ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / BHIMASHANKAR

Completed No litigation declared Residential / Group Housing project

BHIMASHANKAR

By MADHHU DAULATRAO PATIL

RG-MH-24633 · RERA P52000011874 · Last updated on MahaRERA portal: 31 Mar 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 4 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Internal walls, 70%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

BHIMASHANKAR is a Residential / Group Housing project by MADHHU DAULATRAO PATIL in Raigarh, Maharashtra, registered with MahaRERA as P52000011874 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019.

At a glance

Project

  • NameBHIMASHANKAR
  • TypeResidential / Group Housing
  • Location
    • Taloje Panchnad
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000011874
  • ReraGenie IDRG-MH-24633

Builder

  • NameMADHHU DAULATRAO PATIL
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017PromisedDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHIMASHANKARNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 70%.

BHIMASHANKAR: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1649.7
Proposed, not sanctioned1,650 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 20 AND 21 RAHUL APT PLOT NO E 125 SECTOR 12 KHARGHAR TALUKA PANVEL DISTT RAIGAD 410210

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISTAAR ARCHITECTS AND PLANERS
EngineerSTRUCTURAL CONCEPT DESIGNS PVT LTD
PartnerRole in project
MADHHU DAULATRAO PATIL-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5-Annual Report-Madhuraj-Bhimashankar-2019-20.pdf31 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY18-19-Bhimashankar.pdf30 Mar 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM - 4 -ARCHITECT CERTIFICATE.pdf13 Aug 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE OF ARCHITECT (Form 1).pdf21 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE (Form 1).pdf30 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE (Form 2).pdf30 Nov 2019
Certificates of CA (Form 5)File: Form 5 FY18-19-Bhimashankar.pdf30 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE OF ARCHITECT (Form1).PDF16 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATE OF ENGINEERS (Form2).PDF16 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE OF ARCHITECT (Form 1).PDF19 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE OF ARCHITECT (Form 1).PDF19 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE OF ARCHITECT (Form 1).PDF19 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATE OF ENGINEER (Form 2).PDF19 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATE OF ENGINEERS (Form 2).PDF19 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CERTIFICATE OF ENGINEER (Form 2).PDF19 Apr 2019
Certificates of CA (Form 5)File: Form-5-Nageshwar-2017-18.pdf30 Sep 2018
Certificates of CA (Form 5)File: Form-5-Bhimashankar-2017-18.pdf30 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.PDF14 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.PDF13 Apr 2018
Layout approvalFile: Plan-2.pdf27 Jul 2017
Layout approvalFile: Plan-3.pdf27 Jul 2017
Layout approvalFile: Plan-1.pdf27 Jul 2017
Layout approvalFile: Plan-4.pdf27 Jul 2017
Building plan approvalFile: Commencement Certificate.pdf27 Jul 2017
PAN CardFile: Madhu Patil PAN.pdf27 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf27 Jul 2017
Details of encumbrancesFile: Encumbrances.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan-1.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan-2.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan-3.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan-4.pdf27 Jul 2017
Building Plan Approval (IOD)File: Commencement Certificate.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf27 Jul 2017
Declaration in FORM BFile: Form-B-Bhimashankar-Developers.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1-ARCHITECTS CERTIFICATE.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-ENGINEERS CERTIFICATE.pdf27 Jul 2017
Certificates of CA (Form 3)File: Form-3-CA Certificate-Bhimashankar.pdf27 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER AND AGREEMENT TO SELL - MADHURAAJ BHIMASHANKAR.pdf27 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SOMESHWARPLOT NO 21 SECTOR 2 TALOJE PANCHANAND PHASE I TALUKA PANVEL DISTT RAIGAD 41020849CompletedDec 2016Sep 2016
KAPALESHWARPLOT NO 15 SECTOR 26 TALOJE PANCHANAND PHASE II TALUKA PANVEL DISTT RAIGAD 41020858CompletedDec 2016Oct 2016
NANDISHWARPLOT NO 94 SECTOR 10 TALOJE PANCHANAND TAULKA PANVEL DISTT RAIGAD 41020827CompletedMay 2015Mar 2015
GANGESHWARPLOT NO 69 SECTOR 27 KHARGHAR TALUKA PANVEL DISTT RAIGAD 41021022CompletedDec 2014Sep 2014

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHIMASHANKAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Taloje Panchnad5,900+ in Raigarh

2 kmBHIMASHANKARCompleted 53Lapsed / revoked 13Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 92 registered projects within 2 km.

Builder: MADHHU DAULATRAO PATIL

MADHHU DAULATRAO PATIL has 2 registrations on MahaRERA, including BHIMASHANKAR and NAGESHWAR. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if BHIMASHANKAR is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHIMASHANKAR?

The registered promoter entity is MADHHU DAULATRAO PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHIMASHANKAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHIMASHANKAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHIMASHANKAR?

The professionals named in the filing: Architect: VISTAAR ARCHITECTS AND PLANERS; Engineer: STRUCTURAL CONCEPT DESIGNS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHIMASHANKAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHIMASHANKAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHIMASHANKAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.