Red flags
- Rs 3.00 crore secured on the land, in favour of The Ashta People co op bank limited Ashta
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
BHOSALE EMPIRE is a Others project by BHOSALE DEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100053023 on 10 Oct 2023. The registration is recorded completed; possession was promised by 31 May 2026. 11 of the 47 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameBHOSALE EMPIRE
- TypeOthers
- Location
- S T STAND ROAD NEAR MODERN BAKERY GAONBHAG SANGLI
- DINANATH CHOWK
- Miraj
- Sangli
- 416416
- Pincode416416
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100053023
- ReraGenie IDRG-MH-85333
Builder
- NameBHOSALE DEVELOPERS
- Entity typePartnership
- Partnersyogesh sambhaji bhosale, SACHIN ANANDRAO BHOSALE
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on10 Oct 2023
- Promised completion31 May 2026
- Revised completionNone
- Buildings1 building record
- Documents filed86 files
Current status
Figures as on 26 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BHOSALE EMPIRE | NA | 7 | 6 | 33 | 14 | 47 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
BHOSALE EMPIRE: 71% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed52
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership6
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| SACHIN ANANDRAO BHOSALE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| yogesh sambhaji bhosale | Sangli Miraj Kupwad (M Corp.) | Sangli |
| MANOJ SHAHAJI BHOSALE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| SNEHAL SACHIN BHOSALE | Sangli Miraj Kupwad (M Corp.) | Sangli |
| amruta yogesh bhosale | Sangli Miraj Kupwad (M Corp.) | Sangli |
| PRAJWAL MAHESH CHAVAN | Sangli Miraj Kupwad (M Corp.) | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BHOSALE EMPIRE | NA | Rs 3.40 cr | Rs 3.40 cr |
| - | NA | Rs 25.00 lakh | Rs 25.00 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RUSHIKESH D PAWAR |
| Engineer | vikas laxman more |
| Chartered Accountant | amit anil shende |
| Chartered Accountant | MAHESH V THANEDAR |
| Partner | Role in project |
|---|---|
| BHOSALE DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jun 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Dec 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed86
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: FULL OC CERTIFICATE BHOSALE EMPIRE.pdf | 26 May 2026 |
| Occupational CertificateFile: Bhosale Empire Full OC Rera email.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: FORM-1 31-03-26 .pdf | 25 May 2026 |
| Withdrawal Update Form 2File: FORM-2 31-03-26.pdf | 25 May 2026 |
| Withdrawal Update Form 3File: FORM-3 31-03-26 .pdf | 25 May 2026 |
| Form 2A (FY 2025-2026)File: FORM-2A 31-03-26 .pdf | 25 May 2026 |
| Form 5 (FY 2025-2026)File: FORM-5 31-03-26 .pdf | 23 May 2026 |
| Withdrawal Update Form 1File: Form 1 31-12-2025.pdf | 12 May 2026 |
| Withdrawal Update Form 1File: Form 1 31-12-2025.pdf | 12 May 2026 |
| Withdrawal Update Form 2File: Form 2 31-12-2025.pdf | 12 May 2026 |
| Withdrawal Update Form 2File: Form 2 31-12-2025.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: Form 2 31-12-2025.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: Form 3 31-12-2025.pdf | 12 May 2026 |
| Form 2A (FY 2024-2025)File: FORM -2A 24-25.pdf | 27 Dec 2025 |
| Building plan approvalFile: BHOSALE EMPIRE REVISED SANCTION DRAWING.pdf | 24 Dec 2025 |
| Form 5 (FY 2024-2025)File: FORM-5 24-25.pdf | 17 Dec 2025 |
| Withdrawal Update Form 1File: FORM-1 (Bhosle Empire) 30-9-25.pdf | 12 Dec 2025 |
| Withdrawal Update Form 2File: FORM-2 (Bhosle Empire) 30-9-25.pdf | 12 Dec 2025 |
| Withdrawal Update Form 3File: FORM-3 (Bhosle Empire) 30-9-25.pdf | 12 Dec 2025 |
| Withdrawal Update Form 1File: FORM-1 29-7-25 (BHOSLE EMPIRE).pdf | 10 Oct 2025 |
| Withdrawal Update Form 2File: FORM-2 01-8-25 (BHOSLE EMPIRE).pdf | 10 Oct 2025 |
| Withdrawal Update Form 3File: FORM-3 02-8-25 (BHOSLE EMPIRE).pdf | 10 Oct 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 upto 31032025 with sign.pdf | 3 Jun 2025 |
| Withdrawal Update Form 2File: FORM -2.pdf | 3 Jun 2025 |
| Withdrawal Update Form 3File: FORM-3 (2).pdf | 3 Jun 2025 |
| Form 1File: FORM-1.pdf | 5 May 2025 |
| Form 2File: FORM-2.pdf | 5 May 2025 |
| Form 3File: FORM-3.pdf | 5 May 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 31-12-24.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 31-12-24.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 31-12-24.pdf | 21 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 10 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 10 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5 12-11-24 .pdf | 10 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2.pdf | 23 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2A.pdf | 23 May 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSUR OF SOLD.pdf | 23 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 23 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 27 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2.pdf | 27 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: DISLOSURE OF SOLD.pdf | 27 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3.pdf | 27 Jan 2024 |
| Other - FinanceFile: DAST.pdf | 27 Jan 2024 |
| Other - TechnicalFile: Bhosale empire cc verification email NEW.pdf | 2 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE AERTIFICATE.pdf | 7 Jul 2023 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE AERTIFICATE.pdf | 7 Jul 2023 |
| Other - LegalFile: DEVELOPMENT AGREEMENT.pdf | 20 Jun 2023 |
| Other - LegalFile: POWER OF ATTORNY_BHOSALE FAMILY.pdf | 20 Jun 2023 |
| Other - LegalFile: DEVELOPMENT AGREEMENT - PRAJWAL CHAVAN.pdf | 20 Jun 2023 |
| Other - LegalFile: KULMUKHTYARPATRA PRAJWAL CHAVAN.pdf | 20 Jun 2023 |
| Other - LegalFile: KHAREDIPATRA.pdf | 20 Jun 2023 |
| Layout approvalFile: AMALGAMATION DWG.pdf | 19 Jun 2023 |
| Building plan approvalFile: MUN DWG.pdf | 19 Jun 2023 |
| PAN CardFile: PAN CARD - BHOSALE DEV.pdf | 19 Jun 2023 |
| Copy of the legal title reportFile: SEARCH REPORT.pdf | 19 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE - LEGAL.pdf | 19 Jun 2023 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE - LEGAL.pdf | 19 Jun 2023 |
| Copy of Layout Approval (in case of layout)File: AMALGAMATION DWG.pdf | 19 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: MUN DWG.pdf | 19 Jun 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION CERTIFICATE.pdf | 19 Jun 2023 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE2_compressed.pdf | 19 Jun 2023 |
| Declaration in FORM BFile: FORM B.pdf | 19 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 19 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEERS CERTIFICATE.pdf | 19 Jun 2023 |
| CERSAI detailsFile: UNDERTAKING.pdf | 19 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE form 3 LATEST_compressed.pdf | 19 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTREST IN OTHER REAL ESTATE ORG - YOGESH BHOSALE.pdf | 19 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTREST IN OTHER REAL ESTATE ORG 0- MANOJ BHOSALE.pdf | 19 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 86 filed documents as one ZIP, foldered, with a manifest
Keep BHOSALE EMPIRE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DINANATH CHOWK790+ in Sangli
Filed coordinates, straight-line distance. 53 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
EVARA ESTATE
DSDB REALTY LLP
VISION CITY
VISION GROUP
NAKSHTRA
SHIV-NAKSHTRA DEVELOPERS LLP
SAHYADRISIDDHI
SAHYADRIDEVELOPERS
See every Sangli project, with the district possession charts
Builder: BHOSALE DEVELOPERS
BHOSALE DEVELOPERS has 1 registration on MahaRERA, including BHOSALE EMPIRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What are my rights if BHOSALE EMPIRE is delayed beyond 31 May 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of BHOSALE EMPIRE?
The registered promoter entity is BHOSALE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in BHOSALE EMPIRE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for BHOSALE EMPIRE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at BHOSALE EMPIRE?
The professionals named in the filing: Architect: RUSHIKESH D PAWAR; Engineer: vikas laxman more; Chartered Accountant: amit anil shende; Chartered Accountant: MAHESH V THANEDAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in BHOSALE EMPIRE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback