan 3.pdf6 Jun 2022
Building plan approvalFile: Building Plan 4.pdf6 Jun 2022
PAN CardFile: Fast color scan to a PDF file_30.PDF6 Jun 2022
Details of encumbrancesFile: No Encumbrances Letter DB.pdf6 Jun 2022
Copy of Layout Approval (in case of layout)File: Building Plan 1.pdf6 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf6 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf6 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 3.pdf6 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf6 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: 2320670_FirstCC_signed.pdf6 Jun 2022
Declaration about Commencement CertificateFile: Declaration about CC on letter head DB-converted.pdf6 Jun 2022
Declaration in FORM BFile: Affidavit Divine.pdf6 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf6 Jun 2022
CERSAI detailsFile: CERSAI REPORT.pdf6 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf6 Jun 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Blue Star CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai6,700+ in Mumbai Suburban

Builder: Thomas Joseph Vazhaparampil

Thomas Joseph Vazhaparampil has 1 registration on MahaRERA, including Blue Star CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Blue Star CHSL is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Blue Star CHSL?

The registered promoter entity is Thomas Joseph Vazhaparampil, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Blue Star CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Blue Star CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Blue Star CHSL?

The professionals named in the filing: Architect: SHRIKANT VICHARE & ASSOCIATES; Engineer: G M PANDHI; Chartered Accountant: Himani R Patel & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Blue Star CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Blue Star CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Blue Star CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.