ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / Bhoomi's Nikunj

Registration approved Residential/Group Housing project

Bhoomi's Nikunj

By Bhoomi Groups

RG-KA-60343 · RERA PRM/KA/RERA/1257/334/PR/220523/004892 · Last updated on RERA Karnataka portal: 7 May 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Apr 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 102 documents Report an error

Bhoomi's Nikunj is a Residential/Group Housing project by Bhoomi Groups in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/220523/004892 on 23 May 2022. Possession is promised by 1 Apr 2023.

At a glance

Project

  • NameBhoomi's Nikunj
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/220523/004892
  • ReraGenie IDRG-KA-60343

Builder

  • NameBhoomi Groups
  • Entity typePartnership Firm
  • Authorized SignatorySHANKARNARAYANA KOTIAN
  • OthersMURALIDHARA, SHANKARNARAYANA KOTIAN, MADHUKAR B
  • Other registrations3 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredMay 2022PromisedApr 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 May 2022
  • Promised completion1 Apr 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed102 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHOOMIS KRISHNAKUNJ---14014

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 7 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 7 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area607 sq m
Named landowners2
LandownerVillageDistrict
BHOOMI GROUPS--
Mrs.Lekha Rao & others--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.05 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMadhukar B
EngineerH.Anand Bhat

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed102

As listed on the registration, under the names the promoter filed them with; the newest 80 of 102 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/220523/004892 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
AFFIDAVIT FOR NON COLLECTION OF FUNDS FROM ALLOTTEEFile: AFFIDAVIT FOR NON COLLECTION OF FUNDS.pdf7 May 2022
REQUEST LETTER FROM THE DEVELOPERSFile: Approval for project -nk.PDF7 May 2022
C A CERTIFICATEFile: CA -Certificate.PDF7 May 2022
NOC issued by Water supply AuthorityFile: NOC WATER.PDF6 Apr 2022
NOC Issued by Power supply AuthorityFile: NOC MESCOM WITH RECEIPT.pdf6 Apr 2022
1. NOC issued by Water Supply and Power Supply AuthoritiesFile: NOC issued by water supply and power supply authorities.pdf16 Aug 2021
2.Section 3(1) Notarized AffidavitFile: AFFIDAVITH 3(1).pdf16 Aug 2021
3. Approved Building /Plotting PlanFile: 12.pdf16 Aug 2021
1.UPLOADED CORRECT DRAWING OF THE PROJECT (BASEMENT+GF+4UPPERFLOORS)File: Building drawings 23-07-2021 new.pdf4 Aug 2021
FINANCIAL STATEMENT BALANCESHEET 2017-18File: 2017-18.pdf27 Jul 2021
INCOME TAX RETURN ACKNOWLEDGEMENTFile: 2017-18.pdf27 Jul 2021
AUDITED PROFIT & LOSS A/CFile: 2017-18.pdf27 Jul 2021
AUDIT REPORTFile: 2017-18.pdf27 Jul 2021
BHOOMI GROUPS RERA DESIGNATED ACCOUNT FOR BHOOMI'S NIKUNJ-RERA COLLECTION A/C 037721010000006File: IMG-20210727-WA0006.pdf27 Jul 2021
BHOOMI GROUPS RERA DESIGNATED ACCOUNT FOR BHOOMI'S NIKUNJ -037721010000007 RERA PROJECT ACCOUNTFile: IMG-20210727-WA0007.pdf27 Jul 2021
BHOOMI GROUPS RERA DESIGNATED ACCOUNT FOR BHOOMI'S NIKUNJ -037721010000008 RERA OPERATIVE ACCOUNT TFile: BANK ACCOUNT 0008.pdf27 Jul 2021
KATA SERIAL NO:1360265File: Khatha.pdf27 Jul 2021
TITLE DEED KISHORE KUMAR TO LEKHA K RAOFile: TITLE DEED.PDF27 Jul 2021
BUILDING DRAWINGSFile: Building drawings 23-07-2021.pdf27 Jul 2021
NOC ISSUED FROM WATER SUPPLY & POWER SUPPLY ARE NOT APPLICABLE IN MANGALORE MUDAFile: 1.pdf27 Jul 2021
PROJECT ON GOING STATUS : FOUNDATION STAGEFile: IMG-20210122-WA0013.jpg27 Jul 2021
FIRE FORCE NOCFile: FIRE NOC.pdf27 Jul 2021
CertificateFile: CERTIFICATE OF REGISTRATION OF FIRM.pdf-
Commencement certificate or building (2)-
Approved Building plan-
Approved layout plan or Single site plan-
Proforma of sale deed-
Proforma of agreement for sale-
Sale deed & RTC-
APROVED SECTION OF BUILDING-
AREA DEVELOPMENT PLAN-
PROFORMA OF ALLOTMENT LETTER_page-0001-
Brochure of current project-
Project Specification-
EC-
NOTARIZED AFFIDAVIT-
JD AFFIDAVIT-
Khatha-
Joint developement agreement-
Any other documents-
Conversion certificate under sec95-
ApprovalNOC under sec 14 of KTCP A ct_page-0001 - Copy - Copy-
Utilization certificate-
Transfer of development rights certificate-
RELIQUISHMENT DEED-
Unnamed document-
Airport Authority of India NOC_page-0001 - Copy - Copy-
BESCOM NOC_-
BWSSB NOC-
KSPCB NOC-
SEIAA NOC-
BSNL NOC-
NOC in case of building proposals abutting to neighbouring properties_page-0001-
Unnamed document-
URBAN LAND CEILING NOC-
BMRCL NOC-
BANGALORE URBAN ARTS COMMISSION_page-0001 - Copy-
ISPECTOR OF FACTORIES CONTROLLER OF EXPLOSIVES RAILWAYS-
DISTRICT MAGISTRATE-
COASTALREGULATION ZONE AUTHORITY_page-0001-
Structural safety of the building-
SECTIONAL DRAWING OF THE APPARTMENT-
EXISTING LAYOUT PLAN-
EXISTING SECTION PLAN AND SPECIFICATION-
CHANGE OF LAND USE-
legal opinion NIKUNJ-
Balance Sheet 2019 - 2020File: Balacesheet 2020-21.pdf-
Balance Sheet 2018 - 2019File: 2019-20.pdf-
Balance Sheet 2017 - 2018File: 2018-19.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P&L 2020-21.pdf-
Audited Profit and Loss Statement 2018 - 2019File: 2019-20.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P&L 2018-19.PDF-
Director's Report 2019 - 2020File: DIRECTOR REPORT.pdf-
Director's Report 2018 - 2019File: DIRECTOR REPORT.pdf-
Director's Report 2017 - 2018File: DIRECTOR REPORT.pdf-
Cash Flow Statement 2019 - 2020File: CASH FLOW.jpg-
Cash Flow Statement 2018 - 2019File: CASH FLOW.jpg-
Auditor's Report 2019 - 2020File: Audit Report 2020-21.pdf-
Auditor's Report 2018 - 2019File: AUDIT REPORT 2019-20.pdf-
Auditor's Report 2017 - 2018File: Bhoomi Form F3CB-3CD_Filed Form.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Bhoomi's Samruddhi-Completed-No date filed
Bhoomi's SAMSKRUTHI-Completed-No date filed

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Bhoomi's Nikunj on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmBhoomi's NikunjOther 67Dot size: filed unitsN

Filed coordinates, straight-line distance. 67 registered projects within 2 km.

Builder: Bhoomi Groups

Bhoomi Groups has 4 registrations on RERA Karnataka, including Bhoomi's Samruddhi and Bhoomi's Samskruthi. Its filings declare 3 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Bhoomi's Nikunj is delayed beyond 1 Apr 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Bhoomi's Nikunj?

The registered promoter entity is Bhoomi Groups, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Bhoomi's Nikunj?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Bhoomi's Nikunj?

The professionals named in the filing: Architect: Madhukar B; Engineer: H.Anand Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhoomi's Nikunj?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhoomi's Nikunj. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhoomi's Nikunj to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.