Home / Browse projects / Palghar, Maharashtra / BLU PEARL
BLU PEARL
RG-MH-25036 · RERA P99000008670 · Last updated on MahaRERA portal: 11 Oct 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 24 months past the filed date
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BLU PEARL is a Others project by SB LIFESPACES PVT LTD in Palghar, Maharashtra, registered with MahaRERA as P99000008670 on 19 Aug 2017. Possession was promised by 3 Oct 2024 and is now 24 months past that date. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameBLU PEARL
- TypeOthers
- Location
- Chikaldongre
- Virar
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401303
- Pincode401303
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000008670
- ReraGenie IDRG-MH-25036
Builder
- NameSB LIFESPACES PVT LTD
- Entity typeCompany
- Managing DirectorKIRIT WADHWANA
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion3 Oct 2024
- Revised completionRevised to 3 Oct 2024 (originally 4 Oct 2022)
- Buildings6 building records
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLDG NO 2 WING B | NA | 17 | 0 | 0 | 0 | 0 |
| BLDG NO 3 WING C | NA | 17 | 0 | 0 | 0 | 0 |
| BLDG NO 2 A WING D | NA | 17 | 0 | 0 | 0 | 0 |
| BLDG NO 4 WING E | NA | 17 | 0 | 0 | 0 | 0 |
| YK2 | NA | 16 | 0 | 0 | 0 | 0 |
| BLDG NO 1 WING A | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 11 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
66 of 66 construction stages are filed complete across 6 buildings.
BLDG NO 2 WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 3 WING C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 2 A WING D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 4 WING E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
YK2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BLDG NO 1 WING A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 95% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 5% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed61
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BLDG NO 2 WING B | 7 | 5 | 12 |
| BLDG NO 3 WING C | 2 | 5 | 7 |
| BLDG NO 2 A WING D | 2 | 5 | 7 |
| BLDG NO 4 WING E | 5 | 5 | 10 |
| YK2 | 6 | 5 | 11 |
| BLDG NO 1 WING A | 9 | 5 | 14 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHAH GATTANI CONSULTANTS |
| Chartered Accountant | NEHALI & CO |
| Partner | Role in project |
|---|---|
| SB LIFESPACES PVT LTD | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to covid-l9 the work at site came to a grinding halt and post which mobilisation of works took time and there was a delay in supply of construction raw material as well due to which the project was not able to get completed in time. The project is 90% complete. we would like to request you to further grant un extension till 03/10/2023
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 03-10-2024
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Mar 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 11 Oct 2024
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Decalration for OC.pdf | 11 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Blu Pearl.pdf | 11 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Blu Pearl.pdf | 11 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Decalration for OC.pdf | 11 Oct 2024 |
| Certificates of CA (Form 3)File: 4 Project Information.pdf | 26 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 23 Q3.pdf | 26 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 23 Q4.pdf | 26 Feb 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Blu pearl OC.pdf | 19 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 June 23.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 June 23.pdf | 30 Dec 2023 |
| Declaration in FORM BFile: Form B.PDF | 10 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A March 23.pdf | 10 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Form 5 23.pdf | 10 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory March 23.pdf | 10 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 23.pdf | 10 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 23.pdf | 7 Nov 2023 |
| Certificates of CA (Form 3)File: Blu Pearl Form 3 march 23 (1).pdf | 26 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 21-22.pdf | 9 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - 21-22.pdf | 6 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 21-22.PDF | 6 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2a 21-22.pdf | 6 Mar 2023 |
| Details of encumbrancesFile: Encumberance ABFL.pdf | 29 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - 21-22.pdf | 8 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1.PDF | 7 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2a 20-21.PDF | 7 Jun 2022 |
| CERSAI detailsFile: Cersai declaration.PDF | 7 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure_compressed.pdf | 7 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 20-21.pdf | 7 Jun 2022 |
| PAN CardFile: Sb pan card.pdf | 15 Mar 2022 |
| Declaration about Commencement CertificateFile: cc letter.PDF | 15 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: from 2A 19-20.PDF | 15 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 (FY 2019-20) -BLU PEARL.pdf | 29 Mar 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA_CERTIFICATE.pdf | 1 Feb 2020 |
| OtherFile: p01.pdf | 25 Oct 2018 |
| OtherFile: p02.pdf | 25 Oct 2018 |
| Certificates of CA (Form 5)File: BLU PEARL.pdf | 14 Oct 2018 |
| Details of encumbrancesFile: Scan1.PDF | 19 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate form - 1.PDF | 31 Mar 2018 |
| Certificates of CA (Form 3)File: img-331203904.pdf | 31 Mar 2018 |
| Layout approvalFile: MYSCAN_20180327_0005 (2)-ilovepdf-compressed.pdf | 29 Mar 2018 |
| Building plan approvalFile: MYSCAN_20180327_0001.pdf | 29 Mar 2018 |
| Building plan approvalFile: MYSCAN_20180327_0002.pdf | 29 Mar 2018 |
| Building plan approvalFile: MYSCAN_20180327_0003.pdf | 29 Mar 2018 |
| Building plan approvalFile: MYSCAN_20180327_0004.pdf | 29 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20180327_0005 (2)-ilovepdf-compressed.pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: MYSCAN_20180327_0001.pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: MYSCAN_20180327_0002.pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: MYSCAN_20180327_0003.pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: MYSCAN_20180327_0004.pdf | 29 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: BLU PEARL CC.PDF | 26 Mar 2018 |
| Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.PDF | 30 Jul 2017 |
| Layout approvalFile: Layout.pdf | 29 Jul 2017 |
| Building plan approvalFile: MYSCAN_20170727_0001.pdf | 29 Jul 2017 |
| Building plan approvalFile: MYSCAN_20170727_0002.pdf | 29 Jul 2017 |
| Building plan approvalFile: MYSCAN_20170727_0003.pdf | 29 Jul 2017 |
| Building plan approvalFile: MYSCAN_20170727_0004.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: BLU PEARL TITLE CERTIFICATE-ilovepdf-compressed.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: ENCUMBRANCE.PDF | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: MYSCAN_20170727_0001.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: MYSCAN_20170727_0002.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: MYSCAN_20170727_0003.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: MYSCAN_20170727_0004.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: BLU PEARL - FORM B [AFFIDAVIT CUM DECLARATION].PDF | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.PDF | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 ENGINEERS CERTIFICATE.PDF | 29 Jul 2017 |
| Proforma of Allotment letterFile: allotment and agreement for sale-ilovepdf-compressed.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep BLU PEARL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Virar3,200+ in Palghar
Filed coordinates, straight-line distance. 165 registered projects within 2 km.
Mayfair Virar Gardens Cluster-VI
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS CLUSTER IV
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19,
MAYFAIR HOUSING
Agarwal Infinity
Laxminarayan Prabhudayal Agarwal
GOKUL HARI ANANTA
Mehta Ventures
GOKUL NAKSHATRA II
JSB HOMEMAKERS PRIVATE LIMITED
See every Palghar project, with the district possession charts
Builder: SB LIFESPACES PVT LTD
SB LIFESPACES PVT LTD has 2 registrations on MahaRERA, including BLU PEARL and SANDEEP HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that BLU PEARL shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if BLU PEARL is delayed beyond 3 Oct 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BLU PEARL?
The registered promoter entity is SB LIFESPACES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BLU PEARL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BLU PEARL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BLU PEARL?
The professionals named in the filing: Architect: SHAH GATTANI CONSULTANTS; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BLU PEARL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback